Portfolio Evidence and Readiness Matrix

.md · 1 sections · 4896 characters

Source, owner, and dates

workbench: Research Packages/FORTRESS America and Military Installation Energy Independence 2026-09-30/PORTFOLIO_EVIDENCE_AND_READINESS_MATRIX.md

Canonical source SHA-256: f39f0a0b1ae3d6f5371e05079486334cb06d3f0555e04636777e8aeed2ced1ba

Served copy SHA-256: f39f0a0b1ae3d6f5371e05079486334cb06d3f0555e04636777e8aeed2ced1ba

Owner evidence cutoffs: {"fortress-america-installation-energy-independence": "2026-09-30T23:59:59-04:00"}

These are package-level cutoffs, not a claim that this source was rechecked on those dates. Use its own publication and capture dates.

Owners: fortress-america-installation-energy-independence

Portfolio Evidence and Readiness Matrix

Section 1 of 1

# Portfolio Evidence and Readiness Matrix

Status: current bounded comparison; not a scorecard Cutoff: 2026-09-30 ET Rule: record the highest publicly supported state and the exact load/test boundary; do not turn missing evidence into a zero or failure

## Evidence ladder

Code State Minimum receipt
P0 direction signed direction or official program announcement
P1 scope fixed named site, electrical boundary, mission loads, duration and performance standard
P2 authority and money fixed appropriation/obligation or executed agreement with accountable owner/operator
P3 design and permission fixed accepted architecture, interconnection, cyber controls and required license/authorization
P4 built physical completion with material deficiencies identified or closed
P5 commissioned integrated system accepted for service and delivering power
P6 island tested observed no-grid start, transfer and carriage of a defined load
P7 endurance and recovery tested defined load carried for the required duration and safely resynchronized/recovered
P8 recurring readiness repeated exercise, maintenance, fuel, staffing and exception evidence

These are evidence states, not a single maturity score. A prototype can reach advanced technical testing without becoming a base-power service; a commissioned site can still lack public endurance evidence.

## Publicly supportable positions

Object Public state at cutoff Load boundary Highest supportable installation-power state Missing receipt that matters most
FORTRESS America department program established every major installation; “independent power” undefined P0 direction implementation constitution and covered-site list
Army SCI energy portfolio six conditional developer/site pairings solicitation says installation support for at least 14 days after qualifying outage before P2 executed lease/PPA, finance close and site design
Army Janus five vendor/site pairings site requirements not equivalent to full-base load before P2/P3 task award, authorization, accepted design and construction
NWS Crane MMR planned joint Navy/Army Janus deployment by September 2028 critical operations; commercial ownership/operation described P0/P1 planning direction final commercial agreement, authorization, design, construction and accepted delivery
Eielson microreactor notice of intent to negotiate with Oklo up to 5 MW for critical infrastructure P1 proposal final award, NRC license, construction and commissioning
Project Pele prototype construction/test path at INL transportable reactor demonstration, not installation service project-specific build/test lane fueled criticality and published output/test result; then a separate base-service agreement
MCAS Yuma operational public description backup capacity described for 100% of current and projected base requirements P5 publicly described current black-start, load, duration and recovery receipt
MCAS Miramar completed and exercised public exercise supports mission-critical islanding; design description says up to 21 days P6 observed endurance/recovery evidence at the claimed load boundary
SUBASE New London operational microgrid essential functions; 10.75 MW CHP plus first-right 7.4 MW fuel-cell access P5 current black-start/endurance result
Fort McCoy Main Gate operational scope-limited microgrid gate and nearby mission-essential facilities; stated at least 14 days P5 observed 14-day and recovery result
DLA Distribution Sigonella activated tenant-facility microgrid DLA facilities; stated up to 14 days on one fuel load P5 observed endurance and recovery result

## Required portfolio fields

Every future FORTRESS site row should contain:

  1. installation and electrical boundary;
  2. covered mission and excluded loads;
  3. normal, peak and critical load;
  4. generation, storage, fuel and switching architecture;
  5. outage duration and replenishment assumption;
  6. legal authority and financing instrument;
  7. asset owner, emergency operator and site-access rights;
  8. utility interconnection and island permission;
  9. cyber/physical control standard;
  10. construction and commissioning state;
  11. black-start, transfer, island-load and recovery results;
  12. exception list, maintenance clock and next recurring exercise.

## Comparison ruling

The portfolio is heterogeneous by design. Full-load, critical-load, campus, gate and tenant-facility systems cannot be counted as interchangeable “independent bases.” The valid denominator is not project count; it is the number of covered installations whose defined required load has passed the required test for the required duration and remains in recurring readiness.