Federal fusion project, capital and regulatory registry, 2022–2035

Evidence cutoff: 2026-08-15
Status: current workbench research; object-level implementation registry
Scope: the eight companies in DOE's Milestone-Based Fusion Development Program, their machines and sites, public capital, verified milestones, regulatory and grid objects, and the Genesis-linked implementation layer
Authority boundary: federal, state, utility, laboratory and local-government records control public-program and regulatory state. Company records establish company designs, contracts, experiments and claims only at the verb and boundary the source supports.

Short answer

DOE's eight Milestone companies are one funding cohort, not eight equivalent U.S. fusion power plants. At the cutoff:

The durable plot is therefore:

appropriation -> program allocation -> selection -> executed instrument -> obligation -> verified milestone -> outlay -> technical output -> commissioned capability -> licensed operation -> net electricity -> grid delivery

No current object reaches the end of that chain.

Object and state rules

  1. A company, legal recipient, machine, site, program award and power plant are separate objects.
  2. selected, negotiating, executed, obligated, verified, outlaid, completed and closed are different capital states.
  3. A preconceptual-design review does not establish machine performance, site control, construction, licensing, interconnection or electricity.
  4. An operating laser, magnet, plasma or repetitive-pulse platform is not silently promoted to an operating fusion power plant.
  5. A PPA, letter of intent, land-use approval or interconnection application is meaningful commercial execution, but none proves construction or grid delivery.
  6. Company power figures remain design or target values until a measured plant record defines heat, gross electricity, internal/recirculating load, net electricity and export.
  7. Foreign-parent, foreign-machine and foreign-site facts remain visible. A U.S. DOE recipient is not automatically a U.S.-sited power project.

Federal Milestone Program baseline

DOE selected the eight recipients on May 31, 2023 and announced that all eight had signed Technology Investment Agreements on June 6, 2024. Payments are conditional on satisfactory review of negotiated milestones. DOE initially obligated $46 million for the first 18 months; the $415 million program figure is a statutory authorization through FY2027, not an appropriation or an award already paid.

DOE's January 16, 2025 public update independently identified five completed early milestones: two for Focused Energy, one for Realta Fusion and two for Thea Energy. It said CFS, Tokamak Energy, Type One, Xcimer and Zap were still working on early science-and-technology milestones at that time. The June 2026 roadmap lists all eight as participating as of April 2026. Later company releases report additional DOE approvals; those retain the provenance company-reported DOE approval unless a DOE action record is cited.

Sources: DOE award list · DOE June 2024 strategy and agreements · DOE January 2025 milestone update · DOE 2026 roadmap

Eight-company field registry

Commonwealth Fusion Systems

FieldCurrent defensible state
Legal/program objectCommonwealth Fusion Systems, LLC; Milestone recipient
Approachhigh-field HTS tokamak
Current machineSPARC, under construction at CFS's Devens, Massachusetts campus; no first plasma or Q > 1 result at cutoff
Power-plant objectARC / Fall Line Fusion Power Station, proposed at the James River Industrial Center, Chesterfield County, Virginia
DOE milestone statefirst-phase agreement described by CFS as worth $15 million; CFS reported DOE validation of its full-scale toroidal-field magnet milestone and an $8 million payment on 2025-09-30
Regulatory/site stateMassachusetts broad-scope radioactive-materials license for SPARC reported granted 2024-10-24; Chesterfield conditional-use permit approved in September 2025
Commercial stateGoogle 200 MW PPA announced 2025-06-30; Eni PPA described as more than $1 billion announced 2025-09-22
Grid stateCFS announced a PJM Cycle 1 interconnection application 2026-04-28; PJM confirmed fusion among Cycle 1 applicants 2026-04-29; no completed study or executed interconnection agreement located
Power claimARC design about 1.1 GW fusion / 400 MWe net; target only
Missing promotion proofSPARC first plasma and gain; ARC final design/FID, construction authorization, interconnection studies/agreement, commissioning and measured electricity

The CFS chain is the strongest current example of commercial objects moving in parallel without yet constituting a plant: license for the research machine, land-use approval for the proposed plant, PPAs and a grid application are four different states.

Sources: SPARC · ARC · $15 million agreement · DOE magnet validation and payment reported by CFS · SPARC license · Chesterfield permit · Google PPA · Eni PPA · CFS PJM application · PJM confirmation

Focused Energy

FieldCurrent defensible state
Legal/program objectFocused Energy Inc.; Milestone recipient with U.S. and German operations
Approachdirect-drive laser inertial fusion plus proton fast ignition; LightHouse architecture and Pearl D-T targets
Current facilitiesDarmstadt targetry laboratory; Austin target-tracking and engagement facility reported open in early 2026; announced Bay Area laser-development facility not proven operating
Plant/site objectBiblis, Germany is the current industrialization/pilot-plant site lane; no named U.S. power-plant site located
DOE milestone stateDOE independently identifies completed high-gain-target modeling and ion-beam-focusing milestones; Focused reports DOE verification of both
Capital state$240 million Series A announced 2026-05-27; RWE entered as investor and site/approval partner
Power targetcompany roadmap: diagnostic chamber first light 2031, implosion 2033, pilot plant 2035 and first grid MWh 2037
Missing promotion proofapproved preconceptual design, U.S. project site, license, construction, PPA/interconnection and architecture-specific ignition/gain

NIF's indirect-drive ignition record is not proof for Focused's distinct driver, target, proton-fast-ignition, chamber or repetition-rate architecture.

Sources: Focused early milestones · company and roadmap · $240 million Series A · Biblis hub

Realta Fusion

FieldCurrent defensible state
Legal/program objectRealta Fusion, Inc.; Milestone recipient
Approachhigh-field axisymmetric/tandem magnetic mirror
Current machineWHAM, a 17 T research prototype at UW–Madison's Physical Sciences Laboratory in Stoughton, Wisconsin; first plasma 2024-07-15
Next project/siteHammir planned at The Realta Forge, OM Station/former Oscar Mayer plant, Madison; site and incentives announced, construction not begun at cutoff
DOE milestone stateDOE identifies completed whole-device modeling of simple-mirror equilibria toward a tandem-mirror scientific-gain goal of at least 5; no public full preconceptual-design approval located
Physical resulton 2026-06-19 a WHAM direct-energy converter drew multiple amps at about 100 volts during plasma operation, enough for a few lightbulbs
Boundarymost converted energy was externally supplied plasma-heating input; Realta expressly says the result was neither net electricity nor large-scale conversion of fusion-born power
Site capitalWisconsin and Madison support described as up to $55 million; publication 2026-07-15 08:00 ET; groundbreaking expected before year-end, not completed
Missing promotion proofHammir construction/commissioning, fusion-dominant direct conversion, gain, power-plant site, license, PPA/interconnection and net electricity

This is a real intermediate rung between plasma operation and power conversion, but it sits below engineering gain, net generation and grid delivery.

Sources: UW first plasma · WHAM direct-energy-conversion technical account · exact publication clock · Forge/Hammir site announcement · WEDC confirmation

Thea Energy

FieldCurrent defensible state
Legal/program objectThea Energy, Inc.; Milestone recipient
Approachsoftware-controlled stellarator using arrays of planar HTS shaping coils
Current hardwarefull-size, full-current, full-field Eos shaping coil reported operated at Kearny, New Jersey on 2026-05-13
Machine/plant objectsEos, planned D-D neutron-source and integrated demonstration machine; Helios, D-T pilot/commercial design; Eos site not announced
DOE milestone stateDOE independently confirms optimized-equilibria downselection and operation of one HTS planar-coil building block; Thea reported DOE certification/approval of the Helios preconceptual design on 2026-01-13
Genesis/AI joinHelios digital twin and surrogate-model collaboration with NVIDIA, Synopsys, Argonne and PPPL announced 2026-06-08; design/model infrastructure, not DCP operation or a plant result
Supply-chain capitalARPA-E selected Thea on 2026-07-09 for up to $20 million to scale domestic modular HTS-magnet production; selection/maximum is not a paid amount
Power targetHelios design about 1.1 GW thermal / 400 MWe net in the 2030s
Missing promotion proofEos site/build/operation, independent DOE approval object, license, plant site, PPA/interconnection and electricity

Sources: DOE stellarator account · Helios design certification reported by Thea · full-scale coil · digital twin

Tokamak Energy Inc.

FieldCurrent defensible state
Legal/program objectU.S. subsidiary at Bruceton Mills, West Virginia; Milestone recipient; operating machine belongs to the UK-centered company system
Approachhigh-field spherical tokamak
Current machineST40 at Oxfordshire, UK; reported 1 MA plasma current and triple product about \(8 +/- 2 x 10^18\) m^-3 keV s in 2025, then paused for the LEAPS upgrade
DOE milestone stateDOE said the company was still working on early milestones in January 2025; no public preconceptual-design approval located
Public-private capital$52 million ST40 upgrade announced 2024-12-05, divided evenly among DOE, UK DESNZ and Tokamak Energy
U.S. plant objectno named U.S. pilot site, license, PPA or interconnection located
Power targetcurrent U.S. design page: 800 MW fusion / 85 MWe net in the mid-2030s; supersedes older up to 200 MWe public language
Boundarytemperature, current and triple product are not energy gain or electricity

Sources: U.S. program page · fusion technology · $52 million ST40 upgrade · ST40 2025 result

Type One Energy — Project Infinity / Bull Run

Project Infinity is an umbrella containing several separate objects:

FieldCurrent defensible state
Approachoptimized stellarator with non-planar HTS magnets
DOE milestone stateDOE's January 2025 state was working on early milestones; Type One's 2025 initial design review was company-chaired with outside experts, not DOE certification
Utility executionTVA Power Service Shops fabrication/welding contracts announced 2025-07-22; actual limited contracts and site preparation, not Infinity Two construction
Commercial stateTVA letter of intent announced 2025-09-19 for potential deployment once commercially ready; not a PPA and expressly gated by TVA Board, planning and regulatory review
Licensing stateType One reported an initial byproduct-material application submitted 2026-01-29; no public application, receipt, docket, completeness finding, disposition, license, inspection or operating authorization located
State frameworkTennessee Chapter 0400-20-14 filed 2026-03-11 at 10:37 a.m., timezone unstated, and effective 2026-06-09; a framework is not a project license
Site-control stateTVA ownership/control and Type One's authorized physical use are publicly established; exact lease/access/site-use instrument and final Infinity Two footprint are not public
Workforce/capital commitmentTennessee Nuclear Fund database: $4.5 million contracted award, 330-job commitment and $223.5 million investment commitment; commitments are not realized totals
Grid stateno public Infinity Two queue request, study, agreement or point of interconnection located

The 350/400 MWe seam

Dated 2025 releases, the January 2026 licensing announcement, TVA's current page and NRC's current page retain 350 MWe. Current Type One copy and TDEC's June 2026 release use 400 MWe from the same stated 800 MW fusion design. No primary change-control record explains the increase. Preserve the values as source versions; do not average them or treat them as two plants.

The January package cannot have been a completed application under Chapter 0400-20-14, which was filed in March and effective in June. Type One calls it an initial filing and TDEC says it laid groundwork for subsequent submissions. Its exact scope—Infinity One, Infinity Two, both, or a staged campus safety basis—remains unresolved.

Sources: TVA fusion page · TVA FY2025 Form 10-K · TVA/Type One cooperative agreement release · PSS contracts · TVA LOI · initial application announcement · TDEC rules release · operative Tennessee rule · NRC Agreement-State activities · ORNL high-heat-flux facility · Tennessee Nuclear Fund

Xcimer Energy

FieldCurrent defensible state
Legal/program objectXcimer Energy Inc.; Milestone recipient
ApproachKrF excimer-laser inertial fusion with stimulated Brillouin scattering and a HYLIFE-type liquid-wall chamber
Current platformPhoenix, operating in a 74,000-square-foot Denver laser bay; demonstrated integrated laser amplification/compression and more than 1 kJ, not a fusion shot or ignition
Next machinesAnvil, planned 200 kJ-on-target step for 2028; Vulcan, planned 4 MJ and upgradeable 12 MJ engineering-breakeven machine at an unselected site
Plant objectAthena, planned roughly 400 MWe architecture in the mid-2030s
DOE milestone stateXcimer reported DOE approval of Athena's preconceptual design and technology roadmap on 2026-06-10
Missing promotion proofDOE action object, Anvil/Vulcan site/build/operation, architecture-specific ignition/gain, license, PPA/interconnection and electricity

NIF's result does not establish performance of Xcimer's KrF driver, target, liquid chamber, repetition rate or wall-plug loop.

Sources: Phoenix operations · Athena design approval reported by Xcimer · current project ladder · commercialization roadmap

Zap Energy

FieldCurrent defensible state
Legal/program objectZap Energy, Inc.; Milestone recipient
Approachsheared-flow-stabilized Z pinch without external confinement magnets or lasers
Plasma machinesFuZE-Q and FuZE-3; FuZE-3's 2025 pressure result is a preliminary path-to-gain metric, not Q > 1
Engineering platformCentury, an operating repetitive pulsed-power/liquid-metal test platform using ordinary hydrogen/helium; it does not produce fusion reactions or neutrons
DOE milestone stateZap reported DOE-certified completion on 2025-02-25 of a three-hour, 1,080-shot Century milestone; it reported DOE approval on 2026-05-19 of an approximately 50 MWe-net-per-module preconceptual design
Power boundaryCentury's reported 39 kW average on 2025-09-30 was electrical input delivered to cables, not generated output
Site/grid stateno selected pilot-plant site, license/application, PPA or interconnection located; Centralia was a feasibility study, not a selected Zap plant
Missing promotion proofDOE action object, fusion-producing integrated platform, gain, plant site, license, commercial contract, interconnection and electricity

Sources: Century milestone · Century input-power result · FuZE-3 pressure result · pilot-design approval reported by Zap

Public-capital ledger

Appropriation and request clocks

All values are nominal dollars. FY2026 is enacted control; FY2027 is a budget request and must not be reported as funded.

ObjectFY2026 enactedFY2027 requestRuling
FES research$634.973M$677.751Menacted vs request
U.S. ITER construction$170.684M$77.500Menacted vs requested reduction
Total FES$805.657M$755.251MFY2027 request is $50.406M below FY2026 enacted
Public-Private Partnerships$100.000M$135.000Mparent program line, not award ledger
Closing the Fusion Cycle$56.238M$89.000Menacted vs request
Fusion Materials/Internal Components$76.411M$68.000Menacted vs request
Theory/Simulation$65.776M$72.540Menacted vs request
Sustain a Burning Plasma$141.661M$140.000Menacted vs request
Discovery Plasma S&T$65.000M$55.900Menacted vs request
DIII-D operations$74.000M$61.000Mrequested operating reduction
NSTX-U operations$50.200M$47.000Mrequested operating reduction
MPEX operations$0$1.000Mstartup request, not operation
Office of Fusion separate account$0$10.000Mfirst requested standalone account; not enacted

FY2026 directs at least $70 million of the $100 million PPP line to the Milestone Program. Absent transfers or other accounts, no more than $30 million within that parent line remains for INFUSE, Private Facility Research and Fusion BRIDGE collectively. A public execution breakout was not located. FIRE is distributed through core FES research lines and must not be added to the PPP line as a separate subaccount.

The FY2026 explanatory statement gives MPEX $25.473 million while DOE's FY2027 capital table reports FY2026 enacted at $25.180 million. Preserve the discrepancy until an execution/control table resolves it. The FY2027 request also includes $8 million for Integrated Blanket/Fuel Cycle Test Facility design; design money is not construction authority.

Sources: P.L. 119-74 · FY2026 explanatory statement · FY2027 FES request · FY2027 Office of Fusion request

Milestone award accounting

USAspending data current through 2026-08-15 records the eight Technology Investment Agreements with cumulative obligations of $110.685 million and linked outlays of $28.490 million.

Recipient / awardCumulative obligationLinked outlayDisplayed award end
Commonwealth Fusion Systems — DESC0024885$33.085M$9.700M2025-12-04
Zap Energy — DESC0024886$17.800M$4.000M2027-06-04
Thea Energy — DESC0024881$13.700M$3.000M2027-06-04
Xcimer Energy — DESC0024890$13.500M$1.500M2026-03-31
Type One Energy — DESC0024888$9.500M$2.000M2025-12-04
Realta Fusion — DESC0024887$8.100M$3.140M2025-12-04
Tokamak Energy — DESC0024889$7.500M$3.000M2026-01-31
Focused Energy — DESC0024883$7.500M$2.150M2025-12-04

The initial June 2024 obligations total exactly $46 million. January 10–15, 2025 revisions add $36.6 million. Only Zap (+$8.3 million on June 1), Thea (+$6.2 million on June 9) and CFS (+$13.585 million on July 13) show positive 2026 revisions in the checked data.

These accounting objects do not supply a one-to-one milestone/payment join. That requires the TIA amendment, verification memorandum, invoice and payment record. An outlay is a disbursement linked to an award; it does not establish the recipient's cash-receipt instant or the technical milestone settled.

CFS's displayed award period ends 2025-12-04 while its current total includes a July 2026 revision. The July amendment and period-of-performance record are a high-priority retrieval item rather than grounds to silently correct the public display.

Sources: USAspending freshness · DOE FES public-private partnerships

Other federal program states

ProgramHighest demonstrated rungMissing next proof
Milestone Programexecuted TIAs -> obligations -> some outlays -> publicly identified verified milestonesamendment-level milestone/payment join, results and closeout
INFUSErecurring selections/vouchers; 20 one-year projects totaling $6.1 million selected 2025-09-10executed CRADA/subcontract, exact voucher value, lab work and delivered result
FIRE round 1six teams selected 2025-01-16executed award/FWP IDs, obligations, work packages and outputs
FIRE round 2seven teams selected 2025-09-10same
Private Facility ResearchFY2025 pilot named in budget/roadmapproject list, host facility, instrument and open research output
Fusion BRIDGEfunded parent-account narrative and roadmap program designsolicitation, consortium agreement, award, cost share, site, construction and operation
Genesis fusion/DCPRFA issued; 278 cross-domain projects selected 2026-07-22 for negotiationsexecuted OTA/FWP, amount, platform access, logged workflow and experiment/result
Office of Fusionorganizational office and roadmap mandatenamed successor, enacted operating account, staff/FTE, governance and reporting cadence
MPEXconstruction projectreconciled baseline/TPC, commissioning, CD-4 and operating test output
IB-FCTF / FPNSstudies, design or mission-need stageCD-0/1, site, construction appropriation, build and operation

FIRE announcements mix current-year tranches, selected multi-year scope and contingent outyears. Official selection material preserves the negotiation/no- commitment disclaimer; do not convert $107 million or $128 million headlines into obligations without PAMS/FWP records. INFUSE selections likewise require the executed instrument and delivered laboratory result.

Sources: FIRE round 1 list · FIRE/INFUSE September 2025 release · INFUSE selections

Genesis and AI-Fusion DCP implementation

The March 17, 2026 Genesis RFA anticipated $293.76 million across all subjects, not fusion alone. Phase I was described as $500,000–$750,000 for nine months; Phase II as $6–$15 million over three years. Laboratory work may use Field Work Proposals while non-laboratory awards may use Other Transaction Authority, so a USAspending-only audit is incomplete.

The RFA makes the fusion DCP more concrete than the roadmap alone. It calls for:

The July 22 selection list includes named work on fusion design orchestration, control twins, structural-material creep/fatigue, born-digital interfaces, REBCO and magnet manufacturing, a D-T process-loop replica, a multimodal multi-device foundation model, plant lifecycle engineering, Realta neutral-beam optimization, PPPL gyrotron delivery, target manufacturing, diagnostic edge AI, lithium-isotope separation, stellarator blanket/neutronics optimization and structural-alloy scale-up.

All 278 projects remain selections for award negotiation in the public record. The list gives neither phase nor project amount, and the promise that awardees will gain platform access is prospective. The separate more than $800 million partner figure mixes compute credits, model access, cloud infrastructure, expertise, partnerships and some direct funding; it is neither all cash nor fusion-specific.

Operating promotion test: an authenticated user or system accesses a named DCP resource, executes a logged cross-resource workflow, calls or informs a physical experiment and receives a traceable result with model, data, instrument, identity, time and correction state.

Sources: Genesis RFA announcement · full RFA · July 22 selections · project list · partner commitments · DIII-D Diag2Diag result

Bottleneck and facility registry

The commercialization race is not only a confinement race. Promote these named bottleneck objects independently of company plant schedules:

ObjectCurrent stateRequired next proof
MPEXconstruction; FY2027 request recognizes cost pressure and retains January 2028 CD-4 targetreconciled baseline/TPC, commissioning and accepted operating result
Integrated Blanket/Fuel Cycle Test FacilityFY2027 request includes design fundingapproved mission need/baseline, site, construction money, build and operation
Fusion Prototypic Neutron Sourceplanning/mission-need laneCD state, site, representative test envelope, construction and qualified output
Bull Run high-heat-flux facilitysite conditioning; end-2027 completion targetsite/instrument record, commissioning and qualified material/component result
Tritium/helium-3 availabilitydirected report clock; public report not locatedreport, inventory/supply, transport, recovery, accountancy and breeding evidence
HTS/REBCO supply chaincompany and Genesis projects activeconductor capacity, repeatable cable/coil fabrication, joints, quench protection, irradiation performance and QA
Remote maintenance / hot cellsroadmap and Genesis project laneradiation-compatible robotics, component exchange, recovery demonstration and RAMI record
DIII-D / NSTX-Uoperating/recovery assets with FY2027 requested reductionsactual availability, weeks of operation, NSTX-U commissioning and experiment results

Material event and publication clocks

These clocks preserve primary-source precision for later astrology. A publication timestamp is not substituted for the underlying agreement, experiment, filing or legal act. A dateline is not proof of web-publication location. The D.C. chart convention and chart selection remain in the separate fusion date/time/place ledger.

Clock IDObjectSource clockLocus / precision ruling
FUS-MILESTONE-SELECT-20230531eight Milestone recipients selected2023-05-31; time not statedDOE selection; date-only
FUS-MILESTONE-TIA-20240603-05eight TIAs signed2024-06-03 through 2024-06-05signature window; exact recipient/signature times and places unretrieved; not a point chart
FUS-MILESTONE-PUB-20240606DOE announces all eight agreements2024-06-06; time not statedonline publication; date-only
FUS-REALTA-WHAM-20240715WHAM first plasma2024-07-15; time not statedphysical event, Stoughton, Wisconsin; date-only
FUS-CFS-LIC-20241024SPARC radioactive-materials license reported granted2024-10-24; time not statedMassachusetts regulatory object; exact issuance clock/place not in checked release
FUS-MILESTONE-UPDATE-20250116DOE identifies five completed early milestones2025-01-16; time not statedDOE publication; date-only; underlying verification clocks unresolved
FUS-ZAP-CENTURY-20250225Zap reports DOE certification of Century milestone2025-02-25; time not statedcompany publication; underlying DOE verification time unresolved
FUS-TYPEONE-IDR-PUB-20250527Type One initial design review release2025-05-27T20:14:26Z / 4:14:26 p.m. EDTexact publication second; Knoxville dateline only, not publication location
FUS-CFS-GOOGLE-20250630Google 200 MW PPA announced2025-06-30; time not statedcontract/publication date; signature clock/place unresolved
FUS-TYPEONE-PSS-PUB-20250722first TVA PSS contracts released2025-07-22T20:13:40Z / 4:13:40 p.m. EDTexact publication second; execution time unresolved
FUS-TYPEONE-LOI-PUB-20250919TVA/Type One LOI released2025-09-20T00:36:27Z / 2025-09-19 8:36:27 p.m. EDTexact publication second; LOI issuance/signature time unresolved
FUS-CFS-ENI-20250922Eni PPA announced2025-09-22; time not statedcontract/publication date; signature clock/place unresolved
FUS-CFS-MAGNET-20250930CFS reports DOE magnet validation and $8M payment2025-09-30; time not statedcompany publication; validation/payment clocks unresolved
FUS-THEA-DESIGN-20260113Thea reports DOE certification of Helios preconceptual design2026-01-13; time not statedcompany publication; DOE decision clock unresolved
FUS-TYPEONE-APP-PUB-20260129Type One initial-application announcement2026-01-29T14:36:00Z / 9:36 a.m. ESTexact publication minute; filing time/place unresolved
FUS-TN-RULE-FILE-20260311rule filing received by Tennessee Secretary of State2026-03-11 10:37 a.m.; timezone unstatedstamped minute; Nashville administrative form locus, delivery mode unresolved
FUS-REALTA-CFS-PUB-20260402Realta/CFS magnet partnership publication2026-04-02 5:00 a.m. ET / 09:00Zexact publication minute; not contract-signature clock
FUS-CFS-PJM-20260428CFS announces PJM interconnection application2026-04-28; time not statedapplication/announcement date; PJM receipt/queue-validation clock unresolved
FUS-THEA-COIL-20260513Thea full-scale shaping-coil operation announced2026-05-13; test time not statedhardware result; Kearny, New Jersey; date-only
FUS-ZAP-DESIGN-20260519Zap reports DOE approval of pilot design2026-05-19; time not statedcompany publication; DOE decision clock unresolved
FUS-FOCUSED-SERIESA-20260527Focused announces $240M Series A2026-05-27; time not statedtransaction/publication date; close/signature clock unresolved
FUS-XCIMER-PHOENIX-20260603Xcimer announces Phoenix operations2026-06-03; operating-start time not statedDenver physical platform; date-only publication, not proof of fusion shot
FUS-THEA-TWIN-20260608Helios digital-twin collaboration announced2026-06-08; time not stateddistributed design/model program; date-only
FUS-XCIMER-DESIGN-20260610Xcimer reports DOE approval of Athena design/roadmap2026-06-10; time not statedcompany publication; DOE decision clock unresolved
FUS-REALTA-DEC-20260619WHAM direct-energy-conversion experiment2026-06-19; time not statedphysical event, Stoughton, Wisconsin; date-only
FUS-REALTA-DEC-PUB-20260630Realta DEC release publication2026-06-30 7:00 a.m. ET / 11:00Zexact publication minute; not experiment time
FUS-THEA-SCALEUP-20260709ARPA-E selects Thea for up to $20M2026-07-09; time not statedfederal selection date; not obligation/payment
FUS-CFS-OBL-20260713USAspending positive obligation revision2026-07-13; transaction time not suppliedfederal award-accounting date; technical milestone not identified
FUS-REALTA-FORGE-PUB-20260715Forge/Hammir site and incentives announced2026-07-15 8:00 a.m. ET / 12:00Zexact publication minute; project site Madison, publication origin unresolved
GEN-FUSION-SELECT-20260722Genesis project selections announced2026-07-22; time not statedselection for negotiation, not award or platform access
FUS-FOCUSED-BIBLIS-20260729Biblis selected as German laser-fusion hub2026-07-29; time not statedBiblis, Germany; date-only

Partial future dates remain non-point-chartable: Infinity Two construction as early as 2028, Infinity One commissioning/startup 2029, Xcimer Anvil 2028, Eos by 2030, and the various mid-2030s plant targets.

Source defects and unresolved seams

  1. NRC's current Agreement-State activities page says CFS is not funded

under the Milestone Program. DOE's award list, roadmap, CFS agreement and reported payment contradict that sentence. Preserve it as an apparent NRC page error pending correction.

  1. Thea, Xcimer and Zap describe DOE-certified/approved designs in detailed

company releases; no matching standalone DOE action record was located.

  1. Type One's 350/400 MWe version conflict lacks a public change-control record.
  2. The January Bull Run application itself, receipt, scope, docket, fee,

completeness finding and review status remain nonpublic or unretrieved.

  1. CFS's current USAspending amount includes a July 2026 revision despite a

displayed 2025 award end. Retrieve the amendment and period extension.

  1. FIRE headline totals, current-year tranches and contingent outyears cannot

be reconciled to executed instruments from public announcements alone.

  1. The FY2026 PPP execution split and Fusion BRIDGE solicitation/award objects

were not located.

  1. A named Office of Fusion successor, separately enacted operating account,

staffing plan and public reporting cadence were not located after JP Allain's departure.

  1. No public artifact was located for the February 22 FES strategy briefing or

the July 22 directed helium-3/tritium report. Record not publicly located,

not noncompliance.

  1. Exact physical-event times are absent for nearly every private-machine

result. Publication clocks must not be substituted silently.

Promotion queue

Event candidates for canonical Energy review

  1. CFS PJM interconnection application — 2026-04-28. Strongest new grid object; application, not study/agreement/connection.
  2. Realta WHAM direct-energy conversion — 2026-06-19. Physical electricity conversion result with explicit input/net/fusion-born boundary.
  3. Thea Helios design certification — 2026-01-13. Company-reported DOE design milestone; not an operating device.
  4. Zap pilot-design approval — 2026-05-19. Company-reported DOE design milestone; not 50 MWe generated.
  5. Xcimer Athena design approval — 2026-06-10. Keep separate from Phoenix operations.
  6. CFS transaction chain. License, local permit, Google/Eni PPAs and PJM application should remain separate atoms if promoted.
  7. Realta Forge/Hammir site/incentives — 2026-07-15. Site selected and incentives announced; construction not begun.

Standing research watches

Interpretation firewall

Sources

Full saved reading

View cited sources (65)

These are the sources cited by this reading. Each source keeps its own date and scope.

Document details and formats
Optional file downloads
For AI readers: complete text and record details
About the dates and filing language
Evidence date
When this document or named claim was checked. A newer collection, export or website date does not update it.
Current, private, Workbench or promotion
These can describe the saved document’s original filing or custody. This public reading preserves that history; publication does not turn its findings into government approval, binding law or newly verified evidence.
Master data and projection
The maintained factual record and a page generated from it. Repeated views are not additional independent evidence.
Provenance and source join
Where a record came from, and the exact reference connecting a claim to its source.
Gate, receipt and operating evidence
A required decision or condition, its documentary record, and evidence that the named activity actually occurred. Permission, delivery and operation stay separate.

Saved research reading. Its original dates and claim limits control; the export date does not refresh the evidence.