FEDERAL RESERVE ECCLES 1951 OIG EVALUATION 2026-09-29

.md · 2 sections · 21908 characters

complete text
Source and version

workbench:Research Packages/Fed, Clearing and Treasury/FEDERAL_RESERVE_ECCLES_1951_OIG_EVALUATION_2026-09-29.md

Source SHA-256: f83e5d5752d5844fc3e6cce7f5cdb16ef57eb6323e951bad5e932fcda0ff514c

Evidence cutoffs by research owner: {"banking-artifact:4fbac13660cbf03a89bd": "2026-09-30"}

Saved source text, not a new finding. Markdown notation and table delimiters are retained.

Document contentsFederal Reserve Eccles-1951 OIG evaluation · What drove the increase

Federal Reserve Eccles-1951 OIG evaluation

Lines 1–193 · Section 1 of 2

# Federal Reserve Eccles-1951 OIG evaluation

Report date: 2026-09-29 Evidence cutoff: 2026-09-30 EDT Status: current Workbench research Owner: fed-clearing-treasury Scope: The Federal Reserve OIG's evaluation of management, governance, contract execution, cost growth, design-feature claims and corrective actions for the Marriner S. Eccles and 1951 Constitution Avenue renovation project. This is not a value-for-money opinion, a criminal investigation or an independent verification of every awarded cost.

## Bottom line

The report closes one allegation and opens a much more concrete institutional case.

The decisive plotline is therefore not criminal luxury spending. It is that a self-funded federal agency chose a contract meant to transfer cost risk and then administered it in a way the OIG says resembled uncapped cost-plus, pay-as-you-go construction.

## The four separate clocks

Clock Current state What it does not establish
Criminal The April 2026 Justice Department probe was closed; the OIG found no reasonable grounds for a criminal referral No acquittal after a merits trial; no approval of project management
Administrative misconduct OIG found no Board-policy violation warranting an administrative-misconduct finding No finding that management was effective
Audit and management OIG found repeated contract-execution, cost-control, governance and reporting deficiencies and issued seven recommendations OIG did not price the avoidable loss or rule on overall cost reasonableness
Corrective operation Chairman Kevin Warsh concurred and directed GSA project leadership, an independent cost audit, GMP negotiations, fixed metrics, contract reconciliation and possible remedies A direction is not completed implementation, a recovered dollar or a final cost ceiling

## What the budget figures mean

The OIG distinguishes the renovation budget from the broader multicycle capital budget. These figures should not be collapsed.

Object February 2020 Latest approved figure in the report Later proposal or state
Construction portion $921,000,000 $2,018,000,000, approved December 2024 $2,135,000,000 contractor GMP proposal in January 2026; not agreed as of July 2026
Eccles-1951 renovation project $1,317,000,000 $2,381,000,000, approved December 2024 OIG describes this as the most recently revised renovation budget
Multicycle capital budget that contains the project $1,378,000,000 $2,455,000,000, approved in 2024 Includes acquisition and other project-related capital objects beyond the OIG's narrower renovation-budget line

The OIG also reports that construction was expected to finish in the second quarter of 2024 under the 2020 plan. By August 2026, the expected construction completion date was December 2027.

## The balance-sheet bridge

The Board's own audited financial statements already show the accounting trail that the awarded-cost audit can penetrate. This is the Board of Governors' balance sheet, not a Reserve Bank balance sheet. The Board prepares it under U.S. GAAP on an accrual basis.

Year-end Board construction in process Annual increase
2022 $132,535,471 —
2023 $357,260,135 $224,724,664
2024 $721,702,038 $364,441,903
2025 $1,239,980,443 $518,278,405

The balance increased $1,107,444,972 from year-end 2022 through year-end 2025. The 2025 statements define construction in process as costs incurred for long-term building enhancements for assets that have not entered productive Board service. They separately report $527,426,113 of 2025 capital expenditures and $343,298,787 in 2024.

These public figures are aggregate Board accounts, not an Eccles-1951 subsidiary ledger. They should not be treated as exact project spend: other long-term building enhancements, accruals, retainage and timing differences may also be present. The proximity is nevertheless important. The Board reported $721,702,038 of total construction in process at year-end 2024, while its 2025 capital budget reported $701,600,000 of cumulative Eccles-1951 spending through that same date. The $20,102,038 difference is a reconciliation question, not permission to equate the two measures.

The audit can expose the missing chain beneath the aggregate line:

contract and subcontractor → price package → invoice or pay application → cost code and project ledger → accrued or retained amount → construction in process → placed-in-service component → fixed-asset subsidiary record → useful life and depreciation

That chain can identify which entity supplied plumbing, HVAC, electrical, earthwork, masonry and other components; what the Board capitalized; what it expensed; whether paid or accrued services were actually received; and how the completed project is divided among buildings, improvements, equipment and other depreciable components. The published financial statements reveal only the aggregate construction-in-process line. The independent audit, contract audit files, project cost ledger, pay applications, retainage schedules and eventual placed-in-service entries are the potential route to the actual fixed asset listing.

The Board's 2025 financial-statement auditor issued an unmodified opinion and reported effective internal control over financial reporting. That opinion addresses whether the statements are materially fairly presented; it is not a vendor-level value-for-money opinion and does not answer whether individual awards were well competed or contract services were received.

## The contract failure

### Intended model

The Board chose construction manager at risk (CMAR). In a normally managed CMAR project:

  1. the construction manager joins during design;
  2. the manager supplies evolving whole-project estimates;
  3. owner, designer and manager use those estimates to keep design within a stated cost limit;
  4. the parties establish a guaranteed maximum price (GMP) near the start of construction or substantial design completion; and
  5. the manager then bears material cost and schedule risk above that ceiling, subject to defined exceptions.

### Actual execution

The Board did not obtain the expected risk transfer.

The OIG's core judgment is functional: accumulating scores of awards without an overall ceiling made the arrangement resemble a higher-risk cost-plus reimbursement contract even though the contract form was CMAR.

## The package and competition evidence

By December 31, 2025, the Board had awarded 69 price packages with an initial award value of $1,978,398,480. The contractor's January 2026 proposal showed those packages finishing $26,600,000 below the award total: the Board would receive $21,600,000 and the CMc the contractually capped $5,000,000 share of savings. Fifteen remaining packages were then valued at $62,891,943.

That package-level underrun does not answer whether the total project was well priced. The ceiling was never set before the packages established the price. Including change orders, the OIG compared $2,078,000,000 of awarded construction work through December 2025 with the architect's March 2022 estimate of $1,117,000,000 for the same packages: a $960,000,000 increase.

The sharpest example is mechanical, electrical and plumbing (MEP):

MEP object Earlier estimate Award Increase
Core and shell MEP $178,000,000 in March 2022 $539,000,000 in July and October 2023 $361,000,000 / 203%
Interior fit-out MEP $28,000,000 in March 2022 $155,000,000 in June 2025 $127,000,000 / 454%
All four MEP packages $206,000,000 $694,000,000 $488,000,000 / 237%

Three of the four MEP packages did not receive the contract's preferred minimum of three bids. Those three packages totaled $624,000,000. The construction manager documented limited availability, but the Board did not ask its separate owner representative to produce an independent estimate or validate the large variance. Staff told the OIG they prioritized keeping the schedule moving.

What drove the increase

Lines 193–375 · Section 2 of 2

## What drove the increase

Seven construction categories explain $799,000,000, or 83 percent, of the OIG's $960,000,000 estimate-to-award increase.

Category March 2022 estimate Awarded cost Increase Increase %
Plumbing and HVAC $107,000,000 $346,000,000 $239,000,000 223%
Electrical $91,000,000 $252,000,000 $161,000,000 177%
Earthwork $49,000,000 $158,000,000 $109,000,000 222%
Wood, plastics and composites $16,000,000 $110,000,000 $94,000,000 588%
Metals $32,000,000 $104,000,000 $72,000,000 225%
Masonry $41,000,000 $108,000,000 $67,000,000 163%
Concrete $65,000,000 $122,000,000 $57,000,000 88%
Total $401,000,000 $1,200,000,000 $799,000,000 199%

The nationwide PPI for new office construction rose about 24 percent from March 2022 to January 2026. The OIG cautions that a national index cannot price a unique historic Washington project. It uses the comparison only to show that inflation alone cannot explain increases ranging from 88 to 588 percent.

The report identifies several interacting causes:

The major owner-directed change occurred in January 2023, after construction began: the Board shifted the interior fit-out from predominantly open workspace to predominantly closed offices. That delayed interior-design completion by 21 months, until October 2024, and overall substantial design completion until January 2025. The delay postponed the planned fall 2023 GMP and extended the project's exposure to inflation and redesign costs.

## Why the “luxury” case is not the OIG case

The OIG checked eight criticized features against the November 2019 initial plan and the May 2021 final plan. All were already part of those plans and did not materially explain later increases.

Feature OIG finding or available cost
Chairman/private elevator Existing pre-renovation feature; serves multiple floors, with controlled access at the governors' floor
Private dining spaces Design language also describes conference rooms; Board says they are multiuse, not governor-only
Water features Four historic Eccles fountains remain; four new 1951 fountains were removed in June 2025 because of expected criticism; GMP proposal showed $3,400,000 for water features
Marble Mostly restoration: project team said 87% restored and 13% new; $107,900,000 masonry category includes much more than marble
Garden terrace Description includes original planter boxes and the south lawn over the new garage
Vegetated roofs Estimated at $615,000 and intended for energy, stormwater and roof-life benefits
Glass atria Two scaffolding components cost $6,000,000 in the proposal
Skylights Proposal showed $27,600,000, including restoration of the historic Eccles skylight
Beehives Not part of the Eccles-1951 project

This does not mean every feature was wise or cheap. It means the OIG found the headline features were not material causes of the billion-dollar construction increase.

## The governance failure

The Board of Governors approved the annual operating and capital budgets but, under delegated administrative authority, did not manage daily execution. The Committee on Board Affairs advised the Board and presented budgets but had no project-level decision role. Facility Services held primary execution responsibility, with procurement, financial-management and executive groups supporting or receiving updates.

The OIG found that this structure did not match the project's risk:

The dashboards did label the budget at risk for four consecutive quarters before the 2025 budget increase. But a moving baseline obscured performance against the original promise.

This closely repeats the prior Martin Building pattern. Earlier OIG work had already identified weak preplanning, unreliable estimates, unused cost controls, incomplete status reporting and unclear governance. All 11 earlier recommendations were formally closed, yet several control failures recurred. Closure of a recommendation therefore did not prove that the underlying management capability had become durable.

## The seven OIG recommendations

The OIG recommends that the chairman or a designee:

  1. negotiate a GMP or determine another way to secure best value for project completion;
  2. set fixed project-cost and schedule-success metrics;
  3. cap the CMc fee as the contract provides;
  4. strengthen governance with a responsible oversight body, clear reporting lines and defined Board/Committee on Board Affairs reporting;
  5. exercise the contract audit clause and validate awarded costs, allowances, contingencies, fees and savings;
  6. reconcile CMAR and CMOR requirements against services received and consider reimbursement for paid-but-unreceived services; and
  7. create an agency-wide framework for future significant initiatives, including full-scope budgets, stated cost limits, metrics, accountability, escalation rules and independent senior oversight.

The OIG will follow up quarterly. Recommendation issuance is not closure.

## Warsh's response and the operating-control shift

Chairman Kevin Warsh concurred with the findings and all recommendations in a September 29 response attached to the report. His letter directs:

This is a substantive state change in the control plane. It brings GSA—the executive branch's ordinary federal-property specialist—into project execution even though the Board's special statutory property authority and ownership do not disappear. It is not yet evidence of a signed GMP, completed audit, validated final cost, recovered funds or on-time completion.

## Plotline significance

The report sharpens the earlier self-funding and real-estate map in four ways.

  1. Insulation reached administration, not only monetary policy. The Board's special purse and property authority permitted a large ordinary construction project to sit outside the normal appropriations/FAR/GSA chain.
  2. Retrospective oversight worked, but late. OIG reconstructed the failure after most work had been priced and more than $2,000,000,000 awarded.
  3. The control response partially imports the missing outside discipline. Warsh's GSA Project Executive, independent audit and fixed metrics insert external construction competence without Congress first rewriting the Federal Reserve Act.
  4. Legal vindication and management accountability diverge. Powell and staff were not found criminally or administratively culpable; the institution was still found to have governed the project badly.

The live question is no longer whether the OIG will rule. It is whether the Board and GSA turn the recommendations into enforceable ceilings, verified costs, contract remedies and a durable governance framework.

## Return gates

Trigger Required proof Boundary
GMP finalized or formally rejected Signed agreement or Board/GSA decision identifying the final cost-control substitute A January 2026 proposal is not an agreed ceiling
Independent audit completed Audit report, tested population, exceptions and quantified questioned costs Engagement announcement is not validation
Contract remedies pursued Demand, credit, reimbursement, settlement or adjudicated recovery “Will seek” is not a recovered dollar
Fixed metrics adopted Named budget baseline, schedule baseline, change protocol and reporting owner Another rebased dashboard is not original-baseline accountability
OIG recommendation closure Recommendation-by-recommendation evidence accepted by OIG Management concurrence is not closure
Construction completion Substantial-completion and acceptance records December 2027 remains a forecast
Final project cost Final contract reconciliation, all packages, changes, fees, credits and closeout Approved budget, awarded amount, invoice, cash payment and final cost remain separate
Durable governance reform Issued agency policy and application to another significant initiative A renovation-only workaround is not institutional learning

## Primary source

## Related Workbench owners