# Federal Reserve Eccles-1951 OIG evaluation

**Report date:** 2026-09-29
**Evidence cutoff:** 2026-09-30 EDT
**Status:** current Workbench research
**Owner:** `fed-clearing-treasury`
**Scope:** The Federal Reserve OIG's evaluation of management, governance,
contract execution, cost growth, design-feature claims and corrective actions
for the Marriner S. Eccles and 1951 Constitution Avenue renovation project.
This is not a value-for-money opinion, a criminal investigation or an
independent verification of every awarded cost.

## Bottom line

The report closes one allegation and opens a much more concrete institutional
case.

- The OIG found **no reasonable grounds to believe a federal criminal-law
  violation occurred that required referral to the Attorney General** and no
  Board-policy violation warranting an administrative-misconduct finding.
- The OIG nevertheless found that the Board **did not effectively manage and
  execute** the construction-manager-at-risk contract. The Board failed to use
  the contract's principal cost controls, did not establish an effective cost
  ceiling and governed a multibillion-dollar project through an insufficient
  oversight structure.
- The construction budget rose from **$921,000,000 in February 2020 to
  $2,018,000,000 in December 2024**, an increase of **$1,097,000,000**, or about
  **119 percent**. The broader renovation-project budget rose from
  **$1,317,000,000 to $2,381,000,000**. A January 2026 contractor proposal put
  construction at **$2,135,000,000**, but the Board still had not agreed to a
  guaranteed maximum price as of July 2026.
- The report does **not** conclude that the final project cost is reasonable or
  unreasonable and does not quantify how much of the increase was caused by
  mismanagement. It identifies contributing causes and missed controls.
- Inflation, site conditions, limited competition and design changes all
  mattered. But the OIG rejected inflation as a sufficient explanation for the
  scale of the largest increases.
- Marble, fountains, the garden terrace, skylights, glass atria, private dining
  language and the chairman's elevator were **not material drivers of the cost
  increase**. The OIG found that these features were already in the design that
  supported the initial budget; beehives were never part of this project.

The decisive plotline is therefore not criminal luxury spending. It is that a
self-funded federal agency chose a contract meant to transfer cost risk and then
administered it in a way the OIG says resembled **uncapped cost-plus,
pay-as-you-go construction**.

## The four separate clocks

| Clock | Current state | What it does not establish |
|---|---|---|
| Criminal | The April 2026 Justice Department probe was closed; the OIG found no reasonable grounds for a criminal referral | No acquittal after a merits trial; no approval of project management |
| Administrative misconduct | OIG found no Board-policy violation warranting an administrative-misconduct finding | No finding that management was effective |
| Audit and management | OIG found repeated contract-execution, cost-control, governance and reporting deficiencies and issued seven recommendations | OIG did not price the avoidable loss or rule on overall cost reasonableness |
| Corrective operation | Chairman Kevin Warsh concurred and directed GSA project leadership, an independent cost audit, GMP negotiations, fixed metrics, contract reconciliation and possible remedies | A direction is not completed implementation, a recovered dollar or a final cost ceiling |

## What the budget figures mean

The OIG distinguishes the renovation budget from the broader multicycle capital
budget. These figures should not be collapsed.

| Object | February 2020 | Latest approved figure in the report | Later proposal or state |
|---|---:|---:|---|
| Construction portion | $921,000,000 | $2,018,000,000, approved December 2024 | $2,135,000,000 contractor GMP proposal in January 2026; not agreed as of July 2026 |
| Eccles-1951 renovation project | $1,317,000,000 | $2,381,000,000, approved December 2024 | OIG describes this as the most recently revised renovation budget |
| Multicycle capital budget that contains the project | $1,378,000,000 | $2,455,000,000, approved in 2024 | Includes acquisition and other project-related capital objects beyond the OIG's narrower renovation-budget line |

The OIG also reports that construction was expected to finish in the second
quarter of 2024 under the 2020 plan. By August 2026, the expected construction
completion date was December 2027.

## The balance-sheet bridge

The Board's own audited financial statements already show the accounting trail
that the awarded-cost audit can penetrate. This is the **Board of Governors'
balance sheet**, not a Reserve Bank balance sheet. The Board prepares it under
U.S. GAAP on an accrual basis.

| Year-end | Board construction in process | Annual increase |
|---|---:|---:|
| 2022 | $132,535,471 | — |
| 2023 | $357,260,135 | $224,724,664 |
| 2024 | $721,702,038 | $364,441,903 |
| 2025 | $1,239,980,443 | $518,278,405 |

The balance increased **$1,107,444,972** from year-end 2022 through year-end
2025. The 2025 statements define construction in process as costs incurred for
long-term building enhancements for assets that have not entered productive
Board service. They separately report **$527,426,113** of 2025 capital
expenditures and **$343,298,787** in 2024.

These public figures are aggregate Board accounts, not an Eccles-1951
subsidiary ledger. They should not be treated as exact project spend: other
long-term building enhancements, accruals, retainage and timing differences may
also be present. The proximity is nevertheless important. The Board reported
`$721,702,038` of total construction in process at year-end 2024, while its
2025 capital budget reported `$701,600,000` of cumulative Eccles-1951 spending
through that same date. The `$20,102,038` difference is a reconciliation
question, not permission to equate the two measures.

The audit can expose the missing chain beneath the aggregate line:

> contract and subcontractor → price package → invoice or pay application →
> cost code and project ledger → accrued or retained amount → construction in
> process → placed-in-service component → fixed-asset subsidiary record →
> useful life and depreciation

That chain can identify which entity supplied plumbing, HVAC, electrical,
earthwork, masonry and other components; what the Board capitalized; what it
expensed; whether paid or accrued services were actually received; and how the
completed project is divided among buildings, improvements, equipment and
other depreciable components. The published financial statements reveal only
the aggregate construction-in-process line. The independent audit, contract
audit files, project cost ledger, pay applications, retainage schedules and
eventual placed-in-service entries are the potential route to the actual fixed
asset listing.

The Board's 2025 financial-statement auditor issued an unmodified opinion and
reported effective internal control over financial reporting. That opinion
addresses whether the statements are materially fairly presented; it is not a
vendor-level value-for-money opinion and does not answer whether individual
awards were well competed or contract services were received.

## The contract failure

### Intended model

The Board chose **construction manager at risk** (CMAR). In a normally managed
CMAR project:

1. the construction manager joins during design;
2. the manager supplies evolving whole-project estimates;
3. owner, designer and manager use those estimates to keep design within a
   stated cost limit;
4. the parties establish a guaranteed maximum price (GMP) near the start of
   construction or substantial design completion; and
5. the manager then bears material cost and schedule risk above that ceiling,
   subject to defined exceptions.

### Actual execution

The Board did not obtain the expected risk transfer.

- The CMc was hired in March 2022, after two design phases were complete.
- The solicitation required prices for only **$1,491,543** of preconstruction
  services and general conditions, not an estimate for the full construction
  scope. Modifications later increased the contract above **$2,000,000,000**.
- The project team set an **$857,000,000 stated cost limitation** in April 2020
  but did not keep it current, require the architect to design within it or tell
  the CMc and owner representative about it.
- Contract provisions called for three detailed CMc estimates as design
  evolved. The Board did not formally request a whole-project estimate until
  December 2025, after more than **$2,000,000,000** of work had been awarded.
- The Board determined design was substantially complete in January 2025 but
  still had no agreed GMP in July 2026.
- Instead of several large phases or one project ceiling, the Board divided
  virtually all work into **84 limited-scope price packages**.
- The CMc received a fee equal to **2.95 percent of construction cost** without
  a project-level cap. That reduced the incentive to restrain total cost.

The OIG's core judgment is functional: accumulating scores of awards without an
overall ceiling made the arrangement resemble a higher-risk cost-plus
reimbursement contract even though the contract form was CMAR.

## The package and competition evidence

By December 31, 2025, the Board had awarded 69 price packages with an initial
award value of **$1,978,398,480**. The contractor's January 2026 proposal showed
those packages finishing **$26,600,000 below** the award total: the Board would
receive **$21,600,000** and the CMc the contractually capped **$5,000,000** share
of savings. Fifteen remaining packages were then valued at **$62,891,943**.

That package-level underrun does not answer whether the total project was well
priced. The ceiling was never set before the packages established the price.
Including change orders, the OIG compared **$2,078,000,000** of awarded
construction work through December 2025 with the architect's March 2022 estimate
of **$1,117,000,000** for the same packages: a **$960,000,000** increase.

The sharpest example is mechanical, electrical and plumbing (MEP):

| MEP object | Earlier estimate | Award | Increase |
|---|---:|---:|---:|
| Core and shell MEP | $178,000,000 in March 2022 | $539,000,000 in July and October 2023 | $361,000,000 / 203% |
| Interior fit-out MEP | $28,000,000 in March 2022 | $155,000,000 in June 2025 | $127,000,000 / 454% |
| All four MEP packages | $206,000,000 | $694,000,000 | $488,000,000 / 237% |

Three of the four MEP packages did not receive the contract's preferred minimum
of three bids. Those three packages totaled **$624,000,000**. The construction
manager documented limited availability, but the Board did not ask its separate
owner representative to produce an independent estimate or validate the large
variance. Staff told the OIG they prioritized keeping the schedule moving.

## What drove the increase

Seven construction categories explain **$799,000,000**, or 83 percent, of the
OIG's **$960,000,000** estimate-to-award increase.

| Category | March 2022 estimate | Awarded cost | Increase | Increase % |
|---|---:|---:|---:|---:|
| Plumbing and HVAC | $107,000,000 | $346,000,000 | $239,000,000 | 223% |
| Electrical | $91,000,000 | $252,000,000 | $161,000,000 | 177% |
| Earthwork | $49,000,000 | $158,000,000 | $109,000,000 | 222% |
| Wood, plastics and composites | $16,000,000 | $110,000,000 | $94,000,000 | 588% |
| Metals | $32,000,000 | $104,000,000 | $72,000,000 | 225% |
| Masonry | $41,000,000 | $108,000,000 | $67,000,000 | 163% |
| Concrete | $65,000,000 | $122,000,000 | $57,000,000 | 88% |
| **Total** | **$401,000,000** | **$1,200,000,000** | **$799,000,000** | **199%** |

The nationwide PPI for new office construction rose about 24 percent from March
2022 to January 2026. The OIG cautions that a national index cannot price a
unique historic Washington project. It uses the comparison only to show that
inflation alone cannot explain increases ranging from 88 to 588 percent.

The report identifies several interacting causes:

- post-pandemic labor, material and supply-chain inflation;
- limited subcontractor competition and segmentation that may have discouraged
  bidders, lost bulk-purchasing economies and produced modification premiums;
- excavation beside a high water table, unstable soil and contamination;
- more hazardous-material abatement than expected;
- historic-preservation and security constraints;
- delayed and changing design; and
- contract and governance decisions that left the Board exposed to these
  risks.

The major owner-directed change occurred in January 2023, after construction
began: the Board shifted the interior fit-out from predominantly open workspace
to predominantly closed offices. That delayed interior-design completion by
21 months, until October 2024, and overall substantial design completion until
January 2025. The delay postponed the planned fall 2023 GMP and extended the
project's exposure to inflation and redesign costs.

## Why the “luxury” case is not the OIG case

The OIG checked eight criticized features against the November 2019 initial
plan and the May 2021 final plan. All were already part of those plans and did
not materially explain later increases.

| Feature | OIG finding or available cost |
|---|---|
| Chairman/private elevator | Existing pre-renovation feature; serves multiple floors, with controlled access at the governors' floor |
| Private dining spaces | Design language also describes conference rooms; Board says they are multiuse, not governor-only |
| Water features | Four historic Eccles fountains remain; four new 1951 fountains were removed in June 2025 because of expected criticism; GMP proposal showed $3,400,000 for water features |
| Marble | Mostly restoration: project team said 87% restored and 13% new; $107,900,000 masonry category includes much more than marble |
| Garden terrace | Description includes original planter boxes and the south lawn over the new garage |
| Vegetated roofs | Estimated at $615,000 and intended for energy, stormwater and roof-life benefits |
| Glass atria | Two scaffolding components cost $6,000,000 in the proposal |
| Skylights | Proposal showed $27,600,000, including restoration of the historic Eccles skylight |
| Beehives | Not part of the Eccles-1951 project |

This does not mean every feature was wise or cheap. It means the OIG found the
headline features were not material causes of the billion-dollar construction
increase.

## The governance failure

The Board of Governors approved the annual operating and capital budgets but,
under delegated administrative authority, did not manage daily execution. The
Committee on Board Affairs advised the Board and presented budgets but had no
project-level decision role. Facility Services held primary execution
responsibility, with procurement, financial-management and executive groups
supporting or receiving updates.

The OIG found that this structure did not match the project's risk:

- no fixed project-level cost or schedule success measure;
- unclear oversight roles and accountability;
- a narrow RACI matrix that escalated specified change events but generally did
  not require senior review of in-scope awards, even when those awards exceeded
  estimates by more than **$100,000,000**;
- a trust-based posture in which senior officials avoided second-guessing the
  project team; and
- quarterly dashboards that repeatedly called the project **on track** because
  the reference budget and schedule were reset to the latest approved numbers.

The dashboards did label the budget at risk for four consecutive quarters
before the 2025 budget increase. But a moving baseline obscured performance
against the original promise.

This closely repeats the prior Martin Building pattern. Earlier OIG work had
already identified weak preplanning, unreliable estimates, unused cost controls,
incomplete status reporting and unclear governance. All 11 earlier
recommendations were formally closed, yet several control failures recurred.
Closure of a recommendation therefore did not prove that the underlying
management capability had become durable.

## The seven OIG recommendations

The OIG recommends that the chairman or a designee:

1. negotiate a GMP or determine another way to secure best value for project
   completion;
2. set fixed project-cost and schedule-success metrics;
3. cap the CMc fee as the contract provides;
4. strengthen governance with a responsible oversight body, clear reporting
   lines and defined Board/Committee on Board Affairs reporting;
5. exercise the contract audit clause and validate awarded costs, allowances,
   contingencies, fees and savings;
6. reconcile CMAR and CMOR requirements against services received and consider
   reimbursement for paid-but-unreceived services; and
7. create an agency-wide framework for future significant initiatives,
   including full-scope budgets, stated cost limits, metrics, accountability,
   escalation rules and independent senior oversight.

The OIG will follow up quarterly. Recommendation issuance is not closure.

## Warsh's response and the operating-control shift

Chairman Kevin Warsh concurred with the findings and all recommendations in a
September 29 response attached to the report. His letter directs:

- **GSA to serve immediately as Project Executive**, reporting to the Board of
  Governors and the chair;
- an independent audit of the accuracy and compliance of all awarded costs;
- prompt GMP negotiations;
- fixed budget and schedule metrics;
- a GSA-assisted review of project contracts and the value of services not
  received;
- reimbursement or project credits where warranted; and
- permanent internal standards for future major initiatives.

This is a substantive state change in the control plane. It brings GSA—the
executive branch's ordinary federal-property specialist—into project execution
even though the Board's special statutory property authority and ownership do
not disappear. It is not yet evidence of a signed GMP, completed audit,
validated final cost, recovered funds or on-time completion.

## Plotline significance

The report sharpens the earlier self-funding and real-estate map in four ways.

1. **Insulation reached administration, not only monetary policy.** The Board's
   special purse and property authority permitted a large ordinary construction
   project to sit outside the normal appropriations/FAR/GSA chain.
2. **Retrospective oversight worked, but late.** OIG reconstructed the failure
   after most work had been priced and more than **$2,000,000,000** awarded.
3. **The control response partially imports the missing outside discipline.**
   Warsh's GSA Project Executive, independent audit and fixed metrics insert
   external construction competence without Congress first rewriting the
   Federal Reserve Act.
4. **Legal vindication and management accountability diverge.** Powell and
   staff were not found criminally or administratively culpable; the institution
   was still found to have governed the project badly.

The live question is no longer whether the OIG will rule. It is whether the
Board and GSA turn the recommendations into enforceable ceilings, verified
costs, contract remedies and a durable governance framework.

## Return gates

| Trigger | Required proof | Boundary |
|---|---|---|
| GMP finalized or formally rejected | Signed agreement or Board/GSA decision identifying the final cost-control substitute | A January 2026 proposal is not an agreed ceiling |
| Independent audit completed | Audit report, tested population, exceptions and quantified questioned costs | Engagement announcement is not validation |
| Contract remedies pursued | Demand, credit, reimbursement, settlement or adjudicated recovery | “Will seek” is not a recovered dollar |
| Fixed metrics adopted | Named budget baseline, schedule baseline, change protocol and reporting owner | Another rebased dashboard is not original-baseline accountability |
| OIG recommendation closure | Recommendation-by-recommendation evidence accepted by OIG | Management concurrence is not closure |
| Construction completion | Substantial-completion and acceptance records | December 2027 remains a forecast |
| Final project cost | Final contract reconciliation, all packages, changes, fees, credits and closeout | Approved budget, awarded amount, invoice, cash payment and final cost remain separate |
| Durable governance reform | Issued agency policy and application to another significant initiative | A renovation-only workaround is not institutional learning |

## Primary source

- [Federal Reserve OIG, *Federal Reserve: Evaluation of the Eccles-1951 Renovation Project Management and Construction Costs*, Report 2026-FMIC-B-016, September 29, 2026](https://oig.federalreserve.gov/reports/board-eccles-1951-renovation-construction-costs-sep2026.pdf)
- [Federal Reserve OIG, *Board of Governors Financial Statements as of and for the Years Ended December 31, 2025 and 2024*, Report 2026-FMIC-B-003, March 12, 2026](https://oig.federalreserve.gov/reports/board-financial-statement-audit-mar2026.pdf)
- [Federal Reserve OIG, *Board of Governors Financial Statements as of and for the Years Ended December 31, 2023 and 2022*, Report 2024-FMIC-B-002, March 11, 2024](https://oig.federalreserve.gov/reports/board-financial-statement-audit-mar2024.pdf)

## Related Workbench owners

- `Federal Reserve Non-Core Initiative Governance 2026/README.md`
- `FEDERAL_RESERVE_SELF_FUNDING_AND_REAL_ESTATE_CONTROL_MAP.md`
- `FEDERAL_RESERVE_PURSE_AUDIT_AND_STOPPING_POWER_MAP_2026-09-20.md`
- `FED_NAMED_CAPITAL_AND_TECHNOLOGY_COUNTERPARTY_LEDGER.md`
- `FEDERAL_RESERVE_USES_OF_MONEY_LEDGER_2025.md`