How it entered the Observatory
The saved starting points
- Earliest file on subject
- Date
- 2026-07-25
- File
- Federal Government Website Sweep 2026-07-25/Domestic Systems Wave 7/DOMESTIC_SYSTEMS_WAVE_7_PRIMARY_OBJECT_LEDGER.md
- Note
- A related file, not one of the thread's 18. Its 'DOE §202(c) emergency-order cluster' paragraph lists the July orders (202-26-32A, -33A, -34, -35, -36).
- Earliest thread file
- Date
- 2026-08-04
- File
- Federal Government Whole-Site Recertification 2026-08-01/Physical Production Systems Full-Surface Wave 2026-08-04/PHYSICAL_PRODUCTION_SYSTEMS_FULL_SURFACE_WAVE_2026-08-04.md
- Note
- The Southwest Power Pool extension (202-26-37A) and its same-day correction.
- Requests
- Id
- K02-020
- When
- 2026-07-25 21:41 UTC
- Subject
- Full federal government website sweep
- Her words
- I want this to be comprehensive FULL sweep, not a blanket of forced brevity.
- Why
- It had been a while since the last sweep.
- Why quote
- We haven't done a real 'government website sweep' in a bit - I'm thinking we should!!
- Package
- Federal Government Website Sweep 2026-07-25
- Id
- K03-003
- When
- 2026-08-04 18:29 UTC
- Subject
- Continue the government-wide audit in waves (Education, physical production, infrastructure, national command/defense/intelligence, justice/homeland, Congress)
- Her words
- Want to continue the government wide audit to see if anything else interesting has happened over the past few days?
- Why
- Things were moving fast and she wanted full coverage.
- Why quote
- Things are starting to move fast so deep dives are needed to even catch everything going on!!
- Package
- Federal Government Whole-Site Recertification 2026-08-01
- Note
- No recorded request names section 202(c), DOE emergency orders or any of the plants. The subject came in through Katie's government-wide website sweeps and was carried in each later weekly sweep.
The dated steps
2025-04-08The President signed Executive Order 14262, 'Strengthening the Reliability and Security of the United States Electric Grid'.
The President signed Executive Order 14262, 'Strengthening the Reliability and Security of the United States Electric Grid'. It directs the Secretary of Energy to streamline, systemize and expedite DOE's processes for issuing section 202(c) orders during periods when a grid operator forecasts a temporary interruption of supply, to develop within 30 days a uniform method for analyzing regional reserve margins (published within 90 days), and to set a protocol that uses all available mechanisms, including section 202(c), to keep generation identified as critical in at-risk regions and, as the Secretary deems appropriate, to prevent a generating resource over 50 megawatts from leaving the bulk-power system.
Who acted: The President (Donald Trump), Executive Order 14262
Stage: signed or enacted
shall, to the maximum extent permitted by law, streamline, systemize, and expedite the Department of Energy's processes for issuing orders under section 202(c) of the Federal Power Act
2026-07-02Order 202-26-32A, a 'specified-unit' order, ran July 2-6.
Order 202-26-32A, a 'specified-unit' order, ran July 2-6. The file does not say which grid operator, utility or plant it was addressed to. The files do not describe an earlier order 202-26-32.
Who acted: Department of Energy (order 202-26-32A; the file does not name the addressee)
Stage: took effect
specified-unit 202-26-32A ran Jul 2–6
2026-07-02Order 202-26-34 ran July 2-6 and authorized maximum output from Duke units notwithstanding specified permit limitations.
Order 202-26-34 ran July 2-6 and authorized maximum output from Duke units notwithstanding specified permit limitations.
Who acted: Department of Energy (order 202-26-34, addressed to 'Duke'; the file does not give the exact Duke legal entity)
Stage: took effect
Duke 202-26-34 ran Jul 2–6 and authorized maximum output notwithstanding specified permit limitations
2026-07-03Order 202-26-33A, a PJM backup-generation order, ran July 3-7.
Order 202-26-33A, a PJM backup-generation order, ran July 3-7. The files do not describe an earlier order 202-26-33.
Who acted: Department of Energy (order 202-26-33A, addressed to PJM)
Stage: took effect
PJM backup-generation 202-26-33A ran Jul 3–7
2026-07-14Order 202-26-35 for PJM ran July 14-21.
Order 202-26-35 for PJM ran July 14-21.
Who acted: Department of Energy (order 202-26-35, addressed to PJM)
Stage: took effect
PJM 202-26-35 ran Jul 14–21
2026-07-20Order 202-26-36 for SPP ran July 20-21.
Order 202-26-36 for SPP ran July 20-21. The same file adds that other named-unit and Puerto Rico orders continued into July, without numbers.
Who acted: Department of Energy (order 202-26-36, addressed to Southwest Power Pool, Inc.)
Stage: took effect
SPP order 202-26-36 ran Jul 20–21
2026-07-26DOE issued base order 202-26-37 for SPP on July 26, initially due to expire August 3 at 11:59 p.m.
DOE issued base order 202-26-37 for SPP on July 26, initially due to expire August 3 at 11:59 p.m. CDT.
Who acted: Department of Energy (order 202-26-37, addressed to Southwest Power Pool, Inc.)
Stage: signed or enacted
the July 26 base order, initially due to expire August 3 at 11:59 p.m. CDT
2026-08-03DOE extended the SPP emergency authority through order 202-26-37A, effective August 4 through August 10.
DOE extended the SPP emergency authority through order 202-26-37A, effective August 4 through August 10. The file does not record any unit being dispatched or how costs were allocated.
Who acted: Department of Energy (order 202-26-37A, addressed to Southwest Power Pool, Inc.)
Stage: signed or enacted
Where the files differ: Settled inside the file: an interim finding in the same campaign said the July 26 order had expired with no successor; DOE added the extension to its order page while the wave was in progress, and the file says the extension 'supersedes the interim research finding'. The August 8 file found the page still showing only this extension.
was extended on August 3 through Order 202-26-37A. The extension is effective August 4 through August 10.
2026-08-05The Secretary of Energy found an emergency under section 202(c) in the Guam Power Authority region and directed the Guam Power Authority to dispatch specified Ukudu gas-turbine units only when it determines they are needed for reliability; additional units are allowed subject to notice and DOE disapproval; daily unit-use reports are required; operation is limited to reliability need and environmental conditions; the order runs through November 4, Guam time.
The Secretary of Energy found an emergency under section 202(c) in the Guam Power Authority region and directed the Guam Power Authority to dispatch specified Ukudu gas-turbine units only when it determines they are needed for reliability; additional units are allowed subject to notice and DOE disapproval; daily unit-use reports are required; operation is limited to reliability need and environmental conditions; the order runs through November 4, Guam time.
Who acted: Secretary of Energy (order 202-26-38, addressed to the Guam Power Authority)
Stage: signed or enacted
the Secretary of Energy found a statutory emergency in the Guam Power Authority region under Federal Power Act §202(c)
2026-08-07DOE renewed its emergency order on PREPA's specified generation resources as order 202-25-1E, effective August 10 through November 7, requiring the listed resources to operate only as needed for reliability, with biweekly Wednesday reports.
DOE renewed its emergency order on PREPA's specified generation resources as order 202-25-1E, effective August 10 through November 7, requiring the listed resources to operate only as needed for reliability, with biweekly Wednesday reports. The prior order 202-25-1D was scheduled to end August 9.
Who acted: Department of Energy (order 202-25-1E, addressed to the Puerto Rico Electric Power Authority)
Stage: signed or enacted
Where the files differ: Missing fact, not a conflict: the markdown files leave the day unstated ('2026-08 (not stated)' in the reader record); the ledger rows give 2026-08-07 at date level.
DOE renewed bounded emergency authority requiring listed generation resources to operate only as needed for reliability.
2026-08-07DOE renewed its emergency order on PREPA's transmission and distribution facilities as order 202-25-2E for 90 days (August 10 - November 7), directing another 400 miles of vegetation management plus asset-management duties and biweekly reports; the ledger says earlier directives were still incomplete.
DOE renewed its emergency order on PREPA's transmission and distribution facilities as order 202-25-2E for 90 days (August 10 - November 7), directing another 400 miles of vegetation management plus asset-management duties and biweekly reports; the ledger says earlier directives were still incomplete.
Who acted: Department of Energy (order 202-25-2E, addressed to the Puerto Rico Electric Power Authority)
Stage: signed or enacted
DOE renewed the order for 90 days and directed another 400 miles of vegetation management plus asset-management and biweekly reporting duties.
2026-08-10Order 202-26-37A expired August 10; DOE's live order page showed no successor at the file's cutoff.
Order 202-26-37A expired August 10; DOE's live order page showed no successor at the file's cutoff. Reporting and compliance duties are kept separate from the expired authority.
Who acted: Department of Energy (order 202-26-37A)
Stage: ended or withdrawn
DOE Order 202-26-37A authorized specified emergency measures from August 4 through **August 10**.
2026-08-14Order 202-26-39 requires MISO and Consumers Energy to keep the Campbell plant available from August 17 to November 14, with MISO using economic dispatch to minimize ratepayer cost, daily operation notices and an August 31 report; Consumers must seek FERC tariff changes or waivers where needed; Campbell cannot be treated as a capacity resource under this order.
Order 202-26-39 requires MISO and Consumers Energy to keep the Campbell plant available from August 17 to November 14, with MISO using economic dispatch to minimize ratepayer cost, daily operation notices and an August 31 report; Consumers must seek FERC tariff changes or waivers where needed; Campbell cannot be treated as a capacity resource under this order. A ledger calls it a renewal of a preceding Campbell emergency period.
Who acted: Department of Energy (order 202-26-39, addressed to the Midcontinent Independent System Operator (MISO) and Consumers Energy)
Stage: signed or enacted
Where the files differ: Scope of the order. The August 20 file says MISO and Consumers 'must keep the 1,420-MW Campbell plant available'; the August 22 ledgers title it 'J.H. Campbell Unit 3 continued-availability order' and say Consumers 'must make Campbell Unit 3 available'. Not settled.
Order 202-26-39 was issued August 14 and is effective August 17–November 14.
2026-08-19Order 202-26-25A lets PJM run Talen's 397-MW Wagner Unit 4 above its 438 fuel-oil-hour annual limit, but only when PJM declares or anticipates a Maximum Generation Alert or Transmission Security Emergency, or dispatches under the FERC-approved ER24-1787 settlement; PJM owes DOE next-business-day notice with exceedance data; PJM had reported no 2026 hours remaining on August 4.
Order 202-26-25A lets PJM run Talen's 397-MW Wagner Unit 4 above its 438 fuel-oil-hour annual limit, but only when PJM declares or anticipates a Maximum Generation Alert or Transmission Security Emergency, or dispatches under the FERC-approved ER24-1787 settlement; PJM owes DOE next-business-day notice with exceedance data; PJM had reported no 2026 hours remaining on August 4. The files do not describe an earlier order 202-26-25.
Who acted: Department of Energy (order 202-26-25A, addressed to PJM; Talen is the unit's owner as the files name it, without a legal-entity form)
Stage: signed or enacted
Where the files differ: Kind of order. The August 20 file contrasts it with Campbell as an alert-only permission ('Unlike Wagner, this is a continuous availability obligation rather than an alert-only permission'); the August 22 ledgers title it 'Wagner Unit 4 continued-availability order' and say 'Talen must make Wagner Unit 4 available to PJM'. Not settled.
Order 202-26-25A was issued August 19 and is effective August 20–November 17.
2026-08-21DOE ordered Eddystone Units 3 and 4 kept available for PJM reliability from August 23 to November 20, with daily notices and a measures report due September 8.
DOE ordered Eddystone Units 3 and 4 kept available for PJM reliability from August 23 to November 20, with daily notices and a measures report due September 8. A ledger says the units were scheduled to retire and calls the order a successor emergency-availability order.
Who acted: Department of Energy (order 202-26-40, 'PJM Interconnection Order No. 202-26-40 regarding Eddystone Units 3 and 4'; a ledger names Constellation as the owner that must make the units available, without a legal-entity form)
Stage: signed or enacted
Where the files differ: Missing fact in the markdown files (date 'not stated'), supplied by the ledgers at date level. One reader record words the units as 'PJM Interconnection's Eddystone Units 3 and 4'; PJM is the addressee, and the ledger names Constellation as the party that must make them available.
DOE ordered the units kept available for PJM reliability and imposed notices plus a September measures report.
2026-09-01DOE issued an emergency order for PJM, effective through September 8, directing specified dispatch actions and permitting backup generation as a last resort before or during an Energy Emergency Alert 3 (EEA3).
DOE issued an emergency order for PJM, effective through September 8, directing specified dispatch actions and permitting backup generation as a last resort before or during an Energy Emergency Alert 3 (EEA3). The order number appears in the September 11 files.
Who acted: Department of Energy (order 202-26-41, addressed to PJM)
Stage: signed or enacted
On September 1, DOE issued an emergency order for PJM, effective through September 8, directing specified dispatch actions and permitting backup generation as a last resort before or during an Energy Emergency Alert 3.
2026-09-02DOE issued an order keeping the Orlando Utilities Commission's Stanton coal unit (Unit 1) available through November 30.
DOE issued an order keeping the Orlando Utilities Commission's Stanton coal unit (Unit 1) available through November 30. The number 202-26-42 first appears in the September 16 library file; the November 6 file gives the 202-26-42A number to the later rehearing notice.
Who acted: Department of Energy (order 202-26-42, concerning the Orlando Utilities Commission's Stanton Energy Center)
Stage: signed or enacted
Where the files differ: Issue date. The September 3 files and the register date the order September 2; the November 6 file says 'Sep. 1 underlying §202(c) availability order covers Stanton Unit 1 Sep. 2–Nov. 30.' Not settled.
On September 2, DOE issued an emergency order concerning the Orlando Utilities Commission's Stanton coal unit, effective through November 30.
2026-09-03DOE issued a Carolinas section 202(c) emergency order effective through 11:59 p.m.
DOE issued a Carolinas section 202(c) emergency order effective through 11:59 p.m. EDT September 8, authorizing Duke Energy Carolinas to dispatch specified units and direct backup generation as a last resort before or during EEA3.
Who acted: Department of Energy (order 202-26-43, addressed to Duke Energy Carolinas)
Stage: signed or enacted
Where the files differ: Date in the reader records: two reader records give 2026-09-08, which is the end of the period; the campaign ledger gives object date 2026-09-03.
DOE issued a Carolinas section 202(c) emergency order effective through 11:59 p.m. EDT September 8, authorizing Duke Energy Carolinas to dispatch specified units and direct backup generation as a last resort before or during EEA3.
2026-09-08Order 202-26-41 expired at 23:59 ET on September 8; the order page showed no public EEA3 or dispatch receipt.
Order 202-26-41 expired at 23:59 ET on September 8; the order page showed no public EEA3 or dispatch receipt.
Who acted: Department of Energy (order 202-26-41)
Stage: ended or withdrawn
DOE PJM Order 202-26-41 | expired 23:59 ET 2026-09-08
2026-09-08Carolinas order 202-26-43 expired as scheduled on September 8.
Carolinas order 202-26-43 expired as scheduled on September 8.
Who acted: Department of Energy (order 202-26-43)
Stage: ended or withdrawn
Craig 202-26-31 still through Sep 26; Stanton 202-26-42 through Nov 30; Carolinas 202-26-43 expired Sep 8 as scheduled.
2026-09-11Order 202-26-44 directs TransAlta Centralia Generation, LLC to keep Unit 2 of the Centralia Generating Station in Washington (729.9 MW, coal) available to operate at the direction of Gridforce Energy Management, LLC or SPP Western RC from September 13 to December 11.
Order 202-26-44 directs TransAlta Centralia Generation, LLC to keep Unit 2 of the Centralia Generating Station in Washington (729.9 MW, coal) available to operate at the direction of Gridforce Energy Management, LLC or SPP Western RC from September 13 to December 11. The order text, as the files read it: Unit 2 had been slated to stop at the end of 2025 under a 2011 Washington law and a TransAlta-state agreement; it 'shall not be considered a capacity resource'; BPA (listed in the files as Bonneville) is to facilitate transmission; daily notice whether Unit 2 operated; a measures filing due September 27; notice within 15 days of any gas-conversion permits; copies to FERC and the Washington UTC (the files do not spell out the abbreviation).
Who acted: Secretary of Energy Chris Wright (order 202-26-44, addressed to TransAlta Centralia Generation, LLC)
Stage: signed or enacted
Where the files differ: Codex treats it as a new numbered order, not an extension of 202-26-28 (see interpretation). The September 11 files said no new 202(c) order was found after September 3; 202-26-44 was posted after that package's freeze, as the September 16 file explains.
Availability-to-operate order for a coal unit previously scheduled to retire end-2025.
2026-09-11Craig order 202-26-31 was in force through September 26, as carried in the September 11 and 16 checks.
Craig order 202-26-31 was in force through September 26, as carried in the September 11 and 16 checks. The files give no issue date, addressee, unit or owner. The notes record no end as of November 6, 2026.
Who acted: Department of Energy (order 202-26-31; the files name no addressee or plant owner)
Stage: other
Craig Order 202-26-31 through 2026-09-26
2026-09-12The earlier TransAlta order 202-26-28 expired as scheduled on September 12, one day before 202-26-44 took effect.
The earlier TransAlta order 202-26-28 expired as scheduled on September 12, one day before 202-26-44 took effect. The files do not give its issue date.
Who acted: Department of Energy (order 202-26-28, TransAlta)
Stage: ended or withdrawn
Replaces expired Order 202-26-28 (through 2026-09-12).
2026-09-17DOE issued order 202-26-45, directing PJM to use specified resources only as needed for the emergency and authorizing backup generation at large loads; the operative period ended September 18.
DOE issued order 202-26-45, directing PJM to use specified resources only as needed for the emergency and authorizing backup generation at large loads; the operative period ended September 18.
Who acted: Department of Energy (order 202-26-45, addressed to PJM)
Stage: signed or enacted
It directed PJM to use specified resources only as needed for the emergency and authorized backup generation at large loads
2026-09-17 Turning pointPJM posted that it had identified a reliability need to use the order's Exhibit A resources for the September 17 operating day (13:00-23:59 EDT); it expressly did not direct maximum output or full load.
PJM posted that it had identified a reliability need to use the order's Exhibit A resources for the September 17 operating day (13:00-23:59 EDT); it expressly did not direct maximum output or full load. The library holds no earlier record of a grid operator invoking a section 202(c) order's operating pathway.
Who acted: PJM Interconnection, L.L.C. (Special Notice 105531)
Stage: first use
said PJM had identified a reliability need to use the Exhibit A resources for the September 17 operating day. It expressly did not direct maximum output or full load.
2026-09-18PJM filed a daily compliance report giving prior-day operating hours for the listed resources, based on generation-owner data subject to later update.
PJM filed a daily compliance report giving prior-day operating hours for the listed resources, based on generation-owner data subject to later update. The file warns the rows include different kinds of specified and backup resources and do not give megawatt-hours.
Who acted: PJM Interconnection, L.L.C. (daily compliance report under order 202-26-45)
Stage: in operation
reports prior-day operating hours for the listed resources and attributes the underlying data to generation owners, subject to later update.
2026-09-18Order 202-26-46 requires NIPSCO and MISO to keep Schahfer Units 17 and 18 available from September 20 to December 18 with economic dispatch, daily notice of whether the units operated, environmental monitoring and compliance, FERC tariff or waiver filings as needed, a MISO report by October 3, and statutory rate recovery; the units are not capacity resources by reason of the order.
Order 202-26-46 requires NIPSCO and MISO to keep Schahfer Units 17 and 18 available from September 20 to December 18 with economic dispatch, daily notice of whether the units operated, environmental monitoring and compliance, FERC tariff or waiver filings as needed, a MISO report by October 3, and statutory rate recovery; the units are not capacity resources by reason of the order. Prior DOE orders had kept the units available through September 19; they had been slated to stop at the end of 2025.
Who acted: Department of Energy (order 202-26-46; NIPSCO and MISO are the parties the file names, without legal-entity forms)
Stage: signed or enacted
prior DOE orders kept Schahfer Units 17/18 and Culley Unit 2 available through September 19; the units had been slated to cease operation at the end of 2025.
2026-09-18Order 202-26-47 requires CenterPoint and MISO to keep Culley Unit 2 available from September 20 to December 18 with economic dispatch, daily use notices, a MISO report by October 3, FERC filings as needed, statutory rate recovery, and no capacity-resource status by reason of the order.
Order 202-26-47 requires CenterPoint and MISO to keep Culley Unit 2 available from September 20 to December 18 with economic dispatch, daily use notices, a MISO report by October 3, FERC filings as needed, statutory rate recovery, and no capacity-resource status by reason of the order. A prior order had kept the unit available through September 19.
Who acted: Department of Energy (order 202-26-47; CenterPoint and MISO are the parties the file names, without legal-entity forms)
Stage: signed or enacted
NIPSCO/MISO and CenterPoint/MISO must keep the specified units available and use economic dispatch.
2026-09-18Order 202-26-48 allowed Duke to dispatch specified resources only as needed and to use backup generation before or during an EEA3 condition from September 18 to 21, with daily reporting, legal and environmental obligations kept, FERC filings or waivers required, and an additional unit allowed subject to prompt notice and later DOE disapproval.
Order 202-26-48 allowed Duke to dispatch specified resources only as needed and to use backup generation before or during an EEA3 condition from September 18 to 21, with daily reporting, legal and environmental obligations kept, FERC filings or waivers required, and an additional unit allowed subject to prompt notice and later DOE disapproval. It recognized a risk of NOx, CO or VOC permit exceedances and applied the statutory emergency treatment to the relevant hours and emissions. The notes record no public daily compliance report as of November 6, 2026.
Who acted: Department of Energy (order 202-26-48, addressed to 'Duke'; the file does not give the exact Duke legal entity)
Stage: signed or enacted
was issued and effective September 18 through September 21.
2026-10-11A request for the emergency order that became 202-26-50 is dated October 11.
A request for the emergency order that became 202-26-50 is dated October 11. The file does not say who made it.
Who acted: Not named in the file (the ledger lists the request date for order 202-26-50; its actor list is 'DOE Secretary; PJM; affected generators, Transmission Owners and Electric Distribution Companies')
Stage: requested
"request": "2026-10-11"
2026-10-12Order 202-26-50 authorized dispatch of specified resources as necessary and backup use only as a last resort before or during EEA3, exempted critical backup needs, required daily designation, operating and environmental reports, denied capacity-resource status, and ended the operating authorization on October 16 while keeping the reporting duties.
Order 202-26-50 authorized dispatch of specified resources as necessary and backup use only as a last resort before or during EEA3, exempted critical backup needs, required daily designation, operating and environmental reports, denied capacity-resource status, and ended the operating authorization on October 16 while keeping the reporting duties. Its exhibits were updated three times. The ledger notes the order was absent from the October 18 sweep's movement ledger and was recovered on October 22.
Who acted: Secretary of Energy (order 202-26-50, addressed to PJM)
Stage: signed or enacted
A/B authorize specified-resource dispatch as necessary and backup use only as last resort before/during EEA3
2026-10-16The PJM emergency order expired October 16 but kept specified reporting obligations.
The PJM emergency order expired October 16 but kept specified reporting obligations.
Who acted: Department of Energy (order 202-26-50)
Stage: ended or withdrawn
DOE's recovered PJM emergency order expired October 16 but retained specified reporting obligations.
2026-11-03 Turning pointDOE's signed notice 202-26-42A confirms that requests for rehearing of the Stanton order were deemed denied by operation of law after 30 days, while DOE reserved further consideration.
DOE's signed notice 202-26-42A confirms that requests for rehearing of the Stanton order were deemed denied by operation of law after 30 days, while DOE reserved further consideration. The file names neither who asked for rehearing nor when; it records no decision on the merits and no new dispatch or output.
Who acted: Secretary of Energy (notice 202-26-42A on the Stanton order)
Stage: other
Nov. 3 Order 202-26-42A confirms requests for rehearing deemed denied by operation of law following 30 days while reserving further consideration.
2026-11-13Energy Secretary Chris Wright issued Order 202-26-51 to keep the Campbell plant available, with a daily MISO reporting duty.
Energy Secretary Chris Wright issued Order 202-26-51 to keep the Campbell plant available, with a daily MISO reporting duty.
Who acted: Secretary of Energy
Stage: renewal issued
On November 13, 2026, Energy Secretary Chris Wright issued Order 202-26-51 under Federal Power Act §202(c).
2026-11-15The Campbell availability duty took effect through February 12, 2027.
The Campbell availability duty took effect through February 12, 2027.
Who acted: Secretary of Energy; MISO and Consumers Energy
Stage: renewal effective
The order directs MISO and Consumers Energy to keep the J.H. Campbell Generating Facility available from November 15, 2026 through February 12, 2027.
2026-11-17DOE issued Order 202-26-25B on November 17, renewing the Wagner Unit 4 emergency permission from November 18 through December 31, 2026.
DOE issued Order 202-26-25B on November 17, renewing the Wagner Unit 4 emergency permission from November 18 through December 31, 2026.
Who acted: Department of Energy
Stage: issued renewal
DOE issued Order 202-26-25B on November 17, renewing the Wagner Unit 4 emergency permission from November 18 through December 31, 2026.
Where it stands
As of the November 21, 2026 return, DOE issued Wagner Unit 4 Order 202-26-25B on November 17, effective November 18 through December 31, 2026. The Campbell renewal and other earlier order snapshots retain their own dates and terms. As of November 16, 2026, Campbell order 202-26-51 is effective through February 12, 2027. The order sets a November 28 MISO availability-report deadline. At the November 6, 2026 snapshot, the library records these section 202(c) orders as running past that date by their stated terms: Puerto Rico 202-25-1E and 202-25-2E (to November 7), Campbell 202-26-39 (to November 14), Wagner Unit 4 202-26-25A (to November 17), Eddystone 3 and 4 202-26-40 (to November 20), Stanton Unit 1 202-26-42 (to November 30; rehearing requests deemed denied by operation of law on November 3, with DOE reserving further consideration), Centralia Unit 2 202-26-44 (to December 11), and Schahfer 17 and 18 202-26-46 and Culley 2 202-26-47 (to December 18). The Guam order 202-26-38 ran to November 4 by its terms; no file records a renewal, successor or end. The short event orders for PJM, SPP and Duke ran their stated days; files record the ends of 202-26-37A (August 10), 202-26-41 and 202-26-43 (September 8), 202-26-28 (September 12) and 202-26-50 (October 16, with reporting duties surviving). The library holds one record that resources ran under an order: PJM's September 17 notice and September 18 hours report under 202-26-45. The November 6 snapshot did not record megawatt-hours, costs, rate-recovery filings or a court case.
What comes next
- When
- 2026-11-07
- What
- End of the period of Puerto Rico orders 202-25-1E and 202-25-2E.
- Stage
- scheduled (end date in the orders)
- Files
- Federal Government Full Freshness Sweep 2026-08-22/waves/wave_4_logistics/energy_labs_sublane/PRIMARY_OBJECT_DISPOSITION_LEDGER.csv
- When
- 2026-11-14
- What
- End of the Campbell order 202-26-39.
- Stage
- scheduled (end date in the order)
- Files
- Federal Government Weekly Delta 2026-08-20/WAVE_3_HUMAN_PHYSICAL_INFRASTRUCTURE.md
- Federal Government Full Freshness Sweep 2026-08-22/waves/wave_4_logistics/energy_labs_sublane/PRIMARY_OBJECT_DISPOSITION_LEDGER.csv
- When
- 2026-11-16 and 2026-11-20
- What
- Replies due in FERC's large-load show-cause proceedings (five RTO/ISOs November 16; SPP November 20).
- Stage
- scheduled (another story)
- Files
- Federal Government Weekly Catch-up 2026-11-06/DOMESTIC_SOURCE_REVIEW.md
- When
- 2026-11-17
- What
- End of the Wagner Unit 4 order 202-26-25A.
- Stage
- scheduled (end date in the order)
- Files
- Federal Government Weekly Delta 2026-08-20/WAVE_3_HUMAN_PHYSICAL_INFRASTRUCTURE.md
- Federal Government Full Freshness Sweep 2026-08-22/waves/wave_4_logistics/energy_labs_sublane/PRIMARY_OBJECT_DISPOSITION_LEDGER.csv
- When
- 2026-11-20
- What
- End of the Eddystone order 202-26-40.
- Stage
- scheduled (end date in the order)
- Files
- Federal Government Full Freshness Sweep 2026-08-22/waves/wave_4_logistics/energy_labs_sublane/PRIMARY_OBJECT_DISPOSITION_LEDGER.csv
- Federal Government Full Freshness Sweep 2026-08-22/waves/operations_full_fresh/PRIMARY_OBJECT_DISPOSITION.csv
- When
- 2026-11-28
- What
- MISO availability report due under order 202-26-51.
- Stage
- scheduled in signed order
- Files
- Federal Government Deep Website Review 2026-09-22/DOE_CAMPBELL_EMERGENCY_DISPATCH_RENEWAL_2026-11-16.md
- When
- 2026-11-30
- What
- End of the Stanton Unit 1 order 202-26-42. DOE has reserved further consideration of the rehearing requests; no date is given for that.
- Stage
- scheduled (end date in the order); further consideration pending, undated
- Files
- Federal Government Weekly Delta 2026-09-03/waves/WAVE_1C_OPERATIONS_INDUSTRY_DELIVERY.md
- Federal Government Weekly Catch-up 2026-11-06/DOMESTIC_SOURCE_REVIEW.md
- When
- 2026-12-11
- What
- End of the Centralia Unit 2 order 202-26-44.
- Stage
- scheduled (end date in the order)
- Files
- Federal Government Weekly Delta 2026-09-16/waves/WAVE_1C_OPERATIONS_INDUSTRY_DELIVERY.md
- Federal Government Weekly Delta 2026-09-16/WHOLE_GOVERNMENT_WEEKLY_MERGE_2026-09-16.md
- When
- 2026-12-18
- What
- End of the Schahfer 202-26-46 and Culley 202-26-47 orders.
- Stage
- scheduled (end date in the orders)
- Files
- Federal Government Deep Website Review 2026-09-22/waves/WAVE_4_INDUSTRIAL_ENERGY_LOGISTICS.md
- When
- 2027-02-12
- What
- Campbell order 202-26-51 ends by its terms.
- Stage
- scheduled in signed order
- Files
- Federal Government Deep Website Review 2026-09-22/DOE_CAMPBELL_EMERGENCY_DISPATCH_RENEWAL_2026-11-16.md
What the notes do not record
- The notes do not record megawatt-hours, generation or continuous operation under any order. The one use record (PJM, September 17-18) gives operating hours from owners' data, subject to update.
- The notes do not record any cost figure, any FERC rate-recovery or tariff filing made under an order, or who finally paid.
- The notes do not record who asked for rehearing of the Stanton order, when, or on what grounds; any court petition on any order.
- The notes do not record who requested any order. 202-26-50 has a request date (October 11); the requester is not named.
- The notes do not record any order made because of data-center demand. EO 14262's purpose text cites AI data centers, and 202-26-45 authorized backup generation 'at large loads' without naming them; no order is tied to a data center in the files.
- The notes do not record the predecessor orders behind the letter suffixes and 'prior orders' (202-26-25, 202-26-32, 202-26-33, 202-25-1D, the earlier Campbell, Eddystone, Schahfer and Culley orders) and the issue dates of 202-26-28 and 202-26-31.
- The notes do not record whether an order 202-26-49 exists, or any orders numbered below 202-26-25.
- The notes do not record the exact Duke entity for 202-26-34 and 202-26-48; the legal-entity forms of Talen, Constellation, NIPSCO and CenterPoint; PREPA's 'covered operators'.
- The notes do not record whether the Campbell order covers the whole plant or Unit 3.
- The notes do not record who owns or receives the Craig order 202-26-31, which unit it covers, and what happened on September 26.
- The notes do not record whether the Guam order was renewed after November 4, or the Puerto Rico orders after November 7.
- The notes do not record whether DOE published the reserve-margin methodology or the critical-resource protocol EO 14262 called for.
What it touches
- Executive Order 14421: national emergency to secure the bulk-power system and the Energy Secretary's 120/180-day duties
Executive Order 14421 (signed August 26, published August 31, 2026) declared a bulk-power-system national emergency; DOE CESER's webinar on its request for information was held September 16, the day before 202-26-45.
- Federal Energy Regulatory Commission (FERC)'s six section 206 large-load proceedings (June 18, 2026) and their dispositions
FERC opened six Federal Power Act section 206 proceedings on June 18, 2026 covering every RTO/ISO; replies are due November 16 (five RTO/ISOs) and November 20 (SPP). FERC also receives the tariff and waiver filings the 202(c) orders require.
- Federal handling of artificial intelligence data-center load on the electric grid
The thread register merges a reader name 'Grid reliability for AI data-center load (FERC/NERC computational-load standards; DOE 202(c) orders)' into that question. EO 14262's purpose cites 'the expansion of artificial intelligence data centers'; 202-26-45 authorized backup generation at large loads; Codex says 202-26-50 is 'Not a blanket data-center operating permit'.
- Environmental Protection Agency (EPA) repeal of power-plant greenhouse-gas standards (partial-repeal final and residual SNPRM, Sep 2026)
EPA signed the partial repeal on September 14; the September 16 file states it is 'Not a §202(c) order'.
- Department of Energy (DOE) National Interest Electric Transmission Corridors (NIETC) process ended without designation
The same August 22 files that record the Eddystone and Puerto Rico orders record DOE's final decision to designate none of the three proposed National Interest Electric Transmission Corridors.
Graphics and studies
- No federal data-center ban, just scattered permits and leases
- What materially changed across the federal government through October 25
- What changed in the federal government, August 2–8
- What changed in the federal government, August 8–13
- What changed in the federal government, August 31–September 3