Federal Data Center Return Refresh — October 5, 2026
Full saved reading
View cited sources (18)
These are the sources cited by this reading. Each source keeps its own date and scope.
- SB Energy S-1/A, Properties
- GAO-27-108063, Appendix I
- DOE selection
- NNSA selection
- Army selection
- EO 14318 §§3, 5
- CEQ categorical-exclusion guidance
- February 19 memorandum
- 90 FR 10610
- September 29 memorandum
- 91 FR 618
- June 18, 2026 NYISO order, EL26-69-000
- DOE Speed to Power
- September 2026 Paducah CAB binder
- Kentucky PSC data-center tariff discussion
- FERC RM26-4 docket page
- FERC six-proceeding announcement
- FERC major orders
Saved research reading. Its original dates and claim limits control; the export date does not refresh the evidence.
Saved source details
---
title: Federal Data Center Return Refresh — 2026-10-05
status: current
artifact_role: answer
research_id: data-center-federal-legal-spine
evidence_cutoff: 2026-10-05
---
Federal Data Center Return Refresh — October 5, 2026
November 18 dated source return: GAO's reported Oak Ridge solicitation pause adds the October 16 report's project-state observation. The prior October baseline and November 15 lease passages below remain separately dated.
Federal land and permitting through November 15, 2026
| Site | Lease evidence | Terms and scope |
|---|---|---|
| Portsmouth, Ohio | SB Energy’s September S-1/A identifies Pike County Portsmouth DC LLC as the subsidiary that entered into a DOE lease on February 26, 2026. GAO records 189 acres. SB Energy S-1/A, Properties · GAO-27-108063, Appendix I | SB Energy expects one data-center building on DOE land and most campus buildings on private land. Lease text, rent, duration and renewal terms were not located. |
| Paducah, Kentucky | DOE officials told GAO that DOE signed a lease with a private company in July 2026 for the 785-acre Parcel B. GAO’s appendix lists Brookfield/NextEra. GAO-27-108063, redevelopment discussion and Appendix I | DOE identifies Brookfield as campus developer and NextEra as generation developer. Exact lessee, signature day and lease terms were not located. Kentucky approval of the power-service agreement is separate. DOE selection |
| Savannah River, South Carolina | NNSA selected Amentum in July for negotiations on a phased lease. GAO’s narrative reports negotiations. NNSA selection · GAO-27-108063 | GAO’s appendix lists a lease as the realty action. Its narrative and the NNSA announcement identify the negotiations stage. An executed phased lease was not located. |
| Fort Bliss, Texas and Dugway, Utah | The Army selected Carlyle and CyrusOne, respectively, for exclusive negotiations under 10 U.S.C. §2667. Army selection | The announcement expressly conditions final agreements on negotiation. A final lease for either installation was not located. |
EO 14318 §3 assigns Commerce, in consultation with OSTP, the financial-support initiative. DOE publicly identifies its American Energy Hubs site-reuse initiative. A Commerce/OSTP instrument implementing §3 and the agency submissions identifying existing support were not located. Section 5(a) required agencies to identify relevant existing established or adopted categorical exclusions to CEQ within 10 days. Section 5(b) directs CEQ to coordinate establishment of new categorical exclusions with the agencies. CEQ published general categorical-exclusion guidance on April 9, 2026. The agency lists under §5(a) were not located. EO 14318 §§3, 5 · DOE Paducah announcement · CEQ categorical-exclusion guidance
Under EO 14154 §5(b), CEQ issued its NEPA implementation memorandum on February 19, 2025, the day it signed the interim final rule removing its government-wide implementing regulations. CEQ issued further implementation guidance on September 29, 2025. In the January 8, 2026 final rule, CEQ said it had convened a working group of select agencies and was continuing to coordinate revision of agency-level procedures under §5(c). CEQ’s final rule does not identify the agencies. February 19 memorandum · 90 FR 10610 · September 29 memorandum · 91 FR 618
<!-- managed-discovery-batch-2026-11-03:ferc -->
Dated source extension — NYISO payment-to-rate accountability
FERC's June 18, 2026 NYISO order, EL26-69-000, ¶¶85–91 (printed pp.54–57), adds detail beneath the existing cost-causation account. It preliminarily considers minimum contributions and financial security when requested load underdelivers or does not materialize. Paragraph 88 seeks briefing on substituting a direct large-load agreement for the transmission-service customer's agreement with comparable protection; ¶89 considers avoiding duplicative security. These counterparties are distinct.
Paragraph 91 expects payments to be credited to transmission revenue requirements under cost-of-service regulations and preliminarily considers a separate annual workpaper showing their treatment in formula rates. Collecting protection payments and demonstrating their rate treatment are separate accountability steps. Ordinary cost causation and efficient, reliable interconnection explain the proposal.
The order institutes a section 206 proceeding and requires justification or proposed reforms; these positions do not by themselves establish final tariff terms. Integrated November 3 from the bounded reading. No later merits disposition or deadline-extension letter was verified. Educational OPP dates are not adopted as current deadlines here. The October 5 baseline and existing final-order return remain separate; no AI-compute recurring check is created.
<!-- /managed-discovery-batch-2026-11-03:ferc -->
<!-- plain-english-entry:start -->
In plain English
Question: Which federal legal objects actually govern U.S. data-center buildout, and which proposed, issued, authorized, constructed and operating states remain separate?
Answer: The saved review found no general federal ban or single national code for commercial data centers. Existing environmental, land, utility and project-approval rules still apply. The July 2025 executive order has produced leases, selections and permit changes; those steps do not prove a finished project or a blanket exemption.
Evidence checked through: 2026-10-05
The detailed record below keeps the legal wording, source limits and open questions.
<!-- plain-english-entry:end -->
In plain English
Question: Did the federal data-center push become a consolidated program,
executed site leases, or operative large-load rules?
Answer: DOE now publicly uses the name American Energy Hubs for its
federal-site reuse lane, but no Commerce/OSTP section-3 instrument consolidates
all authorities, eligibility and support. Savannah River is still a selection
for lease negotiations. At the October 5 cutoff Paducah had selected sponsors
and a mapped reuse parcel. GAO subsequently reported a July lease for Parcel B.
The power agreement remains subject to Kentucky approval. FERC's national large-load docket remains an
advance-rulemaking record, while six section 206 proceedings remain the main
federal tariff path.
1. A named DOE lane exists, not one consolidated federal programme
DOE's July Paducah announcement calls the site-reuse lane its **American Energy
Hubs initiative**. DOE's Speed to Power page separately inventories large-load,
transmission, technical-assistance and Tribal-energy actions. Those objects make
the architecture less inferential than it was in August.
They still do not supply the section 3 object asked for in this return: no
located Commerce/OSTP document joins governing authority, programme inventory,
applicant eligibility, administrators and each support instrument into one
consolidated initiative. DOE's named lane is real; it is not a government-wide
fund, entitlement or single approval path.
Primary sources: DOE Paducah partnership,
2. Savannah River remains at negotiation
NNSA's current public object still says Amentum was selected to **enter
negotiations** for a phased lease. It expressly says selection is not a final
lease award and makes any agreement contingent on negotiation, permitting,
safety and security review and other federal approvals.
No signed phased lease, site-control instrument, project-specific permit,
financing close, notice to proceed or construction record was located. Other
Savannah River contracts and construction announced in September belong to the
site's nuclear-cleanup and operating missions and cannot be used as receipts
for the proposed data center.
Primary source: NNSA Amentum selection.
3. Paducah has a clearer physical plan but not the controlling agreements
DOE's September Community Advisory Board materials now map roughly 785 acres
for an AI data center. The July announcement keeps the role split explicit:
Brookfield was selected to develop and operate the campus; NextEra was selected
to build and own dedicated generation; Big Rivers would provide wholesale
service; Jackson Purchase would provide retail service; and Paducah Power would
serve as community partner.
The same release says the power-service agreement remains subject to Kentucky
Public Service Commission approval. At the October 5 cutoff, no final
project-specific PSC order, interconnection agreement, generation CPCN,
environmental permit or construction notice was located. The Kentucky
Commission's already-approved EKPC Data Center Power tariff is a useful
cost-separation precedent, not the Paducah service approval.
Primary sources: DOE Paducah partnership,
September 2026 Paducah CAB binder,
Kentucky PSC data-center tariff discussion.
4. FERC's federal large-load layer is active but not final
RM26-4 remains an advance notice of proposed rulemaking. FERC's April order
committed the Commission to act, and its June 18 action opened six separate
section 206 proceedings for the regional grid operators to defend or reform
their tariffs. Those proceedings are real adjudicative control surfaces.
No final RM26-4 rule or six-proceeding merits disposition was located by the
cutoff. State large-load tariffs—including Kentucky's Data Center Power tariff
and the many other approved or pending state tariffs noted by FERC—show the
cost-causation model moving in parallel. They do not create one national tariff
or prove any named data center received service.
Primary sources: FERC RM26-4 docket page,
FERC six-proceeding announcement,
Return disposition
- ret-data-center-eo3-initiative: open, source-triggered.
- ret-savannah-river-data-center-lease: open, source-triggered.
- ret-paducah-data-center-power-and-lease: open, source-triggered.
- ret-large-load-tariff-federal-state-bridge: open; return on a final FERC or
material state/project order rather than another comment filing.
Boundary
Selection, lease, tariff, project service approval, permit, financing,
construction and operation remain separate clocks.