Federal Science Operating System — factual spine, 2025–2026
Full saved reading
View cited sources (72)
These are the sources cited by this reading. Each source keeps its own date and scope.
- EO 14300 — NRC reform
- EO 14301 — DOE testing
- EO 14299 — national-security power
- EO 14302 — industrial base
- DOE Reactor Pilot selections
- DOE worker-safety comment reopening
- NRC Part 53 final rule
- April 13 technical correction
- January 21 underlying proposal
- Proposed rule
- NRC schedule
- Final rule, NRC-2025-1503
- Executive Order 14301, §5
- DOE program and application
- DOE Mark-0 release
- DOE Ward 250 release
- DOE Unity release
- DOE Aalo-X release
- DOE Groves release
- DOE fact sheet
- DOE March 9 construction-permit notice
- NRC Hermes licensing page
- DOE HALEU enrichment services
- Part 57 microreactor proposal
- Prior DOE/Defense design evidence
- Contested adjudications proposal
- Fusion-machine framework proposal
- FY2026 fee final rule
- Foreign ownership exceptions
- April 23 direct final rule
- June 5 confirmation
- May 15 Part 57 correction
- NEIMA section 103(a)(4), 132 Stat. 5572
- ADVANCE section 205, 138 Stat. 1460–1462
- Public Law 118-67
- NRC — Fusion and the ADVANCE Act
- NRC fusion FAQ
- White House — Declaring a National Energy Emergency
- White House — Executive Order 14279 PDF
- White House — Accelerating Federal Permitting of Data Center Infrastructure
- White House — Improving Oversight of Federal Grantmaking
- Federal Register — EO 14363
- DOE — Data Centers: Exploring the Opportunity for Tribes
- Public Law 119-74
- FY2026 Energy and Water explanatory statement
- Type One — initial Bull Run licensing application
- NRC — fusion-machine rulemaking status
- DOE RFA announcement
- full RFA
- White House — DPA grid-infrastructure determination
- CFS application announcement
- PJM confirmation
- NSF — X-Labs initiative
- DOE — U.S.–Japan Genesis partnership
- DOE — finalized roadmap release
- DOE — full roadmap
- Tennessee — fusion regulations
- FERC — large-load integration orders
- Realta technical account
- exact publication clock
- LLNL — achieving fusion ignition
- White House — Science: A New Golden Age
- White House — NSTM-5 / M-26-16
- DOE announcement
- project list
- DOE X — main post
- continuation
- final card
- official PDF
- NSB report announcement
- NSF MPS update
- NSF funding decisions
Saved research reading. Its original dates and claim limits control; the export date does not refresh the evidence.
Federal Science Operating System — factual spine, 2025–2026
As of: 2026-08-17; targeted Reactor reconciliations added 2026-09-07, covering all thirteen original Reactor filings
Status: source-first factual spine
Boundary: dates, entities, instruments and legal states first; synthesis belongs in the control-surface map
Object ladder
| Object | Date | Legal or administrative state | What it can do | What it cannot do by itself |
|---|---|---|---|---|
Science: A New Golden Age | 2026-07-21 | OSTP report to the President | state doctrine, diagnose the old model, recommend institutions and horizon systems | appropriate funds, amend statutes, create a blockchain or compel every agency |
| National Security Science & Technology Strategy | 2026-08 cover month; exact publication/transmittal clock unresolved | national functional strategy supporting the 2025 NSS | select security missions and CETs; define resilience, acceleration and protection posture; promise OSTP/NSC follow-on plans | appropriate funds, assign every agency, prove statutory transmission, operate a platform or advance a named project |
| NSTM-5 / M-26-16 | 2026-07-21 | joint OSTP–OMB budget memorandum | direct FY2028 budget formulation and require qualifying agencies' implementation plans | guarantee Congress funds a proposal or turn speculative report concepts into programs |
| EO 14363 | signed 2025-11-24; published 2025-11-28 | executive order | charter Genesis Mission and direct DOE to build and operate the American Science and Security Platform | override appropriations, classification, IP, privacy, export-control or other applicable law |
| ADVANCE Act section 205 | 2024-07-09 | enacted statute | amend fusion-machine and fusion-produced byproduct-material definitions and amend the existing NEIMA framework provisions | finalize the rule or decide any project application |
| FY2026 Fusion Energy Sciences appropriation | 2026-01-23 | enacted appropriation and incorporated explanatory table | fund the FES account, including research and U.S. ITER construction | fund every facility or milestone named in the later roadmap |
| Type One / Bull Run initial application | 2026-01-29 | company-reported initial Tennessee byproduct-material application | begin a named project licensing record under an Agreement State framework | establish completeness, issuance, inspection, operation or power generation |
| NRC fusion-machine proposed rule | 2026-02-26 | proposed federal rule and draft guidance | open a technology-neutral federal licensing framework for comment | create a final effective rule or issue a particular license |
| Finalized Fusion Science and Technology Roadmap | 2026-06-09 | final DOE strategy; no specific funding commitment | coordinate science, AI/HPC, facilities, public-private programs, workforce, regulation and mid-2030s targets | appropriate funds, issue awards or prove a pilot plant operates |
DOE Energy Without Limits thread | 2026-08-15 | official communications event | amplify the finalized roadmap and commercialization agenda | establish a new experiment, award, facility, license or electricity result |
| EO 14332 | 2025-08-07 | executive order | tighten political and annual review of discretionary grants; direct termination and drawdown controls | replace the statutes authorizing each award or collapse student aid into R&D grants |
| EO 14318 | 2025-07-23 | executive order | create federal support and permitting lanes for qualifying data-center and component projects | approve every site or erase land, environmental, water, tribal or grid requirements |
| EO 14156 | 2025-01-20 | national-emergency declaration | direct use of lawful emergency processes for energy supply and infrastructure | make every private data center an emergency facility or supply a missing project authority |
| DPA section 303 grid determination | 2026-04-20 | presidential determination | authorize purchases, commitments and financial instruments to expand named grid capabilities | blanket-preempt siting, environmental review, utility jurisdiction or tribal consent |
Reactor reconciliation — seven filings reviewed September 7, 2026
Scope: the four May 2025 nuclear orders, the initial DOE pilot selection, the worker-safety comment reopening and NRC Part 53. This addition joins those original Tech questions to selected saved implementation evidence. It does not refresh every nuclear program, the remaining Reactor filings or the original August 17 science chronology.
The original question was how a nuclear revival would move through institutions, testing, fuel, sites and industrial capacity. Those are complementary investigations: an executive direction, a selected pilot, a construction permit and criticality answer different parts of it. The table corrects compressed descriptions while retaining the original dated filings and their thesis lens.
| Instrument / primary source | Source clocks | Verified meaning |
|---|---|---|
| EO 14300 — NRC reform | Signed 2025-05-23; filed 2025-05-28 08:45; published 2025-05-29, 90 FR 22587–22590. | NRC reform direction: decision deadlines and hourly-fee recovery caps require implementation. The approximately 100-to-400 GW aspiration for 2050 is in section 2(c). |
| EO 14301 — DOE testing | Signed 2025-05-23; filed 2025-05-28 08:45; published 2025-05-29, 90 FR 22591–22593. | DOE laboratory testing and the separate outside-laboratory pilot have different processes. The latter requires sufficient DOE control, not DOE ownership of the land; its research jurisdiction excludes commercial electric-power production. |
| EO 14299 — national-security power | Signed 2025-05-23; filed 2025-05-28 08:45; published 2025-05-29, 90 FR 22581–22586. | Separate Defense and DOE assignments connect national-security missions, sites and fuel. The Defense operating target is September 30, 2028; the DOE first-site goal is thirty months after signing. |
| EO 14302 — industrial base | Signed 2025-05-23; filed 2025-05-28 08:45; published 2025-05-29, 90 FR 22595–22599. | Fuel-cycle, workforce, financing and voluntary-agreement directions. Section 4(a) targets five GW of uprates and ten large reactors with complete designs under construction by 2030; the 2050 capacity aspiration belongs to EO 14300. |
| DOE Reactor Pilot selections | Official announcement 2025-08-12; no time established. Criticality target 2026-07-04 is prospective in that source. | Eleven projects across ten companies were initially selected; companies bear project costs. Selection and the July 4, 2026 criticality goal do not themselves establish authorization or achievement. |
| DOE worker-safety comment reopening | Original NOPR published 2026-01-21; extension request dated 2026-02-04; reopening signed 2026-02-24; filed 2026-02-25 08:45; published 2026-02-26, 91 FR 9498–9499; comments through 2026-03-23. | Reopened comments on the January 21 proposed Part 851 rule through March 23. The AFL-CIO request cited review time and affiliate coordination; it is not itself evidence of substantive opposition or a final rule. |
| NRC Part 53 final rule | Rule dated 2026-03-25; filed 2026-03-27 08:45; published 2026-03-30, 91 FR 15696; effective 2026-04-29. Correction dated 2026-04-09; filed 2026-04-10 08:45; published 2026-04-13; effective 2026-04-29. | Optional commercial fission licensing alongside Parts 50 and 52, including light-water designs. Effective April 29; the April 13 correction retained that date. Fusion has a separate rulemaking; this is distinct from the broader EO 14300 overhaul. |
For Part 53, see also the April 13 technical correction. For the safety reopening, the January 21 underlying proposal supplies the proposed changes. This reconciliation read the four orders and two short notices in full; Part 53 and the underlying safety proposal received targeted scope, authority and clock checks, not a complete technical review or later-rule census.
NRC licensing overhaul and previously authorized designs
The NRC published its broader proposed rule on reactor licensing, decommissioning and operational oversight on September 24, at 91 FR 60702 (NRC-2025-1138, RIN 3150-AL45). The final printed notice set November 9, 2026 at 11:59 p.m. ET as the comment deadline. Proposed rule
EO 14300 §5 gave NRC 18 months from signing to complete its revision of rules and guidance. NRC identifies November 23, 2026 as that deadline. The final rule on reactor designs previously authorized by the Departments of Energy or War was published October 26 at 91 FR 67195, with a scheduled effective date of November 25. It adds to Parts 50 and 53 a route for applicants to use a prior authorization to demonstrate specified safety functions. The applicant must identify how the earlier authorization satisfies applicable NRC requirements. A commercial license still requires NRC review and decision. NRC schedule · Final rule, NRC-2025-1503
DOE Reactor Pilot Program — reported tests and sites
- 23 May 2025. Under EO 14301 §5(a), the President directed the Secretary of Energy to create a pilot outside national laboratories and approve at least three test reactors with a goal of criticality by July 4, 2026. Executive Order 14301, §5
- 18 June 2025. DOE opened applications for construction and operation of qualified test reactors outside the national laboratories. The initial window ran through July 21, with later applications on a rolling basis. DOE program and application
- 12 August 2025. DOE announced eleven initial projects across ten companies, including two Oklo projects, for work through its authorization process. DOE initial selections
- 4 June 2026. DOE reported that Antares Nuclear’s Mark-0 completed a zero-power fueled criticality demonstration at Idaho National Laboratory. DOE Mark-0 release
- 18 June 2026. DOE reported that Ward 250 completed its zero-power fueled criticality demonstration at the Utah San Rafael Energy Lab in Emery County. DOE described it as the first DOE-authorized reactor built outside a national laboratory. DOE Ward 250 release
- 30 June 2026. Deployable Energy’s Unity reached zero-power fueled criticality at Idaho National Laboratory. DOE announced it July 1 and counted it as the third demonstration. DOE Unity release
- 4 July 2026. Aalo-X completed a zero-power fueled criticality demonstration at Idaho National Laboratory. DOE announced it July 6 and counted it as the fourth DOE-authorized advanced reactor to reach criticality. DOE Aalo-X release
- 5 August 2026. The Groves Isotope Test Reactor reached criticality in Lockhart, Texas. DOE reported the result the next day and identified it as the fifth DOE-authorized advanced reactor to reach criticality that summer. DOE Groves release
DOE’s retrospective places Mark-0, Unity and Aalo-X at Idaho National Laboratory and Ward 250 at the Utah San Rafael Energy Lab. The department counts all four in its July 4 total. EO 14301 §5(a) calls for a pilot outside the national laboratories. DOE’s releases give the test sites and the tally. DOE fact sheet · EO 14301, §5
Later evidence: a test milestone, construction permissions and fuel production
DOE's August 6 Groves release reports that Oklo's Groves Isotope Test Reactor reached criticality the previous night in Lockhart, Texas. August 5 is inferred from that relative wording; the exact physical time is unstated. DOE calls it the fifth DOE-authorized advanced reactor to reach criticality that summer. This is an attributed program milestone, not an independently reconstructed census. The release describes a future commercial isotope-producing variant still in development; continuous operation, commercial NRC approval, isotope production and delivery are separate findings.
The saved finding belongs to the Chronicle's August 8 Federal Government Weekly Delta — Full Merge, section 2, “Oklo Groves reached criticality.” That inquiry was a bounded whole-government delta through August 8, not a reactor census; its vault landing controls over the workbench wave. The exact DOE release was reread for this reconciliation.
The August 18 energy, manufacturing and materials map asks which companies can turn federal position into accepted output. Its row/source registry preserves three relevant, distinct returns:
- TerraPower / Natrium: active federal cost share and an issued construction permit; fuel, operating license, commissioning and generation remain separate. Exact edge w2-energy-terrapower-007, source w2-src-terrapower, DOE March 9 construction-permit notice.
- Kairos / Hermes: construction permission and build activity; operating authorization, fuel loading and criticality remain separate in that saved reading. Exact edge w2-energy-kairos-009, source w2-src-kairos, NRC Hermes licensing page.
- American Centrifuge Operating: demonstration HALEU production and a definitive expansion contract; commercial-scale output is a further question. Exact edge w2-mat-centrus-028, source w2-src-haleu, DOE HALEU enrichment services.
Those company findings retain the map's August 18 cutoff. The three selected edges and their source objects were reconciled here; the full registry was not recertified. They do not establish that these projects were authorized under the DOE pilot or caused by the four orders. Fusion's scientific, capital and licensing sequence remains with the existing commercialization bridge and project registry, under their own saved cutoffs.
Reactor licensing paths, hearings, fees and ownership
Reviewed September 7, 2026: the six remaining original Reactor filings. Their questions complement the earlier orders and pilot: which designs can enter a path, what safety evidence carries over, how a decision can be contested, what review costs, and who may own a licensee. Keeping these questions together makes the nuclear-revival thesis testable against particular legal changes and eventual project results.
| Filing / original primary source | Distinct clocks | What the source establishes |
|---|---|---|
| Part 57 microreactor proposal | Dated 2026-04-29; filed 2026-04-30 08:45; published 2026-05-01, 91 FR 23628–23766. Comments due 2026-06-15 at 23:59 Eastern. Correction filed 2026-05-14 08:45 and published 2026-05-15, 91 FR 27870–27871. | Proposed optional microreactor path for qualifying designs, with conditional construction permission and separate operating approval. The May 15 correction does not finalize the framework. |
| Prior DOE/Defense design evidence | Dated 2026-03-31; filed 2026-04-01 08:45; published 2026-04-02, 91 FR 16584–16588. Comments due 2026-05-04. | Proposed reuse of tested DOE/Defense safety evidence in NRC review, with a mapping to NRC requirements and changed conditions. Authorization alone does not convert into a commercial license. |
| Contested adjudications proposal | Dated 2026-02-27; filed 2026-03-02 08:45; published 2026-03-03, 91 FR 10450. Comments due 2026-04-02. | Proposed changes to merits submissions, discovery and contested proceedings. Filing windows vary; appeals sit outside the fixed EO timeline. |
| Fusion-machine framework proposal | Dated 2026-02-23; filed 2026-02-25 at 08:45 (timezone not specified in filing line); published 2026-02-26, 91 FR 9476–9498. Comments due 2026-05-27. NRC selected the Part 30 approach on 2023-04-13. NEIMA enacted 2019-01-14 already set 2027-12-31; ADVANCE enacted 2024-07-09 retained that date and separately required a section 205(c) report within one year (2025-07-09). No final-rule effective date established by this proposal. | Proposed Part 30 byproduct-material framework, following NRC’s 2023 policy choice and ADVANCE’s substantive definitions. The pre-existing NEIMA deadline and state/project licensing clocks remain separate. |
| FY2026 fee final rule | Dated 2026-06-05; filed 2026-06-15 08:45; published 2026-06-16, 91 FR 36470–36509. General effectiveness 2026-08-17; fixed caps start 2026-10-01. Hourly rates begin with the first full pay period after general effectiveness. | Final fee rule generally effective August 17; fixed caps begin October 1. Hourly billing remains. Caps cover requested activities involving a final safety evaluation; decision deadlines are deferred. |
| Foreign ownership exceptions | Proposal and direct final dated 2026-04-06; filed 2026-04-22 08:45; published 2026-04-23. Confirmation dated 2026-06-03; filed 2026-06-04 08:45; published 2026-06-05. Direct final effective 2026-07-07. | The companion April 23 direct final rule was confirmed June 5 as effective July 7. Exceptions concern listed eligible foreign interests in utilization facilities, subject to NRC’s non-inimicality determination; production-facility restrictions remain. |
The ownership entry has a confirmed later state: the April 23 direct final rule and June 5 confirmation establish July 7 effectiveness. The 37 listed jurisdictions comprise 36 eligible OECD members plus India; the July 9, 2024 statutory sanctions screen excludes Turkey. Eligibility is not evidence of a completed investment or an approved ownership structure. The May 15 Part 57 correction corrects the proposal’s presentation, without establishing adoption.
The fusion proposal connects to the existing February 26 chronology below and the commercialization bridge. NRC had selected its byproduct-material approach in 2023. ADVANCE amended the statutory definitions in 2024; the December 31, 2027 optional-framework deadline originated in NEIMA in 2019. A proposed federal framework, an Agreement State’s effective rules and a particular research machine’s license remain parallel evidence, rather than a single nationwide start date for commercial fusion.
The later Groves, construction and fuel findings in the preceding reconciliation answer different questions from these legal mechanisms. A demonstrated test can inform a review; it does not settle the commercial application. A more predictable cost or ownership route can enable a project; it does not measure construction, financing close or electricity delivery. The existing company and fusion project studies retain their saved implementation cutoffs.
Reading scope: the short prior-design proposal, ownership instruments and confirmation were read substantively; the long Part 57, adjudication, fusion and fee rules received selected scope, authority, clock and operative-clause checks. This is a review of the six original filings and their identified correction/confirmation chain, not a full technical review or a later-finality census of every proposal.
Pre-2025 statutory hinge
September 7 legal attribution correction: the 2027 framework deadline originated in NEIMA section 103(a)(4), 132 Stat. 5572. ADVANCE section 205, 138 Stat. 1460–1462 amended definitions and related provisions and required a separate report; it did not originate that deadline. The source chronology and forward clock below now use that attribution. This targeted correction does not advance other evidence cutoffs.
2024-07-09 — ADVANCE Act supplies fusion definitions within the existing NEIMA framework
Entity: Congress; President; Nuclear Regulatory Commission
Clock: statute / federal rulemaking
State after: Atomic Energy Act definitions amended; existing NEIMA December 31, 2027 framework deadline retained
Section 205 of Public Law 118-67 added the term fusion machine to the Atomic
Energy Act and brought radioactive material produced by a fusion machine into
the byproduct-material definition. The December 31, 2027 optional-framework
deadline already existed in NEIMA section 103(a)(4), enacted in 2019; ADVANCE
section 205(b) amended the related provisions and terminology. Section 205(c)
separately required a mass-manufactured-fusion licensing report within one year.
These provisions do not themselves create a final rule or project license.
Sources: Public Law 118-67 · NRC — Fusion and the ADVANCE Act · NRC fusion FAQ
2025
2025-01-20 — national energy emergency declared
Entity: President; executive departments and agencies
Clock: emergency / energy infrastructure
State after: active national-emergency framework
Executive Order 14156 identifies inadequate energy production, transportation and infrastructure as an unusual and extraordinary threat. It directs agencies to use lawful emergency permitting and other authorities to facilitate energy supply. The order repeatedly limits action to what existing law permits.
Source: White House — Declaring a National Energy Emergency
2025-04-23 — accreditation and institutional-value clock separated from research funding
Entity: President; Department of Education; recognized accreditors
Clock: accreditation / Title IV institutional eligibility
State after: policy direction toward student-oriented quality and value
Executive Order 14279 directs the Education Department to realign recognition of accreditors toward high-quality, high-value programs and new educational models. This is an institutional-eligibility and student-aid lane. It is adjacent to, but legally distinct from, agency R&D awards.
Source: White House — Executive Order 14279 PDF
2025-07-23 — qualifying data-center infrastructure receives an acceleration lane
Entity: President; Commerce; Energy; Interior; Defense; EPA; CEQ; Permitting Council
Clock: siting / finance / permitting
State after: federal priority and support pathway
Executive Order 14318 defines qualifying projects using alternative thresholds: at least $500 million in committed capital expenditure, more than 100 MW of incremental electric load, protection of national security, or designation by a named Secretary. It directs an initiative that may use loans, guarantees, grants, tax incentives and offtake agreements, plus federal permitting and land actions.
The order covers associated power and technology components. It does not identify every qualifying project or approve any particular parcel.
Source: White House — Accelerating Federal Permitting of Data Center Infrastructure
2025-08-07 — discretionary grant oversight shifts toward priority and progress review
Entity: President; OMB; grantmaking agencies
Clock: award design / annual review / termination
State after: senior-appointee review and stronger progress controls directed
Executive Order 14332 directs pre-issuance senior-appointee review of funding opportunities and discretionary awards, annual review for consistency with agency priorities and substantial progress, and revised terms permitting termination when an award no longer advances agency priorities or the national interest. It also directs tighter drawdown authorization and limits on facilities-and-administration costs.
Source: White House — Improving Oversight of Federal Grantmaking
2025-11-24 — Genesis Mission chartered
Entity: President; DOE; OSTP; OMB; NSTC; participating agencies
Clock: platform / mission / interagency integration
State after: operative executive direction
Executive Order 14363 establishes the Genesis Mission and directs DOE to establish the American Science and Security Platform. The platform is to integrate:
- federal and commercial high-performance computing;
- secure cloud AI environments;
- AI agents and scientific foundation models;
- federal, proprietary, open and synthetic datasets;
- autonomous and AI-augmented experimentation and manufacturing tools.
The order also directs metadata and provenance work; coordinated funding opportunities and prizes; fellowships, internships and apprenticeships; standard partnership, data-use and model-sharing agreements; and policies for ownership, licensing, trade secrets and commercialization of AI-directed experimental results.
Every major command is bounded by applicable law, security requirements and available appropriations.
Source: Federal Register — EO 14363
2026
2026-01-20 — DOE frames Tribes as data-center counterparties
Entity: DOE Office of Indian Energy; Tribal Nations and enterprises
Clock: tribal market development
State after: federal opportunity framing
DOE identifies possible tribal roles beyond land leasing: power sales, long-term operations and infrastructure ownership. It also identifies water, community impacts, transmission, interconnection and fiber as constraints. No Tribe is committed by this publication.
Source: DOE — Data Centers: Exploring the Opportunity for Tribes
2026-01-23 — Fusion Energy Sciences receives enacted FY2026 account funding
Entity: Congress; President; DOE Office of Science; Fusion Energy Sciences
Clock: appropriation / account allocation
State after: enacted FY2026 funding; program and project states remain separate
Public Law 119-74 enacted the FY2026 Energy and Water division. The final
explanatory table allocates $805.657 million to Fusion Energy Sciences:
$634.973 million for research and $170.684 million for U.S. ITER construction.
The account total demonstrates appropriated public research capital. It does
not fund every facility, public-private program or 2030s milestone later mapped
by DOE.
Sources: Public Law 119-74 · FY2026 Energy and Water explanatory statement
2026-01-29 — initial Bull Run fusion-license application reported submitted
Entity: Type One Energy; Tennessee Valley Authority; Tennessee Department of Environment and Conservation
Clock: project licensing / initial application
State after: company-reported initial byproduct-material application submitted
Type One Energy reports that it and TVA made an initial submission in
preparation for licensing the Bull Run project under Tennessee's Agreement
State authority. The announcement says the application lays groundwork for
subsequent submissions. The source does not establish completeness acceptance,
a completed review, an issued license, inspection, operating authorization or
electricity production.
This project clock is parallel to NRC's federal rulemaking clock; NRC states
that commercial fusion development is already occurring in and regulated by
Agreement States.
Sources: Type One — initial Bull Run licensing application · NRC fusion FAQ
2026-02-26 — NRC opens the proposed federal fusion-machine framework
Entity: Nuclear Regulatory Commission
Clock: proposed rule / federal licensing framework
State after: proposed rule and draft consolidated guidance published
NRC published a proposed technology-neutral framework for fusion machines and
draft consolidated materials-licensing guidance. The 90-day comment period
closed May 27. Proposal, final rule, effective date, license application, issued
license and operating authorization remain separate states. Federal
rulemaking, Agreement State frameworks and individual project applications are
parallel clocks, not one mandatory sequence.
Source: NRC — fusion-machine rulemaking status
2026-03-17 — Genesis RFA defines the fusion DCP work program
Entity: DOE; Office of Science; Genesis Mission
Clock: funding opportunity / application process
State after: cross-domain RFA opened; no recipient award or platform access
DOE announced an anticipated $293.76 million across all Genesis subjects, not
fusion alone. The RFA describes Phase I awards of $500,000–$750,000 for nine
months and Phase II awards of $6–$15 million over three years. It makes the
fusion DCP concrete through materials datasets, digital twins, real-time
control, tritium/accountancy models, blanket databases, whole-plant repositories
and remote-maintenance tools. Laboratory work may use Field Work Proposals and
non-laboratory awards may use Other Transaction Authority, so one federal award
database cannot by itself prove complete execution.
Sources: DOE RFA announcement · full RFA
2026-04-20 — grid equipment enters the DPA Title III capacity lane
Entity: President; Secretary of Energy
Clock: industrial capacity / grid
State after: DPA section 303 mobilization authority activated for the named capacity field
The presidential determination finds transformers, transmission lines, conductors, substations, high-voltage circuit breakers, power electronics and related inputs essential to national defense. It authorizes purchases, commitments and financial instruments to expand domestic capability.
The object is grid infrastructure and its supply chain—not every project that consumes electricity.
Source: White House — DPA grid-infrastructure determination
2026-04-28 — CFS enters the PJM interconnection process
Entity: Commonwealth Fusion Systems; PJM Interconnection
Clock: project grid application
State after: company application publicly announced; fusion independently confirmed among Cycle 1 applicants
CFS says it submitted the proposed ARC/Fall Line plant to PJM's Cycle 1
interconnection process. PJM independently confirmed that fusion was among the
more than 800 Cycle 1 project applications. Application, queue validation,
studies, executed agreement, upgrades, synchronization and export remain
separate. This is the strongest current U.S. fusion grid-development atom, not
evidence that ARC is connected or operating.
Sources: CFS application announcement · PJM confirmation
2026-05-14 — NSF announces X-Labs
Entity: National Science Foundation
Clock: institutional model / award opportunity
State after: announced funding initiative
NSF announces up to $1.5 billion over a decade for independent, milestone-driven research teams outside traditional institutions. The first topics concern scientific instrumentation and quantum interconnects. This is direct evidence that federal science funding is opening a lane beyond the conventional university principal-investigator laboratory.
Source: NSF — X-Labs initiative
2026-06-04 — U.S.–Japan Genesis partnership includes fusion
Entity: DOE; Japan MEXT; Japan METI; participating laboratories and institutions
Clock: international partnership plan / future appropriations
State after: planned five-year collaboration announced
DOE and the Japanese ministries announced a planned combined $1 billion over
five years, split equally and subject to future appropriations. Eleven joint
teams are intended to connect twelve DOE national laboratories, one Office of
Science user facility and twelve Japanese institutions across fusion, quantum,
biotechnology, advanced materials, particle physics and autonomous laboratories.
The announcement is an institutional and funding plan, not proof of a fusion
facility, experiment or payment under a specific joint project.
Source: DOE — U.S.–Japan Genesis partnership
2026-06-09 — DOE finalizes the fusion roadmap
Entity: DOE Office of Fusion; Fusion Energy Sciences; industry; national laboratories; universities
Clock: strategy / metrics / implementation coordination
State after: final Build-Innovate-Grow roadmap published
DOE's 122-page Fusion Science and Technology Roadmap combines public
infrastructure, foundational research, high-performance computing, AI, digital
twins, public-private programs, supply chains, workforce, standards and
commercialization. It maps six technical challenge areas and near-, mid- and
long-term milestones toward private pilot plants and grid delivery in the
mid-2030s.
The roadmap expressly commits no specific funding. Support remains contingent
on future public-private partnerships and congressional appropriations. Its
facility map also distinguishes existing, enhanced, under-construction,
planned and gap-identified capabilities.
On the same date, Tennessee's technology-neutral Agreement State fusion-machine
rules became effective. Type One had already reported an initial project
application on January 29; the effective framework, application, review and
license disposition remain separate states.
Sources: DOE — finalized roadmap release · DOE — full roadmap · Tennessee — fusion regulations
2026-06-18 — FERC opens the six-grid-operator speed-to-power proceeding
Entity: FERC; six jurisdictional regional grid operators; transmission owners
Clock: tariff / interconnection / ratepayer protection
State after: show-cause and tariff-reform proceedings opened
FERC directs all six regional operators to justify or reform large-load tariffs. The stated categories include application and study processes, cost shifting, co-location, flexible-load service and study of generation serving nearby or co-located load. This is a tariff process, not an automatic interconnection approval.
Source: FERC — large-load integration orders
2026-06-19 — WHAM directly converts plasma kinetic energy to electricity
Entity: Realta Fusion; University of Wisconsin–Madison; WHAM
Clock: physical experiment / power-conversion rung
State after: several-hundred-watt-scale direct-energy conversion demonstrated
A converter installed on WHAM drew multiple amps at about 100 volts during
plasma operation. Realta says this could illuminate a few lightbulbs, but also
states that most converted energy was supplied plasma-heating input and that
the experiment was neither net-electricity production nor large-scale
conversion of fusion-born power. This is a physical intermediate rung between
plasma operation and future power conversion, below engineering gain and grid
delivery. The experiment time is not public; the technical release was
published June 30 at 7:00 a.m. ET.
Sources: Realta technical account · exact publication clock
2026-06-20 — NIF records its eleventh ignition
Entity: Lawrence Livermore National Laboratory; National Ignition Facility
Clock: experimental result / target-gain measurement
State after: repeated laboratory ignition record extended
LLNL reports a 7.9 MJ yield with ±0.4 MJ measurement uncertainty and
approximately 3.8 target gain. Target gain compares fusion yield with laser
energy delivered to the target. It does not count the facility's total energy
use and is not engineering breakeven, electricity or grid delivery.
Source: LLNL — achieving fusion ignition
2026-07-21 — Science: A New Golden Age transmitted
Entity: OSTP Director Michael Kratsios; President
Clock: doctrine / recommendation
State after: official White House design map
The report calls for:
- prioritizing individual scientists over legacy institutions;
- portable fellowships and broader performer eligibility;
- fast grants, long-duration grants, prizes, advance market commitments, regranting and experimental funding mechanisms;
- metascience units and portfolio evaluation;
- industry–university–federal research partnerships;
- open access to federal and university facilities;
- practical technical training and alternative scientific-career paths;
- Genesis-scale compute, data, model and autonomous-laboratory infrastructure.
Its horizon section imagines blockchain contribution records, DAOs, distributed ledgers, smart-contract milestone payments, agent microtransactions and cloud laboratories. The report expressly says the combined system does not yet exist in mature form.
Source: White House — Science: A New Golden Age
2026-07-21 — FY2028 memorandum converts doctrine into agency instructions
Entity: OSTP; OMB; executive departments and agencies
Clock: budget formulation / program implementation
State after: operative administrative guidance
NSTM-5 / M-26-16 directs agencies to reflect the priorities in FY2028 budget submissions. It identifies Genesis support as a central R&D priority and directs attention to scientific foundation models, dataset curation, industrial-scale data capture, open instrument interfaces, standardized data formats, advanced compute and autonomous closed-loop laboratories.
The memorandum also instructs agencies to consider portable direct funding, cross-sector placements, milestone reviews, fast grants, prizes, advanced market commitments, regranting, quadratic funding and eigenfunding. These mechanisms remain bounded by agency authority, conflict rules, scientific rigor and appropriations.
Source: White House — NSTM-5 / M-26-16
2026-07-22 — Genesis selects 278 projects for negotiations
Entity: DOE; Genesis Mission; selected laboratories, universities and companies
Clock: selection / award negotiation
State after: named cross-domain portfolio selected; executed awards and operating access unproven
The list includes fusion-design orchestration, control twins, materials,
REBCO/magnet manufacturing, a D-T process-loop replica, a multimodal
multi-device foundation model, plant lifecycle engineering, Realta neutral-beam
optimization, gyrotrons, target manufacturing, diagnostic edge AI,
lithium-isotope separation, blanket/neutronics work and alloy scale-up. DOE's
disclaimer controls: all 278 are selections for negotiation. The list supplies
neither a phase nor an amount for each project, and prospective platform access
is not proof of an executed OTA/FWP, logged workflow or physical result.
Sources: DOE announcement · project list
2026-08-15 — DOE activates Energy Without Limits
Entity: Department of Energy
Clock: communications / agenda amplification
State after: finalized fusion roadmap reactivated in official public messaging
At 1:34:04.501 p.m. EDT, DOE published a three-post, five-card X thread
describing fusion, the theoretical energy-density comparison with fission,
national-lab research and the June 9 roadmap. The three-post sequence spans
2.765 seconds. Its official payloads provide no geotag, place or coordinates.
The thread contains no outbound source link and announces no new experimental,
funding, regulatory, facility or electricity object. It is an atomic narrative
event attached to the June 9 policy anchor.
Sources: DOE X — main post · continuation · final card · date/time/place ledger
2026-08 — National Security Science & Technology Strategy becomes public
Entity: President; White House Office of Science and Technology Policy
Clock: strategy / doctrine; cover month only; public availability verified 2026-08-17
State after: national-security mission, resilience, acceleration and protection layer added to federal S&T doctrine
The 24-page strategy supports the 2025 National Security Strategy, says it
satisfies 42 U.S.C. § 19221 and complements NSTM-5 FY2028 R&D priorities. It
organizes national-security S&T around four qualities—focused, resilient, agile
and secure—and five means: workforce, R&D infrastructure, federal R&D funding,
non-Federal partnerships and allies or partners.
The strategy prioritizes battlefield and homeland missions, a national
resilience architecture, acquisition and regulatory acceleration, research
security, inbound and outbound investment control, export and sensitive-data
protection, development-stage funding logic and later OSTP/NSC CET-specific
plans. Appendix A updates the 14-family CET list; Appendix B maps those
families to battlefield, homeland and transformative needs.
The strategy contains no appropriation, agency-by-agency owner matrix,
implementation deadline, metric or reporting cadence. The cover says only
August 2026. PDF creation metadata dated August 14 is not an authoritative
publication, signature or transmittal clock and must not be point-charted.
Sources: official PDF · full-reading delta · preserved source record
Forward clocks created by the source instruments
Unresolved — § 19221 findings report and Congressional transmittal
Congress records transmission of the 2025 National Security Strategy on
2025-12-04. The 90-day calendar date was 2026-03-04. The public August NSSTS
does not include a signed transmittal, receipt record or the separate findings
report contemplated by 42 U.S.C. § 19221. An earlier or nonpublic submission
may exist; do not convert public non-detection into a final noncompliance ruling.
2026-08-21 — Genesis initial-operating-capability target
EO 14363 directs DOE, within 270 days of November 24, 2025 and subject to
available appropriations, to seek an initial operating capability of the
American Science and Security Platform for at least one national challenge.
The August 15 fusion thread does not identify the challenge, platform assets,
users, access rules, completed test or operating result and therefore does not
satisfy this clock by itself.
2026-10-19 — qualifying agency action plans due
The memorandum requires the head of each agency with at least $3 billion in FY2026 R&D budget authority to submit an action plan within 90 days. Each plan must identify specific actions, implementation timelines and responsible offices for the four R&D priority-practice groups. October 19 is 90 calendar days after July 21. The memo directs submission to OMB and OSTP. No public agency plan expressly identified as a submission under this provision, or a public OMB or OSTP receipt list, was located through November 15. NSTM-5 / M-26-16, final page
NSF merit-review criteria and procedures
The National Science Board released *Merit Review for a Changing Landscape* on December 17, 2025, and said it would work with NSF on implementation. On the same day, NSF Mathematical and Physical Sciences leadership described operational changes that gave program officers greater review flexibility while retaining the existing criteria. NSF’s current funding guide continues to specify intellectual merit and broader impacts, with additional criteria where a solicitation provides them. A public NSF instrument adopting the Board’s full recommendations and mapping them to implementation dates was not located through November 15. NSB report announcement · NSF MPS update · NSF funding decisions
FY2028 budget process — program requests become appropriations asks
Agency submissions should show proposed shifts in portfolio composition, Genesis contributions, infrastructure investment, talent programs, funding pilots, cost shares and regional co-location. A budget request is not an appropriation, award or operating capability.
2026-11-24 — first Genesis annual report due under EO 14363
EO 14363 requires DOE to report within one year of the order and annually thereafter on platform status, integration, user engagement, measurable outcomes, partnerships and authority needs. Public availability is not guaranteed by the order.
2027-12-31 — existing NEIMA technology-inclusive framework deadline
NEIMA section 103(a)(4), enacted in 2019 and subsequently amended by ADVANCE,
sets this optional technology-inclusive framework deadline. ADVANCE section 205
did not create the date; its mass-manufactured-fusion report is a separate duty.
A final rule, its effective date, Agreement State implementation and individual
project dispositions must still be recorded separately.
Clock rule
The companion
`FEDERAL_FUSION_DATE_TIME_PLACE_LEDGER_2020-2035.md`
preserves each source clock, timezone, locus, precision defect and later D.C.
chart convention without calculating or interpreting a chart.
The object-level states, eight-company field map and award-accounting chain
live in
`FEDERAL_FUSION_PROJECT_CAPITAL_REGULATORY_REGISTRY_2022-2035.md`.
Never compress these into one “launch” date:
report -> memorandum -> agency plan -> budget request -> appropriation -> funding opportunity -> award or contract -> platform integration -> test -> operating capability -> verified result -> payment or commercialization
For fusion, preserve interacting but parallel clocks:
- communications -> roadmap -> funded mechanism -> verified milestone;
- federal statutory direction -> proposed rule -> final rule -> effective rule;
- Agreement State framework and project application -> completeness -> review -> license -> inspection -> operating authorization;
- site control -> permits -> construction -> equipment -> commissioning;
- queue/request -> studies -> interconnection agreement -> upgrades -> synchronization -> meter -> export;
- reaction -> ignition -> separately measured target/plasma gain -> engineering gain -> heat -> gross electricity -> net electricity -> sustained operation.
Those lanes converge at a named project's licensed, interconnected and measured
commercial operation; none is evidence that the others have completed.