How it entered the Observatory
The saved starting points
- Earliest thread file
- Date
- 2026-07-11
- File
- Sovereign Compute/FEDERAL_TRIBAL_COMPUTE_MOBILIZATION_TIMELINE.md
- Note
- Updated date of the Sovereign Compute timeline, which records EO 14318 on July 23, 2025.
- Katie requests
- Date
- 2026-07-11
- Request
- K01-016
- Package
- Sovereign Compute
- Her words
- Next I want us to looking to data centers being built on indigenous land in U.S.
- Why
- Completely sidesteps anytype of regulation on the land AND they need a revenue source terribly - gambling and casinos are having a terrible year and the reservations need a funding source - in come the data centers.
- Date
- 2026-08-20
- Request
- K03-060
- Package
- Data Center Federal Legal Spine 2025-2026
- Her words
- Hey - I want to follow the war on data centers a bit more - but more from the lens of the actual legislation and regulation, not any opinions.
- Why
- not stated
- Date
- 2026-10-30
- Request
- K14-018
- Package
- Executive Order Source Library
- Her words
- Doing some research and realized we never filled in for Biden's executive orders!!
- Why
- We have both Trump terms and then a huge gap in the middle lol let's fix that.
- Note
- The August 20 request produced the package that holds most of this story. The October 30 request produced the file on EO 14141.
The dated steps
2025-01-14President Biden signed Executive Order 14141, Advancing United States Leadership in Artificial Intelligence Infrastructure, published January 17, 2025 (90 FR 5469).
President Biden signed Executive Order 14141, Advancing United States Leadership in Artificial Intelligence Infrastructure, published January 17, 2025 (90 FR 5469). It set out a process for private AI data centers and clean power on Department of Defense and Department of Energy sites, with land, ownership, security, power, budget and permitting conditions. It was not on the list of orders rescinded on January 20, 2025.
Who acted: The President (Joseph Biden)
Stage: signed
EO 14141, signed January 14, 2025, created an earlier federal-site architecture.
2025-02-28Date in EO 14141 by which the Department of Defense and the Department of Energy were each to identify, if possible, at least three suitable federal sites for AI infrastructure.
Date in EO 14141 by which the Department of Defense and the Department of Energy were each to identify, if possible, at least three suitable federal sites for AI infrastructure.
Who acted: Department of Defense; Department of Energy
Stage: other
By February 28, 2025 if possible each identify at least three suitable Federal sites
2025-03-15Date in EO 14141 by which Interior was to identify Bureau of Land Management sites for clean power and rights-of-way and, if possible, at least five Priority Geothermal Zones.
Date in EO 14141 by which Interior was to identify Bureau of Land Management sites for clean power and rights-of-way and, if possible, at least five Priority Geothermal Zones.
Who acted: Department of the Interior (with Defense and Energy)
Stage: other
Date note: The order map label gives 'March 15' with no year; the year 2025 is the year of the same map's February 28, 2025 date. No file writes '2025-03-15'.
March 15 BLM-site identification for clean power/right-of-way and,if possible,at least five Priority Geothermal Zones
2025-03-31Date in EO 14141 for competitive solicitations for AI infrastructure on the selected federal sites, each to close within 30 days.
Date in EO 14141 for competitive solicitations for AI infrastructure on the selected federal sites, each to close within 30 days.
Who acted: Department of Defense; Department of Energy (Interior and Justice also named in the instruction)
Stage: other
Date note: The order map label gives 'March 31' with no year; the year 2025 is the year of the same map's February 28, 2025 date. No file writes '2025-03-31'.
March 31 competitive solicitations closing within 30 days
2025-06-30Date in EO 14141 for choosing winning proposals, which would give the winners the opportunity to apply for permits.
Date in EO 14141 for choosing winning proposals, which would give the winners the opportunity to apply for permits.
Who acted: Department of Defense; Department of Energy (Interior and Justice also named in the instruction)
Stage: other
Date note: The order map label gives 'June 30' with no year; the year 2025 is the year of the same map's February 28, 2025 date. No file writes '2025-06-30'.
June 30 winning proposals/opportunity to apply for permits
2025-07-23 Turning pointPresident Trump signed Executive Order 14318, Accelerating Federal Permitting of Data Center Infrastructure, published July 28, 2025 (90 FR 35385).
President Trump signed Executive Order 14318, Accelerating Federal Permitting of Data Center Infrastructure, published July 28, 2025 (90 FR 35385). It defines a data-center project as more than 100 MW of new load for AI work, and a 'Qualifying Project' as one with at least $500 million of committed spending, more than 100 MW of new load, a national-security purpose, or a Secretary's designation. It tells Commerce, with the Office of Science and Technology Policy, to launch a financial-support initiative (section 3); agencies to report categorical exclusions to the Council on Environmental Quality within 10 days (section 5); the Federal Permitting Improvement Steering Council's Executive Director to route projects under FAST-41 (section 6); the Environmental Protection Agency to change rules and write Brownfield and Superfund guidance within 180 days (section 7); the Army to review nationwide water permits within 180 days (section 8); and Interior, Energy and Defense to offer federal land (section 9). Section 4 revokes EO 14141.
Who acted: The President (Donald Trump)
Stage: signed
EO 14318, signed July 23, 2025 and published at 90 FR 35385, defines a “Data Center Project” as a facility requiring more than 100 MW of new load for specified AI workloads.
2025-07-24DOE selected four of its sites for future solicitations for AI data centers and energy projects: Idaho National Laboratory, Oak Ridge, Paducah and Savannah River.
DOE selected four of its sites for future solicitations for AI data centers and energy projects: Idaho National Laboratory, Oak Ridge, Paducah and Savannah River.
Who acted: U.S. Department of Energy (DOE)
Stage: other
DOE selected four federal sites for solicitations.
FEDERAL_DATA_CENTER_CLAIM_FIREWALL_AND_WATCHBOARD_2026-08-20.md
2025-08-02Ten-day date in section 5(a) of EO 14318 for each relevant agency to tell the Council on Environmental Quality (CEQ) which categorical exclusions it already has. (A categorical exclusion is a class of actions an agency has found needs no full environmental review.)
Ten-day date in section 5(a) of EO 14318 for each relevant agency to tell the Council on Environmental Quality (CEQ) which categorical exclusions it already has. (A categorical exclusion is a class of actions an agency has found needs no full environmental review.)
Who acted: Each relevant agency (to the Council on Environmental Quality)
Stage: other
Agencies submit existing CE inventories to CEQ within 10 days: Aug. 2, 2025; identify possible new or adopted CEs.
2025-09-09DOE issued a request for applications for applicant-funded long-term leases for AI data centers and energy projects on about 44,000 acres at Idaho National Laboratory, with an initial date of November 7 and rolling review after it.
DOE issued a request for applications for applicant-funded long-term leases for AI data centers and energy projects on about 44,000 acres at Idaho National Laboratory, with an initial date of November 7 and rolling review after it.
Who acted: U.S. Department of Energy (DOE)
Stage: request for information or comment
RFA for applicant-funded long-term leases on about 44,000 acres; rolling after initial Nov. 7 date.
2025-09-29EPA began giving priority handling to new-chemical submissions under section 5 of the Toxic Substances Control Act (TSCA) that are documented as serving qualifying data-center projects.
EPA began giving priority handling to new-chemical submissions under section 5 of the Toxic Substances Control Act (TSCA) that are documented as serving qualifying data-center projects. The review standards did not change.
Who acted: U.S. Environmental Protection Agency (EPA)
Stage: in operation
EPA accepts qualifying new-chemical submissions for priority handling from September 29, 2025.
2025-09-30DOE issued a competitive request for proposals for applicant-funded leases for AI data centers and energy projects at two sites at Oak Ridge.
DOE issued a competitive request for proposals for applicant-funded leases for AI data centers and energy projects at two sites at Oak Ridge.
Who acted: U.S. Department of Energy (DOE)
Stage: request for information or comment
Competitive RFP for applicant-funded leases at two sites.
2025-09-30NNSA issued a request for proposals for long-term lease development for AI infrastructure and energy generation on ten tracts totaling 3,103 acres at the Savannah River Site.
NNSA issued a request for proposals for long-term lease development for AI infrastructure and energy generation on ten tracts totaling 3,103 acres at the Savannah River Site.
Who acted: National Nuclear Security Administration (NNSA), within DOE
Stage: request for information or comment
Invites proposals for long-term lease development across ten tracts totaling 3103 acres.
2025-10-15The Air Force asked for long-term lease proposals for commercial AI data centers at five installations (Arnold, Davis-Monthan, Edwards, Joint Base McGuire-Dix-Lakehurst and Robins), for projects that meet EO 14318's 'Qualifying Project' tests of more than 100 MW of new load and at least $500 million.
The Air Force asked for long-term lease proposals for commercial AI data centers at five installations (Arnold, Davis-Monthan, Edwards, Joint Base McGuire-Dix-Lakehurst and Robins), for projects that meet EO 14318's 'Qualifying Project' tests of more than 100 MW of new load and at least $500 million. It sought fair-market lease payment and kept a right of first refusal on any proposed on-site power plant.
Who acted: Department of the Air Force (Air Force Civil Engineer Center opportunities page)
Stage: request for information or comment
Closed Air Force request for lease proposals for EO 14318 “Qualifying Projects”: greater than 100 MW new load and at least $500 million.
PUBLIC_MILITARY_COMPUTE_AND_DATA_CENTER_OVERLAP_MAP_2026-08-20.md
date not given (after October 15, 2025; before August 20, 2026)Arnold Air Force Base posted a notice that it received no proposal for an AI data center under the five-installation request.
Arnold Air Force Base posted a notice that it received no proposal for an AI data center under the five-installation request.
Who acted: Department of the Air Force (Arnold Air Force Base notice)
Stage: stated by the body
Arnold reported no proposal
2025-11-04DOE issued a request for offers for applicant-funded long-term leases for AI data centers and energy projects at its Paducah site, with offers due January 30, 2026.
DOE issued a request for offers for applicant-funded long-term leases for AI data centers and energy projects at its Paducah site, with offers due January 30, 2026.
Who acted: U.S. Department of Energy (DOE)
Stage: request for information or comment
Invites applicant-funded long-term lease offers due January 30, 2026.
2025-11-17DOE made categorical exclusion determination CX-270875 for a proposed lease of 189 acres at its Portsmouth site.
DOE made categorical exclusion determination CX-270875 for a proposed lease of 189 acres at its Portsmouth site.
Who acted: U.S. Department of Energy (DOE)
Stage: approved or adopted
DOE proposes to lease 189 acres at Portsmouth.
2026-01-08The Corps published final reissued nationwide permits (91 FR 768), effective March 15, 2026.
The Corps published final reissued nationwide permits (91 FR 768), effective March 15, 2026. Nationwide Permit 39 names data centers as commercial and institutional development, generally with a limit of half an acre of waters lost and a notice before construction.
Who acted: U.S. Army Corps of Engineers (files write 'Army')
Stage: published
Final reissued NWPs published Jan. 8, 2026, effective Mar. 15; NWP 39 expressly lists data centers.
2026-01-19180-day date in section 8(b) of EO 14318 for the Army to review the nationwide permits and decide whether a permit for data-center activities is needed.
180-day date in section 8(b) of EO 14318 for the Army to review the nationwide permits and decide whether a permit for data-center activities is needed. The notes record the January 8 reissue (step 17) and no review or decision by the Assistant Secretary under the order.
Who acted: Secretary of the Army, acting through the Assistant Secretary of the Army for Civil Works
Stage: other
Review NWPs within 180 days: Jan. 19, 2026; determine whether activity-specific permit needed.
2026-01 (no day given)An OSTP retrospective of January 2026 says EO 14318 'launches' financial support for qualifying projects.
An OSTP retrospective of January 2026 says EO 14318 'launches' financial support for qualifying projects.
Who acted: Office of Science and Technology Policy (OSTP), in the Executive Office of the President
Stage: stated by the body
OSTP January 2026 retrospective says the order “launches” support.
2026-01 (no day given)EPA issued 'Guidance on Redevelopment of Superfund and Brownfield Sites as AI Data Centers', with screening, liability and reuse points, and public mapping and screening tools.
EPA issued 'Guidance on Redevelopment of Superfund and Brownfield Sites as AI Data Centers', with screening, liability and reuse points, and public mapping and screening tools. It names no sites and waives no cleanup duty.
Who acted: U.S. Environmental Protection Agency (EPA)
Stage: published
Where the files differ: Date: the legal spine and audit files give January 2026; the object registry gives 2026-01-19 and says that is the order's deadline date used for the audit.
EPA issued January 2026 reuse guidance and public mapping/screening tools.
2026-02-04DOE made categorical exclusion determination CX-270900 for an easement for AEP's five 138-kV lines at Portsmouth, with 3.5 miles of new right-of-way plus rebuilding.
DOE made categorical exclusion determination CX-270900 for an easement for AEP's five 138-kV lines at Portsmouth, with 3.5 miles of new right-of-way plus rebuilding.
Who acted: U.S. Department of Energy (DOE)
Stage: approved or adopted
AEP easement for five 138-kV lines, 3.5 miles new ROW plus rebuild.
2026-02-26 Turning pointPike County Portsmouth DC LLC, an SB Energy subsidiary, entered into a lease with DOE on February 26, 2026, according to SB Energy's September S-1/A. GAO records 189 acres.
Pike County Portsmouth DC LLC, an SB Energy subsidiary, entered into a lease with DOE on February 26, 2026, according to SB Energy's September S-1/A. GAO records 189 acres. SB Energy expects one data-center building on DOE land and most campus buildings on private land. The notes do not record the rent, duration or renewal terms.
Who acted: Pike County Portsmouth DC LLC (an SB Energy subsidiary) and the U.S. Department of Energy (DOE)
Stage: lease entered (per the lessee's SEC filing)
[{'text': 'SB Energy’s September S-1/A identifies Pike County Portsmouth DC LLC as the subsidiary that entered into a DOE lease on February 26, 2026. GAO records 189 acres.', 'file': 'Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_RETURN_REFRESH_2026-10-05.md'}, {'text': 'SB Energy expects one data-center building on DOE land and most campus buildings on private land.', 'file': 'Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_RETURN_REFRESH_2026-10-05.md'}]
2026-03-15The reissued nationwide permits, including Nationwide Permit 39 naming data centers, took effect.
The reissued nationwide permits, including Nationwide Permit 39 naming data centers, took effect.
Who acted: U.S. Army Corps of Engineers
Stage: took effect
Army reissued nationwide permits; NWP 39 expressly lists data centers and took effect March 15, 2026.
2026-03-20 Turning pointDOE said an SB Energy affiliate is leasing an initial 189 acres of federal land at Portsmouth (the PORTS Technology Campus) and that groundbreaking took place March 20, 2026.
DOE said an SB Energy affiliate is leasing an initial 189 acres of federal land at Portsmouth (the PORTS Technology Campus) and that groundbreaking took place March 20, 2026. The same Commerce and DOE announcement linked $33.3 billion of planned Japanese-backed power investment to the U.S.-Japan agreement. The files say the FAST-41 campus also takes in private land next to the site; SB Energy expects one data-center building on DOE land and most campus buildings on private land (September S-1/A). The lease itself was entered February 26, 2026 (step 22).
Who acted: U.S. Department of Energy (DOE), with the U.S. Department of Commerce
Stage: other
Portsmouth: DOE publicly confirms an SB Energy affiliate is leasing an initial 189 federal acres; groundbreaking occurred March 20, 2026.
2026-03-26 Turning pointThe Army conditionally selected Carlyle for about 1,384 acres at Fort Bliss, Texas (first operation projected FY2027) and CyrusOne for about 1,201 acres at Dugway Proving Ground, Utah (projected FY2029), and entered exclusive lease negotiations under 10 U.S.C. 2667.
The Army conditionally selected Carlyle for about 1,384 acres at Fort Bliss, Texas (first operation projected FY2027) and CyrusOne for about 1,201 acres at Dugway Proving Ground, Utah (projected FY2029), and entered exclusive lease negotiations under 10 U.S.C. 2667. The developers would finance, build, run and later take down the data centers on Army land. The Army says the deal is not final.
Who acted: Department of the Army
Stage: other
Army conditionally selected Carlyle at Fort Bliss and CyrusOne at Dugway under 10 U.S.C. 2667.
2026-04-01QTS Richmond Technology Park Data Center 5 in Virginia was listed as a FAST-41 covered project, which puts its federal permits on a public coordinated schedule.
QTS Richmond Technology Park Data Center 5 in Virginia was listed as a FAST-41 covered project, which puts its federal permits on a public coordinated schedule. At the August 20 check it was in progress, with 2 of 4 processes complete and estimated completion June 11, 2027. The sponsor used ordinary FAST-41 eligibility.
Who acted: Federal Permitting Improvement Steering Council (Permitting Dashboard); U.S. Army Corps of Engineers leading the federal review
Stage: received or under consideration by the deciding body
Where the files differ: Date: the object registry gives 2026-04-01. The Sovereign Compute timeline's open questions refer to 'the covered FAST-41 data-center project approved in April 2025' without naming it. The files do not say whether these are the same project.
Covered; in progress; estimated completion June 11, 2027; 2 of 4 processes complete.
2026-04-09CEQ issued guidance on how agencies create, revise, adopt and apply categorical exclusions.
CEQ issued guidance on how agencies create, revise, adopt and apply categorical exclusions. It has no force of law and creates no data-center categorical exclusion.
Who acted: Council on Environmental Quality (CEQ)
Stage: published
Explains creation, revision, adoption and application of CEs.
2026-04-10The Air Force asked for lease proposals under 10 U.S.C. 2667 for AI data centers on parcels at Joint Base Elmendorf-Richardson (JBER), Eielson Air Force Base and Clear Space Force Station in Alaska.
The Air Force asked for lease proposals under 10 U.S.C. 2667 for AI data centers on parcels at Joint Base Elmendorf-Richardson (JBER), Eielson Air Force Base and Clear Space Force Station in Alaska. It said any government purchase of data-center services or power was not required or guaranteed and would need separate contracts.
Who acted: Department of the Air Force (Air Force Civil Engineer Center, solicitation AFCEC-26-R-0006)
Stage: request for information or comment
Solicitation under 10 U.S.C. 2667 for JBER, Eielson and Clear SFS.
2026-04-29DOE made categorical exclusion determination CX-270956 for an environmental site assessment of the leased Portsmouth Batch 1 property.
DOE made categorical exclusion determination CX-270956 for an environmental site assessment of the leased Portsmouth Batch 1 property.
Who acted: U.S. Department of Energy (DOE)
Stage: approved or adopted
Environmental site assessment of the leased Portsmouth Batch 1 property.
2026-04-29DOE made categorical exclusion determination CX-270955 for a planned lease of about 188 acres, Parcel C, at Paducah.
DOE made categorical exclusion determination CX-270955 for a planned lease of about 188 acres, Parcel C, at Paducah.
Who acted: U.S. Department of Energy (DOE)
Stage: approved or adopted
DOE plans to lease about 188 acres, Paducah Parcel C.
2026-05-04DOE made categorical exclusion determination CX-270971 for a planned lease of about 785 acres, Parcel B, at Paducah.
DOE made categorical exclusion determination CX-270971 for a planned lease of about 785 acres, Parcel B, at Paducah.
Who acted: U.S. Department of Energy (DOE)
Stage: approved or adopted
DOE plans to lease about 785 acres, Paducah Parcel B.
2026-05-13EPA proposed a rule, 'Begin Actual Construction' in the New Source Review (NSR) preconstruction permitting program (91 FR 26958).
EPA proposed a rule, 'Begin Actual Construction' in the New Source Review (NSR) preconstruction permitting program (91 FR 26958). It would separate certain work that emits nothing from construction that needs a major NSR air permit first.
Who acted: U.S. Environmental Protection Agency (EPA)
Stage: proposed
Would distinguish specified non-emitting work from construction requiring a major NSR permit first.
2026-05-29Offers were due under the Alaska lease solicitation.
Offers were due under the Alaska lease solicitation. The solicitation's public history shows updates through July 14, 2026.
Who acted: Department of the Air Force (solicitation AFCEC-26-R-0006)
Stage: scheduled
offers were due May 29, 2026; later public history showed solicitation updates through July 14.
PUBLIC_MILITARY_COMPUTE_AND_DATA_CENTER_OVERLAP_MAP_2026-08-20.md
2026-06-11The PORTS Technology Campus at Portsmouth was listed as a FAST-41 covered project.
The PORTS Technology Campus at Portsmouth was listed as a FAST-41 covered project. At the August 20 check it was in progress, with 0 of 4 processes complete and estimated completion December 23, 2026.
Who acted: Federal Permitting Improvement Steering Council (Permitting Dashboard); U.S. Army Corps of Engineers lead, U.S. Fish and Wildlife Service participating
Stage: received or under consideration by the deciding body
Covered; in progress; estimated completion December 23, 2026; 0 of 4 processes complete on the reviewed page.
2026-06-26 (decision); 2026-07-20 (announcement)BLM approved a right-of-way for the Townsite Data Center in Nevada on June 26 and announced it on July 20, 2026.
BLM approved a right-of-way for the Townsite Data Center in Nevada on June 26 and announced it on July 20, 2026. BLM's NEPA register still showed the decision in its appeal period. The files say public sources differ on the acreage.
Who acted: Bureau of Land Management (BLM), Department of the Interior
Stage: approved or adopted
BLM Townsite right-of-way approval, Nevada, announced July 20, 2026.
2026-06-29The comment period on EPA's 'Begin Actual Construction' proposal closed.
The comment period on EPA's 'Begin Actual Construction' proposal closed. The rule stays proposed.
Who acted: U.S. Environmental Protection Agency (EPA)
Stage: comment period closed
Proposal; comments closed June 29, 2026.
FEDERAL_DATA_CENTER_CLAIM_FIREWALL_AND_WATCHBOARD_2026-08-20.md
2026-07-17EPA updated its 'Clean Air Act resources for data centers' page, which gathers existing air-permit guidance and says state and local agencies issue most permits.
EPA updated its 'Clean Air Act resources for data centers' page, which gathers existing air-permit guidance and says state and local agencies issue most permits.
Who acted: U.S. Environmental Protection Agency (EPA)
Stage: published
Consolidated existing CAA permit/program guidance; confirms state/local agencies issue most permits.
2026-07-20 Turning pointNNSA selected Amentum to negotiate a phased lease at the Savannah River Site for a proposed 1 GW AI data center and about 2 GW of on-site power, first natural gas and later nuclear.
NNSA selected Amentum to negotiate a phased lease at the Savannah River Site for a proposed 1 GW AI data center and about 2 GW of on-site power, first natural gas and later nuclear. The release cites national security and EO 14299. NNSA says the selection is not a final lease award and that negotiation, permits, safety and security review and other federal approvals remain.
Who acted: National Nuclear Security Administration (NNSA), within DOE
Stage: other
Where the files differ: GAO-27-108063's appendix lists a lease as the realty action; GAO's narrative and NNSA's announcement give the negotiations stage.
NNSA selected Amentum on July 20, 2026 to negotiate a phased lease for a proposed 1 GW data center and about 2 GW of on-site generation, initially gas and later nuclear.
PUBLIC_MILITARY_COMPUTE_AND_DATA_CENTER_OVERLAP_MAP_2026-08-20.md
2026-07-29 Turning pointDOE announced that Brookfield was selected to develop and run a 1.8 GW AI data-center campus on about 785 acres at Paducah, and NextEra to build and own 2 GW of gas generation and up to 2.6 GW of storage.
DOE announced that Brookfield was selected to develop and run a 1.8 GW AI data-center campus on about 785 acres at Paducah, and NextEra to build and own 2 GW of gas generation and up to 2.6 GW of storage. Big Rivers would provide wholesale power, Jackson Purchase retail service, and Paducah Power would be community partner. DOE said the power-service agreement is subject to Kentucky Public Service Commission approval. The announcement calls DOE's site-reuse work its 'American Energy Hubs initiative'.
Who acted: U.S. Department of Energy (DOE)
Stage: other
RFO followed by Brookfield selection for 1.8 GW campus and NextEra selection for 2 GW gas plus up to 2.6 GW storage, about 785 acres.
2026-07 (no day given) Turning pointDOE officials told GAO that DOE signed a lease with a private company in July 2026 for the 785-acre Parcel B at Paducah.
DOE officials told GAO that DOE signed a lease with a private company in July 2026 for the 785-acre Parcel B at Paducah. GAO's appendix lists Brookfield/NextEra. The notes do not record the lessee's legal name, the signing day or the lease terms.
Who acted: U.S. Department of Energy (DOE) and a private company the notes do not name (GAO's appendix lists Brookfield/NextEra)
Stage: lease signed (as DOE officials told GAO)
DOE officials told GAO that DOE signed a lease with a private company in July 2026 for the 785-acre Parcel B. GAO’s appendix lists Brookfield/NextEra.
2026-09 (no day given)DOE's September 2026 Community Advisory Board binder for Paducah mapped about 785 acres for an AI data center.
DOE's September 2026 Community Advisory Board binder for Paducah mapped about 785 acres for an AI data center.
Who acted: U.S. Department of Energy (DOE), for the Paducah Community Advisory Board
Stage: published
DOE's September Community Advisory Board materials now map roughly 785 acres for an AI data center.
2026-10-16GAO published its land-use report, recording DOE officials' statement that Oak Ridge's request for proposals for an AI data center was currently paused.
GAO published its land-use report, recording DOE officials' statement that Oak Ridge's request for proposals for an AI data center was currently paused. The report gives no date for the pause or restart decision.
Who acted: U.S. Government Accountability Office, reporting statements by U.S. Department of Energy officials
Stage: reported
Where the files differ: Underlying pause day and current restart state are not given.
GAO's October 16, 2026 report states that DOE officials described Oak Ridge's AI data-center request for proposals as currently paused.
Where it stands
As of 2026-11-15 (latest research file: the Federal Data Center Return Refresh, with federal land and permitting checked through November 15, 2026): EO 14318 is in force and EO 14141 is revoked. On DOE land, Pike County Portsmouth DC LLC, an SB Energy subsidiary, entered a DOE lease at Portsmouth on February 26, 2026 (189 acres; groundbreaking March 20, 2026); DOE officials told GAO that DOE signed a lease with a private company in July 2026 for the 785-acre Parcel B at Paducah, where Brookfield and NextEra are the selected developers and the power-service agreement awaits Kentucky Public Service Commission approval; Amentum is selected to negotiate at Savannah River; Idaho National Laboratory remains at the previously recorded solicitation stage. A November 18 check of GAO's October 16 report adds DOE officials' statement that the separate Oak Ridge commercial AI data-center solicitation was paused; the report gives no pause day or restart decision. On military land, Carlyle (Fort Bliss) and CyrusOne (Dugway) are in exclusive Army negotiations; the Air Force solicitations at five installations and in Alaska have no recorded selection, and Arnold received no proposal. BLM's Townsite right-of-way was in its appeal period at the August 20 check. QTS Richmond and PORTS are FAST-41 covered projects in progress. Nationwide Permit 39 is in effect; EPA's NSR construction rule is proposed with comments closed. DOE calls its site-reuse work the American Energy Hubs initiative. The notes record no section 3 financial-support initiative from Commerce or OSTP as of 2026-11-15.
What comes next
- When
- 2026-12-23
- What
- Estimated completion of the PORTS Technology Campus FAST-41 schedule (as shown at the August 20 check).
- Stage
- scheduled
- Files
- Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md
- When
- 2027-06-11
- What
- Estimated completion of the QTS Richmond Data Center 5 FAST-41 schedule.
- Stage
- scheduled
- Files
- Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md
- When
- FY2027
- What
- Projected initial operation at Fort Bliss (Carlyle).
- Stage
- projected by the Army
- Files
- Data Center Federal Legal Spine 2025-2026/PUBLIC_MILITARY_COMPUTE_AND_DATA_CENTER_OVERLAP_MAP_2026-08-20.md
- When
- FY2029
- What
- Projected initial operation at Dugway (CyrusOne).
- Stage
- projected by the Army
- Files
- Data Center Federal Legal Spine 2025-2026/PUBLIC_MILITARY_COMPUTE_AND_DATA_CENTER_OVERLAP_MAP_2026-08-20.md
- When
- no date given
- What
- Kentucky Public Service Commission decision on the Paducah power-service agreement; lease negotiations at Savannah River, Fort Bliss and Dugway; end of the Townsite appeal period; rolling review at Idaho National Laboratory.
- Stage
- pending
- Files
- Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_RETURN_REFRESH_2026-10-05.md
- Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md
- Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_CLAIM_FIREWALL_AND_WATCHBOARD_2026-08-20.md
What the notes do not record
- The notes do not record a Commerce or OSTP section 3 initiative document, an agency inventory of existing support sent to OSTP, or any loan, guarantee, grant, tax incentive or offtake agreement under section 3.
- The notes do not record the agencies' 10-day categorical exclusion submissions to CEQ, or a new categorical exclusion written for data centers.
- The notes do not record a FAST-41 transparency-project designation by the Permitting Council's Executive Director under section 6(a).
- The notes do not record a list of Brownfield or Superfund sites identified by EPA for qualifying projects under section 7(b).
- The notes do not record programmatic Endangered Species Act consultation under section 8(a).
- The notes do not record a review or decision by the Assistant Secretary of the Army for Civil Works under section 8(b).
- The notes do not record an Interior list of sites or a Secretary's designation of a Qualifying Project.
- The notes do not record the rent, duration or renewal terms of the Portsmouth lease.
- The notes do not record an executed lease at Savannah River, Fort Bliss or Dugway, or a selection at Idaho National Laboratory, Oak Ridge, the four other Air Force installations or Alaska. For Paducah, the notes do not record the lessee's legal name, the signing day or the lease terms.
- The notes do not record the end of the Townsite appeal period or the right-of-way acreage.
- The notes do not record a final NSR 'Begin Actual Construction' rule.
- The notes do not record any result of EO 14141's 2025 dates.
- The notes do not record the date of Arnold's no-proposal notice.
What it touches
- ai-datacenter-power (batch 5 story)
Grid side of the same projects. Its step 12 is EPA's July 16, 2026 Acid Rain Program memo on islanded generators; its touches list EO 14318.
- army-strategic-capital-initiatives (batch 4 story)
The Army's Strategic Capital Initiative leases installation land for power plants under 10 U.S.C. section 2667 (requests June 15, 2026; conditional awards September 18, 2026). No file used here links it to the Fort Bliss and Dugway selections.
- fortress-america (batch 4 story)
Department of Defense program announced September 30, 2026 with an independent-power goal for major installations. No file used here mentions it.
- Federal land leased for artificial intelligence data centers (Department of Energy (DOE) sites, Army and Air Force installations, BLM land)
Folded in: its files are the land steps of this story.
- Department of Energy (DOE)/NNSA Savannah River artificial intelligence data-center and power project (Amentum)
Folded in: its file records the Amentum selection.
- military-microreactors (EO 14299)
The Savannah River release cites EO 14299 (May 23, 2025), which directs DOE to start critical-defense-facility designation for qualifying AI data centers at or coordinated with DOE facilities.
- FY2026 National Defense Authorization Act (NDAA) data-center duties: Navy nuclear pilot (section 321) and Department of Defense (DOD) data-center estimates (section 1531)
FY2026 NDAA (Public Law 119-60, enacted December 18, 2025): section 321 Navy nuclear pilot to start by December 18, 2026; section 1531 military data-center estimates, first update March 1, 2027.
- Federal data-center legislation in the 119th Congress
H.R.9939, No AI Data Centers on Federal Lands Act, introduced July 23, 2026 and referred to House Natural Resources.
- Federal NEPA procedure: Executive Order 14154 section 5, CEQ's removal of its NEPA regulations, and agencies' own procedures
CEQ removed its government-wide NEPA regulations (interim final February 25, 2025; final January 8, 2026). The CEQ guidance and the EPA NSR proposal are also in that thread.
- Trump's January 2025 mass revocation of Biden orders (Executive Order 14148 and successors)
EO 14141 was not among the January 20, 2025 rescissions; EO 14318 section 4 revoked it.
- Department of Energy (DOE) Office of Indian Energy building a tribal data-center market (publications, webinar, FAQ, planned Tribal Data Center Convening)
DOE Office of Indian Energy data-center publications and events for Tribes (January 20, 2026 onward). The Sovereign Compute timeline says EO 14318 does not designate tribal land.
- Department of Energy (DOE) Speed to Power grid funding selections
The October 5 refresh says DOE's Speed to Power page separately lists large-load, transmission, technical-assistance and Tribal-energy actions.
- Southaven, Mississippi xAI/MZX Tech Clean Air Act suit and Department of Justice (DOJ)'s intervention
DOJ moved on June 15, 2026 to intervene in and dismiss a private Clean Air Act suit over the Southaven, Mississippi xAI/MZX Tech facility.