  "id": "eo-14318-datacenter-permitting",
  "title": "Executive Order 14318 (data-center permitting and federal land) and what agencies did under it",
  "one_line": "President Trump signed EO 14318 on July 23, 2025, revoking President Biden's EO 14141 of January 14, 2025; DOE, NNSA, the Army, the Air Force, BLM, EPA, CEQ, the Corps and the Permitting Council then issued site selections, solicitations, categorical exclusions, a confirmed Portsmouth lease (March 20, 2026), conditional selections (Army March 26; NNSA July 20; DOE Paducah July 29, 2026), a BLM right-of-way in appeal, FAST-41 listings and permit and guidance changes; no section 3 financial-support initiative is recorded as of October 30, 2026.",
  "system": "environmental-review-permitting-and-standards",
  "how_this_machinery_works": [
    {
      "line": "The system has no foundation piece. Its definition: 'Agencies review actions under NEPA with their own procedures, FAST-41 and land agencies site infrastructure and grant rights-of-way, State and local bodies permit, EPA and NHTSA set air, fuel, water and fuel-economy standards, and DOE and EPA run cleanups.'",
      "files": [
        "Obsidian vault: 00 - Index/Operation Inch by Inch/Systems Map 2026-11-14/join/out/CANONICAL_SYSTEMS.json"
      ]
    },
    {
      "line": "The firewall file records each named project in five separate stages: proposal or solicitation; selection or agreement; authorization (land, environmental, utility, rate and building); construction and commissioning; operation.",
      "files": [
        "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_CLAIM_FIREWALL_AND_WATCHBOARD_2026-08-20.md"
      ]
    },
    {
      "line": "The executive order map breaks EO 14318 into its instructions by section, with who is addressed and any date.",
      "files": [
        "Obsidian vault: 00 - Index/Operation Inch by Inch/Executive Order Map 2026-11-14/ORDER_MAP_MERGED.json"
      ]
    }
  ],
  "how_it_entered": {
    "earliest_thread_file": {
      "date": "2026-07-11",
      "file": "Sovereign Compute/FEDERAL_TRIBAL_COMPUTE_MOBILIZATION_TIMELINE.md",
      "note": "Updated date of the Sovereign Compute timeline, which records EO 14318 on July 23, 2025."
    },
    "katie_requests": [
      {
        "date": "2026-07-11",
        "request": "K01-016",
        "package": "Sovereign Compute",
        "her_words": "Next I want us to looking to data centers being built on indigenous land in U.S.",
        "why": "Completely sidesteps anytype of regulation on the land AND they need a revenue source terribly - gambling and casinos are having a terrible year and the reservations need a funding source - in come the data centers."
      },
      {
        "date": "2026-08-20",
        "request": "K03-060",
        "package": "Data Center Federal Legal Spine 2025-2026",
        "her_words": "Hey - I want to follow the war on data centers a bit more - but more from the lens of the actual legislation and regulation, not any opinions.",
        "why": "not stated"
      },
      {
        "date": "2026-10-30",
        "request": "K14-018",
        "package": "Executive Order Source Library",
        "her_words": "Doing some research and realized we never filled in for Biden's executive orders!!",
        "why": "We have both Trump terms and then a huge gap in the middle lol let's fix that."
      }
    ],
    "note": "The August 20 request produced the package that holds most of this story. The October 30 request produced the file on EO 14141."
  },
  "actors": [
    {
      "name": "The President (Donald Trump)",
      "role": "Signed EO 14318 on July 23, 2025."
    },
    {
      "name": "The President (Joseph Biden)",
      "role": "Signed EO 14141 on January 14, 2025."
    },
    {
      "name": "U.S. Department of Energy (DOE)",
      "role": "Selected four sites (July 24, 2025); issued the Idaho National Laboratory, Oak Ridge and Paducah solicitations; made the Portsmouth and Paducah categorical exclusion determinations; announced the Portsmouth lease (with Commerce) and the Paducah selections. The files do not name the DOE office that signed each action."
    },
    {
      "name": "National Nuclear Security Administration (NNSA), within DOE",
      "role": "Issued the Savannah River request for proposals and selected Amentum to negotiate. Files write 'NNSA', 'DOE/NNSA' and 'DOE' for these."
    },
    {
      "name": "U.S. Department of Commerce",
      "role": "Named in section 3 of EO 14318 to launch the financial-support initiative; joint announcer of the March 20, 2026 Portsmouth announcement."
    },
    {
      "name": "Office of Science and Technology Policy (OSTP)",
      "role": "Named in section 3 as Commerce's consultee and as the office agencies report existing support to; its January 2026 retrospective says the order 'launches' support."
    },
    {
      "name": "Council on Environmental Quality (CEQ)",
      "role": "Named in section 5 to receive agencies' categorical exclusions and coordinate new ones; issued categorical exclusion guidance on April 9, 2026."
    },
    {
      "name": "Federal Permitting Improvement Steering Council (FPISC) and its Executive Director",
      "role": "Named in section 6 for FAST-41 routing. The QTS Richmond and PORTS projects are FAST-41 covered projects on its Permitting Dashboard; the files say the sponsor used ordinary statutory eligibility."
    },
    {
      "name": "U.S. Environmental Protection Agency (EPA)",
      "role": "Named in section 7. Began priority chemical review (September 29, 2025), issued Brownfield and Superfund guidance (January 2026), proposed the NSR construction rule (May 13, 2026) and updated its Clean Air Act data-center page (July 17, 2026)."
    },
    {
      "name": "Department of the Army; U.S. Army Corps of Engineers; Assistant Secretary of the Army for Civil Works",
      "role": "Section 8 addresses the Secretary of the Army acting through the Assistant Secretary for Civil Works. The Corps reissued the nationwide permits. The Department of the Army made the Fort Bliss and Dugway selections. Files write 'Army' for all three."
    },
    {
      "name": "Department of the Air Force (Air Force Civil Engineer Center)",
      "role": "Issued the five-installation and Alaska lease solicitations."
    },
    {
      "name": "Department of the Interior; Bureau of Land Management (BLM)",
      "role": "Section 9 addresses Interior. BLM approved the Townsite right-of-way."
    },
    {
      "name": "Private parties named by the agencies",
      "role": "An SB Energy affiliate (Portsmouth; the files do not give its legal name); Amentum (Savannah River); Brookfield and NextEra (Paducah), with Big Rivers, Jackson Purchase and Paducah Power; Carlyle (Fort Bliss) and CyrusOne (Dugway); QTS (Richmond). The NSSTS file says the exact project companies are not identified."
    },
    {
      "name": "Kentucky Public Service Commission (state body)",
      "role": "Its approval is needed for the Paducah power-service agreement, as DOE states."
    }
  ],
  "strands": [
    {
      "strand": "The earlier order (EO 14141)",
      "steps": [
        1,
        2,
        3,
        4,
        5
      ]
    },
    {
      "strand": "The order (EO 14318)",
      "steps": [
        6,
        8,
        18
      ]
    },
    {
      "strand": "DOE sites",
      "steps": [
        7,
        9,
        11
      ]
    },
    {
      "strand": "DOE sites: Savannah River",
      "steps": [
        12,
        38
      ]
    },
    {
      "strand": "DOE sites: Paducah",
      "steps": [
        15,
        30,
        31,
        39,
        40,
        41
      ]
    },
    {
      "strand": "DOE sites: Portsmouth",
      "steps": [
        16,
        21,
        22,
        24,
        29
      ]
    },
    {
      "strand": "Military land: Air Force",
      "steps": [
        13,
        14,
        28,
        33
      ]
    },
    {
      "strand": "Military land: Army",
      "steps": [
        25
      ]
    },
    {
      "strand": "Interior land (BLM)",
      "steps": [
        35
      ]
    },
    {
      "strand": "Permitting coordination (FAST-41)",
      "steps": [
        26,
        34
      ]
    },
    {
      "strand": "Review rules (CEQ)",
      "steps": [
        27
      ]
    },
    {
      "strand": "EPA",
      "steps": [
        10,
        20,
        32,
        36,
        37
      ]
    },
    {
      "strand": "Water permits (Army Corps)",
      "steps": [
        17,
        23
      ]
    },
    {
      "strand": "Financial support (order section 3)",
      "steps": [
        19
      ]
    }
  ],
  "steps": [
    {
      "strand": "The earlier order (EO 14141)",
      "date": "2025-01-14",
      "date_exactness": "day given",
      "body": "The President (Joseph Biden)",
      "what": "President Biden signed Executive Order 14141, Advancing United States Leadership in Artificial Intelligence Infrastructure, published January 17, 2025 (90 FR 5469). It set out a process for private AI data centers and clean power on Department of Defense and Department of Energy sites, with land, ownership, security, power, budget and permitting conditions. It was not on the list of orders rescinded on January 20, 2025.",
      "stage": "signed",
      "status_word": "signed (executive order)",
      "path": "presidential-instrument",
      "rests_on": "official record, linked (Federal Register)",
      "quote": {
        "text": "EO 14141, signed January 14, 2025, created an earlier federal-site architecture.",
        "file": "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md"
      },
      "files": [
        "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md",
        "Executive Order Source Library/Biden Backfill 2026-10-30/WAVE_8B3_AI_INFRASTRUCTURE.md"
      ],
      "register_records": [
        "EO 14141",
        "fgm-2025-01-14-eo-14141-federal-site-lease-security-cost-framework"
      ],
      "disagreement": "none recorded",
      "source_check": "none",
      "from_register": false,
      "weight": "step",
      "where_in_the_system": "Presidential instrument signed or revoked",
      "thesis_words": [],
      "what_moves": "functions: directs Defense, Energy and Interior to identify sites and run competitions for private AI infrastructure on federal land",
      "n": 1,
      "movement_type": "Decided"
    },
    {
      "strand": "The earlier order (EO 14141)",
      "date": "2025-02-28",
      "date_exactness": "day given in the order map",
      "body": "Department of Defense; Department of Energy",
      "what": "Date in EO 14141 by which the Department of Defense and the Department of Energy were each to identify, if possible, at least three suitable federal sites for AI infrastructure.",
      "stage": "other",
      "status_word": "deadline; no result recorded in the notes",
      "path": "presidential-instrument",
      "rests_on": "official record, linked (the order)",
      "quote": {
        "text": "By February 28, 2025 if possible each identify at least three suitable Federal sites",
        "file": "Executive Order Source Library/Biden Backfill 2026-10-30/WAVE_8B3_MAP_SOURCE_SNAPSHOT.json"
      },
      "files": [
        "Executive Order Source Library/Biden Backfill 2026-10-30/WAVE_8B3_MAP_SOURCE_SNAPSHOT.json"
      ],
      "register_records": [
        "eo-14141-p02"
      ],
      "disagreement": "none recorded",
      "source_check": "none",
      "from_register": true,
      "weight": "detail",
      "where_in_the_system": "Instruction with a date on an officer or agency",
      "thesis_words": [],
      "what_moves": "nothing recorded",
      "note": "The date fell while EO 14141 was in force.",
      "n": 2,
      "movement_type": "Clock date"
    },
    {
      "strand": "The earlier order (EO 14141)",
      "date": "2025-03-15",
      "date_exactness": "day and month given in the order map; no year written",
      "body": "Department of the Interior (with Defense and Energy)",
      "what": "Date in EO 14141 by which Interior was to identify Bureau of Land Management sites for clean power and rights-of-way and, if possible, at least five Priority Geothermal Zones.",
      "stage": "other",
      "status_word": "deadline; no result recorded in the notes",
      "path": "presidential-instrument",
      "rests_on": "official record, linked (the order)",
      "quote": {
        "text": "March 15 BLM-site identification for clean power/right-of-way and,if possible,at least five Priority Geothermal Zones",
        "file": "Executive Order Source Library/Biden Backfill 2026-10-30/WAVE_8B3_MAP_SOURCE_SNAPSHOT.json"
      },
      "files": [
        "Executive Order Source Library/Biden Backfill 2026-10-30/WAVE_8B3_MAP_SOURCE_SNAPSHOT.json"
      ],
      "register_records": [
        "eo-14141-p03"
      ],
      "disagreement": "none recorded",
      "source_check": "none",
      "from_register": true,
      "weight": "detail",
      "where_in_the_system": "Instruction with a date on an officer or agency",
      "thesis_words": [],
      "what_moves": "nothing recorded",
      "note": "The date fell while EO 14141 was in force.",
      "date_note": "The order map label gives 'March 15' with no year; the year 2025 is the year of the same map's February 28, 2025 date. No file writes '2025-03-15'.",
      "n": 3,
      "movement_type": "Clock date"
    },
    {
      "strand": "The earlier order (EO 14141)",
      "date": "2025-03-31",
      "date_exactness": "day and month given in the order map; no year written",
      "body": "Department of Defense; Department of Energy (Interior and Justice also named in the instruction)",
      "what": "Date in EO 14141 for competitive solicitations for AI infrastructure on the selected federal sites, each to close within 30 days.",
      "stage": "other",
      "status_word": "deadline; no result recorded in the notes",
      "path": "presidential-instrument",
      "rests_on": "official record, linked (the order)",
      "quote": {
        "text": "March 31 competitive solicitations closing within 30 days",
        "file": "Executive Order Source Library/Biden Backfill 2026-10-30/WAVE_8B3_MAP_SOURCE_SNAPSHOT.json"
      },
      "files": [
        "Executive Order Source Library/Biden Backfill 2026-10-30/WAVE_8B3_MAP_SOURCE_SNAPSHOT.json"
      ],
      "register_records": [
        "eo-14141-p04"
      ],
      "disagreement": "none recorded",
      "source_check": "none",
      "from_register": true,
      "weight": "detail",
      "where_in_the_system": "Instruction with a date on an officer or agency",
      "thesis_words": [],
      "what_moves": "nothing recorded",
      "note": "The date fell while EO 14141 was in force.",
      "date_note": "The order map label gives 'March 31' with no year; the year 2025 is the year of the same map's February 28, 2025 date. No file writes '2025-03-31'.",
      "n": 4,
      "movement_type": "Clock date"
    },
    {
      "strand": "The earlier order (EO 14141)",
      "date": "2025-06-30",
      "date_exactness": "day and month given in the order map; no year written",
      "body": "Department of Defense; Department of Energy (Interior and Justice also named in the instruction)",
      "what": "Date in EO 14141 for choosing winning proposals, which would give the winners the opportunity to apply for permits.",
      "stage": "other",
      "status_word": "deadline; no result recorded in the notes",
      "path": "presidential-instrument",
      "rests_on": "official record, linked (the order)",
      "quote": {
        "text": "June 30 winning proposals/opportunity to apply for permits",
        "file": "Executive Order Source Library/Biden Backfill 2026-10-30/WAVE_8B3_MAP_SOURCE_SNAPSHOT.json"
      },
      "files": [
        "Executive Order Source Library/Biden Backfill 2026-10-30/WAVE_8B3_MAP_SOURCE_SNAPSHOT.json"
      ],
      "register_records": [
        "eo-14141-p04"
      ],
      "disagreement": "none recorded",
      "source_check": "none",
      "from_register": true,
      "weight": "detail",
      "where_in_the_system": "Instruction with a date on an officer or agency",
      "thesis_words": [],
      "what_moves": "nothing recorded",
      "note": "The date fell while EO 14141 was in force; EO 14141 was revoked on July 23, 2025 (step 6).",
      "date_note": "The order map label gives 'June 30' with no year; the year 2025 is the year of the same map's February 28, 2025 date. No file writes '2025-06-30'.",
      "n": 5,
      "movement_type": "Clock date"
    },
    {
      "strand": "The order (EO 14318)",
      "date": "2025-07-23",
      "date_exactness": "day given",
      "body": "The President (Donald Trump)",
      "what": "President Trump signed Executive Order 14318, Accelerating Federal Permitting of Data Center Infrastructure, published July 28, 2025 (90 FR 35385). It defines a data-center project as more than 100 MW of new load for AI work, and a 'Qualifying Project' as one with at least $500 million of committed spending, more than 100 MW of new load, a national-security purpose, or a Secretary's designation. It tells Commerce, with the Office of Science and Technology Policy, to launch a financial-support initiative (section 3); agencies to report categorical exclusions to the Council on Environmental Quality within 10 days (section 5); the Federal Permitting Improvement Steering Council's Executive Director to route projects under FAST-41 (section 6); the Environmental Protection Agency to change rules and write Brownfield and Superfund guidance within 180 days (section 7); the Army to review nationwide water permits within 180 days (section 8); and Interior, Energy and Defense to offer federal land (section 9). Section 4 revokes EO 14141.",
      "stage": "signed",
      "status_word": "signed (executive order); revokes EO 14141",
      "path": "presidential-instrument",
      "rests_on": "official record, linked (Federal Register)",
      "quote": {
        "text": "EO 14318, signed July 23, 2025 and published at 90 FR 35385, defines a “Data Center Project” as a facility requiring more than 100 MW of new load for specified AI workloads.",
        "file": "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_LEGAL_SPINE_2025-2026.md"
      },
      "files": [
        "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_LEGAL_SPINE_2025-2026.md",
        "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md",
        "Executive Order Source Library/Biden Backfill 2026-10-30/WAVE_8B3_AI_INFRASTRUCTURE.md",
        "Sovereign Compute/FEDERAL_TRIBAL_COMPUTE_MOBILIZATION_TIMELINE.md",
        "Data Center Federal Legal Spine 2025-2026/DATA_CENTER_WAR_LANDSCAPE_FRESH_ORIENTATION_2026-08-20.md",
        "Data Center Federal Legal Spine 2025-2026/README.md",
        "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_CLAIM_FIREWALL_AND_WATCHBOARD_2026-08-20.md",
        "Federal Science Operating System/FEDERAL_SCIENCE_OPERATING_SYSTEM_FACTUAL_SPINE_2025-2026.md",
        "Federal Government Whole-Site Recertification 2026-08-01/lanes/TRUMP_AI_EXECUTIVE_ORDER_OFFICIAL_INVENTORY_2026-08-01.md"
      ],
      "register_records": [
        "EO-14318",
        "EO 14141 status 1",
        "ai-transition-eo-14318-data-centers"
      ],
      "disagreement": "none recorded",
      "source_check": "none",
      "from_register": false,
      "weight": "turning point",
      "where_in_the_system": "Presidential instrument signed or revoked",
      "thesis_words": [],
      "what_moves": "legal existence: EO 14141 revoked; functions: new instructions to Commerce, CEQ, the Permitting Council's Executive Director, EPA, the Army, Interior, Energy and Defense",
      "note": "The legal spine file says the order 'expressly preserves applicable law and appropriations'. The Sovereign Compute timeline says the order does not itself designate tribal land as a project site.",
      "n": 6,
      "movement_type": "Decided"
    },
    {
      "strand": "DOE sites",
      "date": "2025-07-24",
      "date_exactness": "day given",
      "body": "U.S. Department of Energy (DOE)",
      "what": "DOE selected four of its sites for future solicitations for AI data centers and energy projects: Idaho National Laboratory, Oak Ridge, Paducah and Savannah River.",
      "stage": "other",
      "status_word": "sites selected for future solicitations",
      "path": "agency-operation-or-program",
      "rests_on": "the body's own statement, linked",
      "quote": {
        "text": "DOE selected four federal sites for solicitations.",
        "file": "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_CLAIM_FIREWALL_AND_WATCHBOARD_2026-08-20.md"
      },
      "files": [
        "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md",
        "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_CLAIM_FIREWALL_AND_WATCHBOARD_2026-08-20.md",
        "Data Center Federal Legal Spine 2025-2026/DATA_CENTER_FEDERAL_LEGAL_OBJECT_REGISTRY_2026-08-20.json"
      ],
      "register_records": [
        "DOE-FOUR-SITES"
      ],
      "disagreement": "none recorded",
      "source_check": "none",
      "from_register": false,
      "weight": "step",
      "where_in_the_system": "Federal land offered: sites identified",
      "thesis_words": [],
      "what_moves": "land: four DOE sites offered for private development",
      "note": "The firewall file says this was a selection of sites, not of developers.",
      "n": 7,
      "movement_type": "Decided"
    },
    {
      "strand": "The order (EO 14318)",
      "date": "2025-08-02",
      "date_exactness": "day given in the audit file",
      "body": "Each relevant agency (to the Council on Environmental Quality)",
      "what": "Ten-day date in section 5(a) of EO 14318 for each relevant agency to tell the Council on Environmental Quality (CEQ) which categorical exclusions it already has. (A categorical exclusion is a class of actions an agency has found needs no full environmental review.)",
      "stage": "other",
      "status_word": "deadline; no result recorded in the notes",
      "path": "presidential-instrument",
      "rests_on": "official record, linked (the order)",
      "quote": {
        "text": "Agencies submit existing CE inventories to CEQ within 10 days: Aug. 2, 2025; identify possible new or adopted CEs.",
        "file": "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md"
      },
      "files": [
        "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md",
        "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_CLAIM_FIREWALL_AND_WATCHBOARD_2026-08-20.md",
        "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_LEGAL_SPINE_2025-2026.md",
        "Data Center Federal Legal Spine 2025-2026/DATA_CENTER_FEDERAL_LEGAL_OBJECT_REGISTRY_2026-08-20.json"
      ],
      "register_records": [
        "GAP-CEQ-CE-INVENTORY"
      ],
      "disagreement": "none recorded",
      "source_check": "none",
      "from_register": false,
      "weight": "detail",
      "where_in_the_system": "Instruction with a date on an officer or agency",
      "thesis_words": [],
      "what_moves": "nothing recorded",
      "note": "The audit file says publication of the submissions was not expressly required by the order.",
      "n": 8,
      "movement_type": "Clock date"
    },
    {
      "strand": "DOE sites",
      "date": "2025-09-09",
      "date_exactness": "day given",
      "body": "U.S. Department of Energy (DOE)",
      "what": "DOE issued a request for applications for applicant-funded long-term leases for AI data centers and energy projects on about 44,000 acres at Idaho National Laboratory, with an initial date of November 7 and rolling review after it.",
      "stage": "request for information or comment",
      "status_word": "request for applications",
      "path": "contract-or-award",
      "rests_on": "the body's own statement, linked",
      "quote": {
        "text": "RFA for applicant-funded long-term leases on about 44,000 acres; rolling after initial Nov. 7 date.",
        "file": "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md"
      },
      "files": [
        "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md",
        "Data Center Federal Legal Spine 2025-2026/DATA_CENTER_FEDERAL_LEGAL_OBJECT_REGISTRY_2026-08-20.json"
      ],
      "register_records": [
        "DOE-INL-RFA"
      ],
      "disagreement": "none recorded",
      "source_check": "none",
      "from_register": false,
      "weight": "step",
      "where_in_the_system": "Proposal or solicitation",
      "thesis_words": [],
      "what_moves": "land: about 44,000 acres offered for lease",
      "n": 9,
      "movement_type": "Asked for input or applications"
    },
    {
      "strand": "EPA",
      "date": "2025-09-29",
      "date_exactness": "day given",
      "body": "U.S. Environmental Protection Agency (EPA)",
      "what": "EPA began giving priority handling to new-chemical submissions under section 5 of the Toxic Substances Control Act (TSCA) that are documented as serving qualifying data-center projects. The review standards did not change.",
      "stage": "in operation",
      "status_word": "priority review workflow",
      "path": "agency-operation-or-program",
      "rests_on": "the body's own statement, linked",
      "quote": {
        "text": "EPA accepts qualifying new-chemical submissions for priority handling from September 29, 2025.",
        "file": "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_LEGAL_SPINE_2025-2026.md"
      },
      "files": [
        "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_LEGAL_SPINE_2025-2026.md",
        "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md",
        "Data Center Federal Legal Spine 2025-2026/README.md",
        "Data Center Federal Legal Spine 2025-2026/DATA_CENTER_FEDERAL_LEGAL_OBJECT_REGISTRY_2026-08-20.json"
      ],
      "register_records": [
        "EPA-TSCA-PRIORITY"
      ],
      "disagreement": "none recorded",
      "source_check": "none",
      "from_register": false,
      "weight": "step",
      "where_in_the_system": "Environmental permits, rules and guidance that apply to data centers",
      "thesis_words": [],
      "what_moves": "nothing recorded",
      "note": "The audit file lists this under the order's section 7 EPA instruction.",
      "n": 10,
      "movement_type": "Live"
    },
    {
      "strand": "DOE sites",
      "date": "2025-09-30",
      "date_exactness": "day given",
      "body": "U.S. Department of Energy (DOE)",
      "what": "DOE issued a competitive request for proposals for applicant-funded leases for AI data centers and energy projects at two sites at Oak Ridge.",
      "stage": "request for information or comment",
      "status_word": "request for proposals",
      "path": "contract-or-award",
      "rests_on": "the body's own statement, linked",
      "quote": {
        "text": "Competitive RFP for applicant-funded leases at two sites.",
        "file": "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md"
      },
      "files": [
        "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md",
        "Data Center Federal Legal Spine 2025-2026/DATA_CENTER_FEDERAL_LEGAL_OBJECT_REGISTRY_2026-08-20.json"
      ],
      "register_records": [
        "DOE-OAK-RIDGE-RFP"
      ],
      "disagreement": "none recorded",
      "source_check": "none",
      "from_register": false,
      "weight": "step",
      "where_in_the_system": "Proposal or solicitation",
      "thesis_words": [],
      "what_moves": "land: two Oak Ridge sites offered for lease",
      "n": 11,
      "movement_type": "Asked for input or applications"
    },
    {
      "strand": "DOE sites: Savannah River",
      "date": "2025-09-30",
      "date_exactness": "day given",
      "body": "National Nuclear Security Administration (NNSA), within DOE",
      "what": "NNSA issued a request for proposals for long-term lease development for AI infrastructure and energy generation on ten tracts totaling 3,103 acres at the Savannah River Site.",
      "stage": "request for information or comment",
      "status_word": "request for proposals",
      "path": "contract-or-award",
      "rests_on": "the body's own statement, linked",
      "quote": {
        "text": "Invites proposals for long-term lease development across ten tracts totaling 3103 acres.",
        "file": "Data Center Federal Legal Spine 2025-2026/DATA_CENTER_FEDERAL_LEGAL_OBJECT_REGISTRY_2026-08-20.json"
      },
      "files": [
        "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md",
        "Data Center Federal Legal Spine 2025-2026/DATA_CENTER_FEDERAL_LEGAL_OBJECT_REGISTRY_2026-08-20.json"
      ],
      "register_records": [
        "DOE-SRS-RFP"
      ],
      "disagreement": "none recorded",
      "source_check": "none",
      "from_register": false,
      "weight": "step",
      "where_in_the_system": "Proposal or solicitation",
      "thesis_words": [],
      "what_moves": "land: 3,103 acres offered for lease",
      "n": 12,
      "movement_type": "Asked for input or applications"
    },
    {
      "strand": "Military land: Air Force",
      "date": "2025-10-15",
      "date_exactness": "day given ('2025-10-15 onward')",
      "body": "Department of the Air Force (Air Force Civil Engineer Center opportunities page)",
      "what": "The Air Force asked for long-term lease proposals for commercial AI data centers at five installations (Arnold, Davis-Monthan, Edwards, Joint Base McGuire-Dix-Lakehurst and Robins), for projects that meet EO 14318's 'Qualifying Project' tests of more than 100 MW of new load and at least $500 million. It sought fair-market lease payment and kept a right of first refusal on any proposed on-site power plant.",
      "stage": "request for information or comment",
      "status_word": "request for lease proposals",
      "path": "contract-or-award",
      "rests_on": "the body's own statement, linked",
      "quote": {
        "text": "Closed Air Force request for lease proposals for EO 14318 “Qualifying Projects”: greater than 100 MW new load and at least $500 million.",
        "file": "Data Center Federal Legal Spine 2025-2026/PUBLIC_MILITARY_COMPUTE_AND_DATA_CENTER_OVERLAP_MAP_2026-08-20.md"
      },
      "files": [
        "Data Center Federal Legal Spine 2025-2026/PUBLIC_MILITARY_COMPUTE_AND_DATA_CENTER_OVERLAP_MAP_2026-08-20.md",
        "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md",
        "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_CLAIM_FIREWALL_AND_WATCHBOARD_2026-08-20.md",
        "Data Center Federal Legal Spine 2025-2026/DATA_CENTER_FEDERAL_LEGAL_OBJECT_REGISTRY_2026-08-20.json"
      ],
      "register_records": [
        "AIR-FORCE-RFLP-FIVE"
      ],
      "disagreement": "none recorded",
      "source_check": "none",
      "from_register": false,
      "weight": "step",
      "where_in_the_system": "Proposal or solicitation",
      "thesis_words": [],
      "what_moves": "land: parcels at five installations offered for lease",
      "n": 13,
      "movement_type": "Asked for input or applications"
    },
    {
      "strand": "Military land: Air Force",
      "date": "date not given (after October 15, 2025; before August 20, 2026)",
      "date_exactness": "no date in the files",
      "body": "Department of the Air Force (Arnold Air Force Base notice)",
      "what": "Arnold Air Force Base posted a notice that it received no proposal for an AI data center under the five-installation request.",
      "stage": "stated by the body",
      "status_word": "no proposal received",
      "path": "contract-or-award",
      "rests_on": "the body's own statement, linked",
      "quote": {
        "text": "Arnold reported no proposal",
        "file": "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md"
      },
      "files": [
        "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md",
        "Data Center Federal Legal Spine 2025-2026/PUBLIC_MILITARY_COMPUTE_AND_DATA_CENTER_OVERLAP_MAP_2026-08-20.md",
        "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_CLAIM_FIREWALL_AND_WATCHBOARD_2026-08-20.md",
        "Data Center Federal Legal Spine 2025-2026/DATA_CENTER_FEDERAL_LEGAL_OBJECT_REGISTRY_2026-08-20.json"
      ],
      "register_records": [],
      "disagreement": "none recorded",
      "source_check": "none",
      "from_register": false,
      "weight": "detail",
      "where_in_the_system": "Responses to a solicitation",
      "thesis_words": [],
      "what_moves": "nothing recorded",
      "n": 14,
      "movement_type": "Status check"
    },
    {
      "strand": "DOE sites: Paducah",
      "date": "2025-11-04",
      "date_exactness": "day given",
      "body": "U.S. Department of Energy (DOE)",
      "what": "DOE issued a request for offers for applicant-funded long-term leases for AI data centers and energy projects at its Paducah site, with offers due January 30, 2026.",
      "stage": "request for information or comment",
      "status_word": "request for offers",
      "path": "contract-or-award",
      "rests_on": "the body's own statement, linked",
      "quote": {
        "text": "Invites applicant-funded long-term lease offers due January 30, 2026.",
        "file": "Data Center Federal Legal Spine 2025-2026/DATA_CENTER_FEDERAL_LEGAL_OBJECT_REGISTRY_2026-08-20.json"
      },
      "files": [
        "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md",
        "Data Center Federal Legal Spine 2025-2026/DATA_CENTER_FEDERAL_LEGAL_OBJECT_REGISTRY_2026-08-20.json"
      ],
      "register_records": [
        "DOE-PADUCAH-RFO"
      ],
      "disagreement": "none recorded",
      "source_check": "none",
      "from_register": false,
      "weight": "step",
      "where_in_the_system": "Proposal or solicitation",
      "thesis_words": [],
      "what_moves": "land: Paducah site offered for lease",
      "n": 15,
      "movement_type": "Asked for input or applications"
    },
    {
      "strand": "DOE sites: Portsmouth",
      "date": "2025-11-17",
      "date_exactness": "day given",
      "body": "U.S. Department of Energy (DOE)",
      "what": "DOE made categorical exclusion determination CX-270875 for a proposed lease of 189 acres at its Portsmouth site.",
      "stage": "approved or adopted",
      "status_word": "categorical exclusion determination",
      "path": "agency-order-or-decision",
      "rests_on": "official record, linked (DOE NEPA listing)",
      "quote": {
        "text": "DOE proposes to lease 189 acres at Portsmouth.",
        "file": "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md"
      },
      "files": [
        "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md",
        "Data Center Federal Legal Spine 2025-2026/DATA_CENTER_FEDERAL_LEGAL_OBJECT_REGISTRY_2026-08-20.json"
      ],
      "register_records": [
        "DOE-CX-270875"
      ],
      "disagreement": "none recorded",
      "source_check": "none",
      "from_register": false,
      "weight": "step",
      "where_in_the_system": "NEPA review route for a named federal action (categorical exclusion determination)",
      "thesis_words": [],
      "what_moves": "nothing recorded",
      "n": 16,
      "movement_type": "Decided"
    },
    {
      "strand": "Water permits (Army Corps)",
      "date": "2026-01-08",
      "date_exactness": "day given",
      "body": "U.S. Army Corps of Engineers (files write 'Army')",
      "what": "The Corps published final reissued nationwide permits (91 FR 768), effective March 15, 2026. Nationwide Permit 39 names data centers as commercial and institutional development, generally with a limit of half an acre of waters lost and a notice before construction.",
      "stage": "published",
      "status_word": "final general permits",
      "path": "agency-rule",
      "rests_on": "official record, linked (Federal Register)",
      "quote": {
        "text": "Final reissued NWPs published Jan. 8, 2026, effective Mar. 15; NWP 39 expressly lists data centers.",
        "file": "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md"
      },
      "files": [
        "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md",
        "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_LEGAL_SPINE_2025-2026.md",
        "Data Center Federal Legal Spine 2025-2026/DATA_CENTER_WAR_LANDSCAPE_FRESH_ORIENTATION_2026-08-20.md",
        "Data Center Federal Legal Spine 2025-2026/README.md",
        "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_CLAIM_FIREWALL_AND_WATCHBOARD_2026-08-20.md",
        "Data Center Federal Legal Spine 2025-2026/DATA_CENTER_FEDERAL_LEGAL_OBJECT_REGISTRY_2026-08-20.json"
      ],
      "register_records": [
        "USACE-NWP-39"
      ],
      "disagreement": "none recorded",
      "source_check": "none",
      "from_register": false,
      "weight": "step",
      "where_in_the_system": "Environmental permits, rules and guidance that apply to data centers",
      "thesis_words": [],
      "what_moves": "nothing recorded",
      "note": "The audit file says the final notice does not state that it was issued under EO 14318. The audit file lists it under the order's section 8 Army instruction.",
      "n": 17,
      "movement_type": "Published"
    },
    {
      "strand": "The order (EO 14318)",
      "date": "2026-01-19",
      "date_exactness": "day given in the audit file",
      "body": "Secretary of the Army, acting through the Assistant Secretary of the Army for Civil Works",
      "what": "180-day date in section 8(b) of EO 14318 for the Army to review the nationwide permits and decide whether a permit for data-center activities is needed. The notes record the January 8 reissue (step 17) and no review or decision by the Assistant Secretary under the order.",
      "stage": "other",
      "status_word": "deadline; no result recorded in the notes",
      "path": "presidential-instrument",
      "rests_on": "official record, linked (the order)",
      "quote": {
        "text": "Review NWPs within 180 days: Jan. 19, 2026; determine whether activity-specific permit needed.",
        "file": "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md"
      },
      "files": [
        "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md"
      ],
      "register_records": [],
      "disagreement": "none recorded",
      "source_check": "none",
      "from_register": false,
      "weight": "detail",
      "where_in_the_system": "Instruction with a date on an officer or agency",
      "thesis_words": [],
      "what_moves": "nothing recorded",
      "note": "The same date was the 180-day date for EPA's Brownfield and Superfund guidance under section 7(b); that guidance is step 20.",
      "n": 18,
      "movement_type": "Clock date"
    },
    {
      "strand": "Financial support (order section 3)",
      "date": "2026-01 (no day given)",
      "date_exactness": "month given, no day",
      "body": "Office of Science and Technology Policy (OSTP), in the Executive Office of the President",
      "what": "An OSTP retrospective of January 2026 says EO 14318 'launches' financial support for qualifying projects.",
      "stage": "stated by the body",
      "status_word": "retrospective",
      "path": "presidential-instrument",
      "rests_on": "the body's own statement, linked",
      "quote": {
        "text": "OSTP January 2026 retrospective says the order “launches” support.",
        "file": "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md"
      },
      "files": [
        "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md",
        "Data Center Federal Legal Spine 2025-2026/DATA_CENTER_FEDERAL_LEGAL_OBJECT_REGISTRY_2026-08-20.json"
      ],
      "register_records": [
        "GAP-COMMERCE-OSTP-SECTION-3"
      ],
      "disagreement": "none recorded",
      "source_check": "none",
      "from_register": false,
      "weight": "detail",
      "where_in_the_system": "Financial-support initiative (order section 3)",
      "thesis_words": [],
      "what_moves": "nothing recorded",
      "n": 19,
      "movement_type": "Said or announced"
    },
    {
      "strand": "EPA",
      "date": "2026-01 (no day given)",
      "date_exactness": "month given, no day; the object registry uses January 19, 2026, the order's 180-day date, and says the document itself is dated January 2026",
      "body": "U.S. Environmental Protection Agency (EPA)",
      "what": "EPA issued 'Guidance on Redevelopment of Superfund and Brownfield Sites as AI Data Centers', with screening, liability and reuse points, and public mapping and screening tools. It names no sites and waives no cleanup duty.",
      "stage": "published",
      "status_word": "nonbinding guidance",
      "path": "staff-position",
      "rests_on": "the body's own statement, linked",
      "quote": {
        "text": "EPA issued January 2026 reuse guidance and public mapping/screening tools.",
        "file": "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_LEGAL_SPINE_2025-2026.md"
      },
      "files": [
        "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_LEGAL_SPINE_2025-2026.md",
        "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md",
        "Data Center Federal Legal Spine 2025-2026/README.md",
        "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_CLAIM_FIREWALL_AND_WATCHBOARD_2026-08-20.md",
        "Data Center Federal Legal Spine 2025-2026/DATA_CENTER_FEDERAL_LEGAL_OBJECT_REGISTRY_2026-08-20.json"
      ],
      "register_records": [
        "EPA-CERCLA-BROWNFIELDS-GUIDANCE"
      ],
      "disagreement": "Date: the legal spine and audit files give January 2026; the object registry gives 2026-01-19 and says that is the order's deadline date used for the audit.",
      "source_check": "none",
      "from_register": false,
      "weight": "step",
      "where_in_the_system": "Environmental permits, rules and guidance that apply to data centers",
      "thesis_words": [],
      "what_moves": "nothing recorded",
      "note": "The audit file lists it as the return for the order's section 7(b) guidance instruction, due within 180 days (January 19, 2026).",
      "n": 20,
      "movement_type": "Published"
    },
    {
      "strand": "DOE sites: Portsmouth",
      "date": "2026-02-04",
      "date_exactness": "day given",
      "body": "U.S. Department of Energy (DOE)",
      "what": "DOE made categorical exclusion determination CX-270900 for an easement for AEP's five 138-kV lines at Portsmouth, with 3.5 miles of new right-of-way plus rebuilding.",
      "stage": "approved or adopted",
      "status_word": "categorical exclusion determination",
      "path": "agency-order-or-decision",
      "rests_on": "official record, linked (DOE NEPA listing)",
      "quote": {
        "text": "AEP easement for five 138-kV lines, 3.5 miles new ROW plus rebuild.",
        "file": "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md"
      },
      "files": [
        "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md",
        "Data Center Federal Legal Spine 2025-2026/DATA_CENTER_FEDERAL_LEGAL_OBJECT_REGISTRY_2026-08-20.json"
      ],
      "register_records": [
        "DOE-CX-270900"
      ],
      "disagreement": "none recorded",
      "source_check": "none",
      "from_register": false,
      "weight": "step",
      "where_in_the_system": "NEPA review route for a named federal action (categorical exclusion determination)",
      "thesis_words": [],
      "what_moves": "nothing recorded",
      "n": 21,
      "movement_type": "Decided"
    },
    {
      "strand": "DOE sites: Portsmouth",
      "date": "2026-02-26",
      "date_exactness": "day given (SB Energy's September S-1/A, as cited in the 15 November 2026 refresh)",
      "body": "Pike County Portsmouth DC LLC (an SB Energy subsidiary) and the U.S. Department of Energy (DOE)",
      "what": "Pike County Portsmouth DC LLC, an SB Energy subsidiary, entered into a lease with DOE on February 26, 2026, according to SB Energy's September S-1/A. GAO records 189 acres. SB Energy expects one data-center building on DOE land and most campus buildings on private land. The notes do not record the rent, duration or renewal terms.",
      "stage": "lease entered (per the lessee's SEC filing)",
      "status_word": "lease entered",
      "path": "contract-or-award",
      "quote": [
        {
          "text": "SB Energy’s September S-1/A identifies Pike County Portsmouth DC LLC as the subsidiary that entered into a DOE lease on February 26, 2026. GAO records 189 acres.",
          "file": "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_RETURN_REFRESH_2026-10-05.md"
        },
        {
          "text": "SB Energy expects one data-center building on DOE land and most campus buildings on private land.",
          "file": "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_RETURN_REFRESH_2026-10-05.md"
        }
      ],
      "files": [
        "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_RETURN_REFRESH_2026-10-05.md"
      ],
      "weight": "turning point",
      "where_in_the_system": "Authorization: lease or right-of-way",
      "what_moves": "land: 189 acres of DOE land at Portsmouth leased to Pike County Portsmouth DC LLC",
      "rests_on": "official record, linked (SB Energy S-1/A on EDGAR; GAO-27-108063)",
      "register_records": [],
      "disagreement": "none recorded",
      "source_check": "none",
      "from_register": false,
      "thesis_words": [],
      "added_2026-11-16": "New step from the 15 November 2026 research refresh.",
      "n": 22,
      "movement_type": "Awarded or agreed"
    },
    {
      "strand": "Water permits (Army Corps)",
      "date": "2026-03-15",
      "date_exactness": "day given",
      "body": "U.S. Army Corps of Engineers",
      "what": "The reissued nationwide permits, including Nationwide Permit 39 naming data centers, took effect.",
      "stage": "took effect",
      "status_word": "effective",
      "path": "agency-rule",
      "rests_on": "official record, linked (Federal Register)",
      "quote": {
        "text": "Army reissued nationwide permits; NWP 39 expressly lists data centers and took effect March 15, 2026.",
        "file": "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_LEGAL_SPINE_2025-2026.md"
      },
      "files": [
        "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_LEGAL_SPINE_2025-2026.md",
        "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md",
        "Data Center Federal Legal Spine 2025-2026/DATA_CENTER_WAR_LANDSCAPE_FRESH_ORIENTATION_2026-08-20.md",
        "Data Center Federal Legal Spine 2025-2026/README.md",
        "Data Center Federal Legal Spine 2025-2026/DATA_CENTER_FEDERAL_LEGAL_OBJECT_REGISTRY_2026-08-20.json"
      ],
      "register_records": [
        "USACE-NWP-39"
      ],
      "disagreement": "none recorded",
      "source_check": "none",
      "from_register": false,
      "weight": "step",
      "where_in_the_system": "Environmental permits, rules and guidance that apply to data centers",
      "thesis_words": [],
      "what_moves": "nothing recorded",
      "n": 23,
      "movement_type": "Took effect"
    },
    {
      "strand": "DOE sites: Portsmouth",
      "date": "2026-03-20",
      "date_exactness": "day given",
      "body": "U.S. Department of Energy (DOE), with the U.S. Department of Commerce",
      "what": "DOE said an SB Energy affiliate is leasing an initial 189 acres of federal land at Portsmouth (the PORTS Technology Campus) and that groundbreaking took place March 20, 2026. The same Commerce and DOE announcement linked $33.3 billion of planned Japanese-backed power investment to the U.S.-Japan agreement. The files say the FAST-41 campus also takes in private land next to the site; SB Energy expects one data-center building on DOE land and most campus buildings on private land (September S-1/A). The lease itself was entered February 26, 2026 (step 22).",
      "stage": "other",
      "status_word": "lease confirmed by DOE announcement; groundbreaking",
      "path": "contract-or-award",
      "rests_on": "the body's own statement, linked",
      "quote": {
        "text": "Portsmouth: DOE publicly confirms an SB Energy affiliate is leasing an initial 189 federal acres; groundbreaking occurred March 20, 2026.",
        "file": "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_LEGAL_SPINE_2025-2026.md"
      },
      "files": [
        "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_LEGAL_SPINE_2025-2026.md",
        "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md",
        "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_CLAIM_FIREWALL_AND_WATCHBOARD_2026-08-20.md",
        "Data Center Federal Legal Spine 2025-2026/DATA_CENTER_WAR_LANDSCAPE_FRESH_ORIENTATION_2026-08-20.md",
        "Data Center Federal Legal Spine 2025-2026/README.md",
        "Data Center Federal Legal Spine 2025-2026/DATA_CENTER_FEDERAL_LEGAL_OBJECT_REGISTRY_2026-08-20.json",
        "Federal Science Operating System/NSSTS Technology-to-Company Map 2026-08-18/NSSTS_WAVE_2_ENERGY_MANUFACTURING_CRITICAL_MATERIALS_MAP_2026-08-18.md",
        "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_RETURN_REFRESH_2026-10-05.md"
      ],
      "register_records": [
        "DOE-PORTSMOUTH-LEASE"
      ],
      "disagreement": "none recorded",
      "source_check": "none",
      "from_register": false,
      "weight": "turning point",
      "where_in_the_system": "Authorization: lease or right-of-way",
      "thesis_words": [],
      "what_moves": "land: 189 DOE acres leased to an SB Energy affiliate (as DOE states it)",
      "n": 24,
      "corrected_2026-11-16": [
        {
          "field": "what",
          "was": "the notes do not record how much of the announced 10 GW campus is on DOE land.",
          "now": "SB Energy expects one data-center building on DOE land and most campus buildings on private land; lease entered February 26, 2026 (step 22).",
          "file": "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_RETURN_REFRESH_2026-10-05.md",
          "quote": "SB Energy expects one data-center building on DOE land and most campus buildings on private land."
        }
      ],
      "movement_type": "Said or announced"
    },
    {
      "strand": "Military land: Army",
      "date": "2026-03-26",
      "date_exactness": "day given",
      "body": "Department of the Army",
      "what": "The Army conditionally selected Carlyle for about 1,384 acres at Fort Bliss, Texas (first operation projected FY2027) and CyrusOne for about 1,201 acres at Dugway Proving Ground, Utah (projected FY2029), and entered exclusive lease negotiations under 10 U.S.C. 2667. The developers would finance, build, run and later take down the data centers on Army land. The Army says the deal is not final.",
      "stage": "other",
      "status_word": "conditional selection; exclusive negotiations (not final, per the Army)",
      "path": "contract-or-award",
      "rests_on": "the body's own statement, linked",
      "quote": {
        "text": "Army conditionally selected Carlyle at Fort Bliss and CyrusOne at Dugway under 10 U.S.C. 2667.",
        "file": "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_LEGAL_SPINE_2025-2026.md"
      },
      "files": [
        "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_LEGAL_SPINE_2025-2026.md",
        "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md",
        "Data Center Federal Legal Spine 2025-2026/PUBLIC_MILITARY_COMPUTE_AND_DATA_CENTER_OVERLAP_MAP_2026-08-20.md",
        "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_CLAIM_FIREWALL_AND_WATCHBOARD_2026-08-20.md",
        "Data Center Federal Legal Spine 2025-2026/DATA_CENTER_FEDERAL_LEGAL_OBJECT_REGISTRY_2026-08-20.json",
        "Federal Science Operating System/NSSTS Technology-to-Company Map 2026-08-18/NSSTS_WAVE_2_CLAIM_AUDIT_AND_WATCHBOARD_2026-08-18.md"
      ],
      "register_records": [
        "ARMY-FORT-BLISS-DUGWAY"
      ],
      "disagreement": "none recorded",
      "source_check": "none",
      "from_register": false,
      "weight": "turning point",
      "where_in_the_system": "Selection or agreement",
      "thesis_words": [],
      "what_moves": "land: two Army parcels under exclusive negotiation",
      "note": "The audit file lists this under the order's section 9 Defense land instruction.",
      "n": 25,
      "movement_type": "Selected or offered, not final"
    },
    {
      "strand": "Permitting coordination (FAST-41)",
      "date": "2026-04-01",
      "date_exactness": "day given in the object registry; the markdown files give no coverage date",
      "body": "Federal Permitting Improvement Steering Council (Permitting Dashboard); U.S. Army Corps of Engineers leading the federal review",
      "what": "QTS Richmond Technology Park Data Center 5 in Virginia was listed as a FAST-41 covered project, which puts its federal permits on a public coordinated schedule. At the August 20 check it was in progress, with 2 of 4 processes complete and estimated completion June 11, 2027. The sponsor used ordinary FAST-41 eligibility.",
      "stage": "received or under consideration by the deciding body",
      "status_word": "FAST-41 covered project; in progress",
      "path": "agency-operation-or-program",
      "rests_on": "official record, linked (Permitting Dashboard)",
      "quote": {
        "text": "Covered; in progress; estimated completion June 11, 2027; 2 of 4 processes complete.",
        "file": "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md"
      },
      "files": [
        "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md",
        "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_LEGAL_SPINE_2025-2026.md",
        "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_CLAIM_FIREWALL_AND_WATCHBOARD_2026-08-20.md",
        "Data Center Federal Legal Spine 2025-2026/DATA_CENTER_WAR_LANDSCAPE_FRESH_ORIENTATION_2026-08-20.md",
        "Data Center Federal Legal Spine 2025-2026/README.md",
        "Data Center Federal Legal Spine 2025-2026/DATA_CENTER_FEDERAL_LEGAL_OBJECT_REGISTRY_2026-08-20.json",
        "Sovereign Compute/FEDERAL_TRIBAL_COMPUTE_MOBILIZATION_TIMELINE.md"
      ],
      "register_records": [
        "FAST41-QTS-RIC5"
      ],
      "disagreement": "Date: the object registry gives 2026-04-01. The Sovereign Compute timeline's open questions refer to 'the covered FAST-41 data-center project approved in April 2025' without naming it. The files do not say whether these are the same project.",
      "source_check": "none",
      "from_register": false,
      "weight": "step",
      "where_in_the_system": "Permitting coordination (FAST-41 covered project)",
      "thesis_words": [],
      "what_moves": "nothing recorded",
      "n": 26,
      "movement_type": "In process"
    },
    {
      "strand": "Review rules (CEQ)",
      "date": "2026-04-09",
      "date_exactness": "day given",
      "body": "Council on Environmental Quality (CEQ)",
      "what": "CEQ issued guidance on how agencies create, revise, adopt and apply categorical exclusions. It has no force of law and creates no data-center categorical exclusion.",
      "stage": "published",
      "status_word": "guidance (no force of law)",
      "path": "staff-position",
      "rests_on": "official record, linked",
      "quote": {
        "text": "Explains creation, revision, adoption and application of CEs.",
        "file": "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md"
      },
      "files": [
        "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md",
        "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_LEGAL_SPINE_2025-2026.md",
        "Data Center Federal Legal Spine 2025-2026/DATA_CENTER_FEDERAL_LEGAL_OBJECT_REGISTRY_2026-08-20.json"
      ],
      "register_records": [],
      "disagreement": "none recorded",
      "source_check": "none",
      "from_register": false,
      "weight": "step",
      "where_in_the_system": "Government-wide review rules and guidance",
      "thesis_words": [],
      "what_moves": "nothing recorded",
      "note": "The audit file lists it under the order's section 5 categorical-exclusion instruction; the order map marks section 5(b) 'found in part' on it. CEQ's January 8, 2026 final rule removing its government-wide NEPA regulations is in the nepa-permitting-changes thread.",
      "n": 27,
      "movement_type": "Published"
    },
    {
      "strand": "Military land: Air Force",
      "date": "2026-04-10",
      "date_exactness": "day given",
      "body": "Department of the Air Force (Air Force Civil Engineer Center, solicitation AFCEC-26-R-0006)",
      "what": "The Air Force asked for lease proposals under 10 U.S.C. 2667 for AI data centers on parcels at Joint Base Elmendorf-Richardson (JBER), Eielson Air Force Base and Clear Space Force Station in Alaska. It said any government purchase of data-center services or power was not required or guaranteed and would need separate contracts.",
      "stage": "request for information or comment",
      "status_word": "request for lease proposals",
      "path": "contract-or-award",
      "rests_on": "official record, linked (SAM.gov)",
      "quote": {
        "text": "Solicitation under 10 U.S.C. 2667 for JBER, Eielson and Clear SFS.",
        "file": "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md"
      },
      "files": [
        "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md",
        "Data Center Federal Legal Spine 2025-2026/PUBLIC_MILITARY_COMPUTE_AND_DATA_CENTER_OVERLAP_MAP_2026-08-20.md",
        "Data Center Federal Legal Spine 2025-2026/DATA_CENTER_FEDERAL_LEGAL_OBJECT_REGISTRY_2026-08-20.json"
      ],
      "register_records": [
        "AIR-FORCE-RFLP-ALASKA"
      ],
      "disagreement": "none recorded",
      "source_check": "none",
      "from_register": false,
      "weight": "step",
      "where_in_the_system": "Proposal or solicitation",
      "thesis_words": [],
      "what_moves": "land: parcels at three Alaska installations offered for lease",
      "n": 28,
      "movement_type": "Asked for input or applications"
    },
    {
      "strand": "DOE sites: Portsmouth",
      "date": "2026-04-29",
      "date_exactness": "day given",
      "body": "U.S. Department of Energy (DOE)",
      "what": "DOE made categorical exclusion determination CX-270956 for an environmental site assessment of the leased Portsmouth Batch 1 property.",
      "stage": "approved or adopted",
      "status_word": "categorical exclusion determination",
      "path": "agency-order-or-decision",
      "rests_on": "official record, linked (DOE NEPA listing)",
      "quote": {
        "text": "Environmental site assessment of the leased Portsmouth Batch 1 property.",
        "file": "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md"
      },
      "files": [
        "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md",
        "Data Center Federal Legal Spine 2025-2026/DATA_CENTER_FEDERAL_LEGAL_OBJECT_REGISTRY_2026-08-20.json"
      ],
      "register_records": [
        "DOE-CX-270956"
      ],
      "disagreement": "none recorded",
      "source_check": "none",
      "from_register": false,
      "weight": "detail",
      "where_in_the_system": "NEPA review route for a named federal action (categorical exclusion determination)",
      "thesis_words": [],
      "what_moves": "nothing recorded",
      "n": 29,
      "movement_type": "Decided"
    },
    {
      "strand": "DOE sites: Paducah",
      "date": "2026-04-29",
      "date_exactness": "day given",
      "body": "U.S. Department of Energy (DOE)",
      "what": "DOE made categorical exclusion determination CX-270955 for a planned lease of about 188 acres, Parcel C, at Paducah.",
      "stage": "approved or adopted",
      "status_word": "categorical exclusion determination",
      "path": "agency-order-or-decision",
      "rests_on": "official record, linked (DOE NEPA listing)",
      "quote": {
        "text": "DOE plans to lease about 188 acres, Paducah Parcel C.",
        "file": "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md"
      },
      "files": [
        "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md",
        "Data Center Federal Legal Spine 2025-2026/DATA_CENTER_FEDERAL_LEGAL_OBJECT_REGISTRY_2026-08-20.json"
      ],
      "register_records": [
        "DOE-CX-270955"
      ],
      "disagreement": "none recorded",
      "source_check": "none",
      "from_register": false,
      "weight": "step",
      "where_in_the_system": "NEPA review route for a named federal action (categorical exclusion determination)",
      "thesis_words": [],
      "what_moves": "nothing recorded",
      "n": 30,
      "movement_type": "Decided"
    },
    {
      "strand": "DOE sites: Paducah",
      "date": "2026-05-04",
      "date_exactness": "day given",
      "body": "U.S. Department of Energy (DOE)",
      "what": "DOE made categorical exclusion determination CX-270971 for a planned lease of about 785 acres, Parcel B, at Paducah.",
      "stage": "approved or adopted",
      "status_word": "categorical exclusion determination",
      "path": "agency-order-or-decision",
      "rests_on": "official record, linked (DOE NEPA listing)",
      "quote": {
        "text": "DOE plans to lease about 785 acres, Paducah Parcel B.",
        "file": "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md"
      },
      "files": [
        "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md",
        "Data Center Federal Legal Spine 2025-2026/DATA_CENTER_FEDERAL_LEGAL_OBJECT_REGISTRY_2026-08-20.json"
      ],
      "register_records": [
        "DOE-CX-270971"
      ],
      "disagreement": "none recorded",
      "source_check": "none",
      "from_register": false,
      "weight": "step",
      "where_in_the_system": "NEPA review route for a named federal action (categorical exclusion determination)",
      "thesis_words": [],
      "what_moves": "nothing recorded",
      "n": 31,
      "movement_type": "Decided"
    },
    {
      "strand": "EPA",
      "date": "2026-05-13",
      "date_exactness": "day given",
      "body": "U.S. Environmental Protection Agency (EPA)",
      "what": "EPA proposed a rule, 'Begin Actual Construction' in the New Source Review (NSR) preconstruction permitting program (91 FR 26958). It would separate certain work that emits nothing from construction that needs a major NSR air permit first.",
      "stage": "proposed",
      "status_word": "notice of proposed rulemaking",
      "path": "agency-rule",
      "rests_on": "official record, linked (Federal Register)",
      "quote": {
        "text": "Would distinguish specified non-emitting work from construction requiring a major NSR permit first.",
        "file": "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md"
      },
      "files": [
        "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md",
        "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_CLAIM_FIREWALL_AND_WATCHBOARD_2026-08-20.md",
        "Data Center Federal Legal Spine 2025-2026/DATA_CENTER_FEDERAL_LEGAL_OBJECT_REGISTRY_2026-08-20.json"
      ],
      "register_records": [
        "EPA-NSR-BEGIN-CONSTRUCTION"
      ],
      "disagreement": "none recorded",
      "source_check": "none",
      "from_register": false,
      "weight": "step",
      "where_in_the_system": "Environmental permits, rules and guidance that apply to data centers",
      "thesis_words": [],
      "what_moves": "nothing recorded",
      "note": "The audit file lists it under the order's section 7 EPA instruction; the order map marks section 7(a) 'found in part' on it.",
      "n": 32,
      "movement_type": "Proposed or filed"
    },
    {
      "strand": "Military land: Air Force",
      "date": "2026-05-29",
      "date_exactness": "day given",
      "body": "Department of the Air Force (solicitation AFCEC-26-R-0006)",
      "what": "Offers were due under the Alaska lease solicitation. The solicitation's public history shows updates through July 14, 2026.",
      "stage": "scheduled",
      "status_word": "offers due; no selection recorded in the notes",
      "path": "contract-or-award",
      "rests_on": "official record, linked (SAM.gov)",
      "quote": {
        "text": "offers were due May 29, 2026; later public history showed solicitation updates through July 14.",
        "file": "Data Center Federal Legal Spine 2025-2026/PUBLIC_MILITARY_COMPUTE_AND_DATA_CENTER_OVERLAP_MAP_2026-08-20.md"
      },
      "files": [
        "Data Center Federal Legal Spine 2025-2026/PUBLIC_MILITARY_COMPUTE_AND_DATA_CENTER_OVERLAP_MAP_2026-08-20.md"
      ],
      "register_records": [],
      "disagreement": "none recorded",
      "source_check": "none",
      "from_register": false,
      "weight": "detail",
      "where_in_the_system": "Responses to a solicitation",
      "thesis_words": [],
      "what_moves": "nothing recorded",
      "n": 33,
      "movement_type": "Clock date"
    },
    {
      "strand": "Permitting coordination (FAST-41)",
      "date": "2026-06-11",
      "date_exactness": "day given in the object registry; the markdown files give no coverage date",
      "body": "Federal Permitting Improvement Steering Council (Permitting Dashboard); U.S. Army Corps of Engineers lead, U.S. Fish and Wildlife Service participating",
      "what": "The PORTS Technology Campus at Portsmouth was listed as a FAST-41 covered project. At the August 20 check it was in progress, with 0 of 4 processes complete and estimated completion December 23, 2026.",
      "stage": "received or under consideration by the deciding body",
      "status_word": "FAST-41 covered project; in progress",
      "path": "agency-operation-or-program",
      "rests_on": "official record, linked (Permitting Dashboard)",
      "quote": {
        "text": "Covered; in progress; estimated completion December 23, 2026; 0 of 4 processes complete on the reviewed page.",
        "file": "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md"
      },
      "files": [
        "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md",
        "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_LEGAL_SPINE_2025-2026.md",
        "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_CLAIM_FIREWALL_AND_WATCHBOARD_2026-08-20.md",
        "Data Center Federal Legal Spine 2025-2026/DATA_CENTER_WAR_LANDSCAPE_FRESH_ORIENTATION_2026-08-20.md",
        "Data Center Federal Legal Spine 2025-2026/README.md",
        "Data Center Federal Legal Spine 2025-2026/DATA_CENTER_FEDERAL_LEGAL_OBJECT_REGISTRY_2026-08-20.json"
      ],
      "register_records": [
        "FAST41-PORTS"
      ],
      "disagreement": "none recorded",
      "source_check": "none",
      "from_register": false,
      "weight": "step",
      "where_in_the_system": "Permitting coordination (FAST-41 covered project)",
      "thesis_words": [],
      "what_moves": "nothing recorded",
      "n": 34,
      "movement_type": "In process"
    },
    {
      "strand": "Interior land (BLM)",
      "date": "2026-06-26 (decision); 2026-07-20 (announcement)",
      "date_exactness": "days given",
      "body": "Bureau of Land Management (BLM), Department of the Interior",
      "what": "BLM approved a right-of-way for the Townsite Data Center in Nevada on June 26 and announced it on July 20, 2026. BLM's NEPA register still showed the decision in its appeal period. The files say public sources differ on the acreage.",
      "stage": "approved or adopted",
      "status_word": "right-of-way decision; in appeal period",
      "path": "agency-order-or-decision",
      "rests_on": "official record, linked (BLM decision and NEPA register)",
      "quote": {
        "text": "BLM Townsite right-of-way approval, Nevada, announced July 20, 2026.",
        "file": "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md"
      },
      "files": [
        "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md",
        "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_LEGAL_SPINE_2025-2026.md",
        "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_CLAIM_FIREWALL_AND_WATCHBOARD_2026-08-20.md",
        "Data Center Federal Legal Spine 2025-2026/README.md",
        "Data Center Federal Legal Spine 2025-2026/DATA_CENTER_FEDERAL_LEGAL_OBJECT_REGISTRY_2026-08-20.json"
      ],
      "register_records": [
        "BLM-TOWNSITE-ROW"
      ],
      "disagreement": "none recorded",
      "source_check": "none",
      "from_register": false,
      "weight": "step",
      "where_in_the_system": "Authorization: lease or right-of-way",
      "thesis_words": [],
      "what_moves": "land: right-of-way on BLM land approved, subject to appeal",
      "note": "The audit file lists it under the order's section 9 Interior land instruction; the object registry describes the decision as 'consistent with EO 14318'.",
      "n": 35,
      "movement_type": "Decided"
    },
    {
      "strand": "EPA",
      "date": "2026-06-29",
      "date_exactness": "day given",
      "body": "U.S. Environmental Protection Agency (EPA)",
      "what": "The comment period on EPA's 'Begin Actual Construction' proposal closed. The rule stays proposed.",
      "stage": "comment period closed",
      "status_word": "proposal; comments closed",
      "path": "agency-rule",
      "rests_on": "official record, linked (Federal Register)",
      "quote": {
        "text": "Proposal; comments closed June 29, 2026.",
        "file": "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_CLAIM_FIREWALL_AND_WATCHBOARD_2026-08-20.md"
      },
      "files": [
        "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_CLAIM_FIREWALL_AND_WATCHBOARD_2026-08-20.md",
        "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md"
      ],
      "register_records": [],
      "disagreement": "none recorded",
      "source_check": "none",
      "from_register": false,
      "weight": "detail",
      "where_in_the_system": "Environmental permits, rules and guidance that apply to data centers",
      "thesis_words": [],
      "what_moves": "nothing recorded",
      "n": 36,
      "movement_type": "Clock date"
    },
    {
      "strand": "EPA",
      "date": "2026-07-17",
      "date_exactness": "day given (page update)",
      "body": "U.S. Environmental Protection Agency (EPA)",
      "what": "EPA updated its 'Clean Air Act resources for data centers' page, which gathers existing air-permit guidance and says state and local agencies issue most permits.",
      "stage": "published",
      "status_word": "resource page update",
      "path": "staff-position",
      "rests_on": "the body's own statement, linked",
      "quote": {
        "text": "Consolidated existing CAA permit/program guidance; confirms state/local agencies issue most permits.",
        "file": "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md"
      },
      "files": [
        "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md",
        "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_LEGAL_SPINE_2025-2026.md"
      ],
      "register_records": [],
      "disagreement": "none recorded",
      "source_check": "none",
      "from_register": false,
      "weight": "detail",
      "where_in_the_system": "Environmental permits, rules and guidance that apply to data centers",
      "thesis_words": [],
      "what_moves": "nothing recorded",
      "note": "EPA's July 16, 2026 Acid Rain Program memo on islanded generators is step 12 of the ai-datacenter-power story.",
      "n": 37,
      "movement_type": "Published"
    },
    {
      "strand": "DOE sites: Savannah River",
      "date": "2026-07-20",
      "date_exactness": "day given",
      "body": "National Nuclear Security Administration (NNSA), within DOE",
      "what": "NNSA selected Amentum to negotiate a phased lease at the Savannah River Site for a proposed 1 GW AI data center and about 2 GW of on-site power, first natural gas and later nuclear. The release cites national security and EO 14299. NNSA says the selection is not a final lease award and that negotiation, permits, safety and security review and other federal approvals remain.",
      "stage": "other",
      "status_word": "selected to enter negotiations; not a final lease award (NNSA's words)",
      "path": "contract-or-award",
      "rests_on": "the body's own statement, linked",
      "quote": {
        "text": "NNSA selected Amentum on July 20, 2026 to negotiate a phased lease for a proposed 1 GW data center and about 2 GW of on-site generation, initially gas and later nuclear.",
        "file": "Data Center Federal Legal Spine 2025-2026/PUBLIC_MILITARY_COMPUTE_AND_DATA_CENTER_OVERLAP_MAP_2026-08-20.md"
      },
      "files": [
        "Data Center Federal Legal Spine 2025-2026/PUBLIC_MILITARY_COMPUTE_AND_DATA_CENTER_OVERLAP_MAP_2026-08-20.md",
        "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md",
        "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_LEGAL_SPINE_2025-2026.md",
        "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_CLAIM_FIREWALL_AND_WATCHBOARD_2026-08-20.md",
        "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_RETURN_REFRESH_2026-10-05.md",
        "Data Center Federal Legal Spine 2025-2026/DATA_CENTER_FEDERAL_LEGAL_OBJECT_REGISTRY_2026-08-20.json",
        "Federal Science Operating System/NSSTS Technology-to-Company Map 2026-08-18/NSSTS_WAVE_2_ENERGY_MANUFACTURING_CRITICAL_MATERIALS_MAP_2026-08-18.md",
        "Trump Davos Address 2026-01-21/HINDSIGHT_LEDGER_THROUGH_2026-07-31.md",
        "Federal Government Website Sweep 2026-07-25/Domestic Systems Wave 7/DOMESTIC_SYSTEMS_WAVE_7_PRIMARY_OBJECT_LEDGER.md",
        "US Inbound Investment and Industrial Capex Funding Map 2025-2026/WAVE_1_PROJECT_LEDGER.md"
      ],
      "register_records": [
        "DOE-SRS-AMENTUM-SELECTION"
      ],
      "disagreement": "GAO-27-108063's appendix lists a lease as the realty action; GAO's narrative and NNSA's announcement give the negotiations stage.",
      "source_check": "none",
      "from_register": false,
      "weight": "turning point",
      "where_in_the_system": "Selection or agreement",
      "thesis_words": [],
      "what_moves": "land: Savannah River tracts under negotiation with Amentum",
      "n": 38,
      "corrected_2026-11-16": [
        {
          "field": "disagreement",
          "was": "none recorded",
          "now": "GAO's appendix lists a lease as the realty action; GAO's narrative and NNSA give the negotiations stage.",
          "file": "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_RETURN_REFRESH_2026-10-05.md",
          "quote": "GAO’s appendix lists a lease as the realty action. Its narrative and the NNSA announcement identify the negotiations stage."
        }
      ],
      "movement_type": "Selected or offered, not final"
    },
    {
      "strand": "DOE sites: Paducah",
      "date": "2026-07-29",
      "date_exactness": "day given in the audit file; the October 5 refresh gives 'July'",
      "body": "U.S. Department of Energy (DOE)",
      "what": "DOE announced that Brookfield was selected to develop and run a 1.8 GW AI data-center campus on about 785 acres at Paducah, and NextEra to build and own 2 GW of gas generation and up to 2.6 GW of storage. Big Rivers would provide wholesale power, Jackson Purchase retail service, and Paducah Power would be community partner. DOE said the power-service agreement is subject to Kentucky Public Service Commission approval. The announcement calls DOE's site-reuse work its 'American Energy Hubs initiative'.",
      "stage": "other",
      "status_word": "sponsor selection and partnership announcement",
      "path": "contract-or-award",
      "rests_on": "the body's own statement, linked",
      "quote": {
        "text": "RFO followed by Brookfield selection for 1.8 GW campus and NextEra selection for 2 GW gas plus up to 2.6 GW storage, about 785 acres.",
        "file": "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md"
      },
      "files": [
        "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md",
        "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_LEGAL_SPINE_2025-2026.md",
        "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_CLAIM_FIREWALL_AND_WATCHBOARD_2026-08-20.md",
        "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_RETURN_REFRESH_2026-10-05.md",
        "Data Center Federal Legal Spine 2025-2026/DATA_CENTER_FEDERAL_LEGAL_OBJECT_REGISTRY_2026-08-20.json",
        "Federal Science Operating System/NSSTS Technology-to-Company Map 2026-08-18/NSSTS_WAVE_2_ENERGY_MANUFACTURING_CRITICAL_MATERIALS_MAP_2026-08-18.md",
        "Federal Government Movement Atlas/generated/COVERAGE_GAP_AUDIT.json"
      ],
      "register_records": [
        "DOE-PADUCAH-SELECTION"
      ],
      "disagreement": "none recorded",
      "source_check": "none",
      "from_register": false,
      "weight": "turning point",
      "where_in_the_system": "Selection or agreement",
      "thesis_words": [],
      "what_moves": "land: about 785 Paducah acres (Parcel B) assigned to selected developers; DOE officials told GAO a lease was signed in July 2026 (step 40)",
      "n": 39,
      "corrected_2026-11-16": [
        {
          "field": "what_moves",
          "was": "land: about 785 Paducah acres assigned to selected developers, leases not executed",
          "now": "land: about 785 Paducah acres (Parcel B) assigned to selected developers; DOE officials told GAO a lease was signed in July 2026 (step 40)",
          "file": "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_RETURN_REFRESH_2026-10-05.md",
          "quote": "DOE officials told GAO that DOE signed a lease with a private company in July 2026 for the 785-acre Parcel B. GAO’s appendix lists Brookfield/NextEra."
        }
      ],
      "movement_type": "Selected or offered, not final"
    },
    {
      "strand": "DOE sites: Paducah",
      "date": "2026-07 (no day given)",
      "date_exactness": "month given (DOE officials to GAO, GAO-27-108063); no day",
      "body": "U.S. Department of Energy (DOE) and a private company the notes do not name (GAO's appendix lists Brookfield/NextEra)",
      "what": "DOE officials told GAO that DOE signed a lease with a private company in July 2026 for the 785-acre Parcel B at Paducah. GAO's appendix lists Brookfield/NextEra. The notes do not record the lessee's legal name, the signing day or the lease terms.",
      "stage": "lease signed (as DOE officials told GAO)",
      "status_word": "lease signed",
      "path": "contract-or-award",
      "quote": {
        "text": "DOE officials told GAO that DOE signed a lease with a private company in July 2026 for the 785-acre Parcel B. GAO’s appendix lists Brookfield/NextEra.",
        "file": "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_RETURN_REFRESH_2026-10-05.md"
      },
      "files": [
        "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_RETURN_REFRESH_2026-10-05.md"
      ],
      "weight": "turning point",
      "where_in_the_system": "Authorization: lease or right-of-way",
      "what_moves": "land: the 785-acre Parcel B at Paducah under lease to a private company",
      "rests_on": "official record, linked (SB Energy S-1/A on EDGAR; GAO-27-108063)",
      "register_records": [],
      "disagreement": "none recorded",
      "source_check": "none",
      "from_register": false,
      "thesis_words": [],
      "added_2026-11-16": "New step from the 15 November 2026 research refresh.",
      "n": 40,
      "movement_type": "Awarded or agreed"
    },
    {
      "strand": "DOE sites: Paducah",
      "date": "2026-09 (no day given)",
      "date_exactness": "month given, no day",
      "body": "U.S. Department of Energy (DOE), for the Paducah Community Advisory Board",
      "what": "DOE's September 2026 Community Advisory Board binder for Paducah mapped about 785 acres for an AI data center.",
      "stage": "published",
      "status_word": "advisory board materials",
      "path": "advisory-committee",
      "rests_on": "the body's own statement, linked",
      "quote": {
        "text": "DOE's September Community Advisory Board materials now map roughly 785 acres for an AI data center.",
        "file": "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_RETURN_REFRESH_2026-10-05.md"
      },
      "files": [
        "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_RETURN_REFRESH_2026-10-05.md"
      ],
      "register_records": [],
      "disagreement": "none recorded",
      "source_check": "none",
      "from_register": false,
      "weight": "detail",
      "where_in_the_system": "Site planning after selection",
      "thesis_words": [],
      "what_moves": "nothing recorded",
      "n": 41,
      "movement_type": "Published"
    },
    {
      "n": 42,
      "date": "2026-10-16",
      "date_exactness": "exact publication day of GAO report; underlying pause day not given",
      "strand": "DOE sites: Oak Ridge",
      "body": "U.S. Government Accountability Office, reporting statements by U.S. Department of Energy officials",
      "what": "GAO published its land-use report, recording DOE officials' statement that Oak Ridge's request for proposals for an AI data center was currently paused. The report gives no date for the pause or restart decision.",
      "stage": "reported",
      "status_word": "solicitation pause reported",
      "path": "oversight-audit",
      "rests_on": "official report, linked (GAO-27-108063)",
      "quote": {
        "file": "Data Center Federal Legal Spine 2025-2026/DOE_LAND_REUSE_AND_OAK_RIDGE_PAUSE_2026-11-18.md",
        "text": "GAO's October 16, 2026 report states that DOE officials described Oak Ridge's AI data-center request for proposals as currently paused."
      },
      "files": [
        "Data Center Federal Legal Spine 2025-2026/DOE_LAND_REUSE_AND_OAK_RIDGE_PAUSE_2026-11-18.md"
      ],
      "primary_source": "https://files.gao.gov/reports/GAO-27-108063/index.html",
      "register_records": [],
      "disagreement": "Underlying pause day and current restart state are not given.",
      "source_check": "November 18 targeted GAO redevelopment-section reading",
      "from_register": false,
      "weight": "detail",
      "where_in_the_system": "DOE site solicitation and realty process",
      "thesis_words": [],
      "what_moves": "The published account records a pause in the Oak Ridge commercial data-center solicitation.",
      "movement_type": "Published"
    }
  ],
  "where_in_the_system": [
    {
      "stage": "Presidential instrument signed or revoked",
      "steps": [
        1,
        6
      ],
      "note": ""
    },
    {
      "stage": "Instruction with a date on an officer or agency",
      "steps": [
        2,
        3,
        4,
        5,
        8,
        18
      ],
      "note": ""
    },
    {
      "stage": "Financial-support initiative (order section 3)",
      "steps": [
        19
      ],
      "note": "The notes record no Commerce or OSTP initiative document, agency inventory or support award under section 3 as of 2026-11-15 (latest refresh through November 15, 2026)."
    },
    {
      "stage": "Federal land offered: sites identified",
      "steps": [
        7
      ],
      "note": ""
    },
    {
      "stage": "Proposal or solicitation",
      "steps": [
        9,
        11,
        12,
        13,
        15,
        28
      ],
      "note": ""
    },
    {
      "stage": "Responses to a solicitation",
      "steps": [
        14,
        33
      ],
      "note": ""
    },
    {
      "stage": "NEPA review route for a named federal action (categorical exclusion determination)",
      "steps": [
        16,
        21,
        29,
        30,
        31
      ],
      "note": ""
    },
    {
      "stage": "Government-wide review rules and guidance",
      "steps": [
        27
      ],
      "note": ""
    },
    {
      "stage": "Permitting coordination (FAST-41 covered project)",
      "steps": [
        26,
        34
      ],
      "note": ""
    },
    {
      "stage": "Environmental permits, rules and guidance that apply to data centers",
      "steps": [
        10,
        17,
        20,
        23,
        32,
        36,
        37
      ],
      "note": ""
    },
    {
      "stage": "Selection or agreement",
      "steps": [
        25,
        38,
        39
      ],
      "note": ""
    },
    {
      "stage": "Authorization: lease or right-of-way",
      "steps": [
        22,
        24,
        35,
        40
      ],
      "note": ""
    },
    {
      "stage": "Site planning after selection",
      "steps": [
        41
      ],
      "note": ""
    },
    {
      "stage": "Construction",
      "steps": [
        24
      ],
      "note": "Groundbreaking at Portsmouth, as DOE states it. The notes record no construction at any other site as of 2026-11-15."
    },
    {
      "stage": "Operation",
      "steps": [],
      "note": "The notes record no operating data center on any of these federal sites as of 2026-11-15."
    }
  ],
  "quiet_stretch": [
    {
      "from": "2025-11-17",
      "to": "2026-03-20",
      "what": "On the DOE land strand, the notes record the February 26, 2026 Portsmouth lease (step 22) between the Portsmouth categorical exclusion and the March 20 Portsmouth announcement. Paducah offers were due January 30, 2026.",
      "was_2026-11-14": "On the DOE land strand, the notes record no selection or lease between the Portsmouth categorical exclusion and the March 20 Portsmouth announcement. Paducah offers were due January 30, 2026.",
      "corrected_2026-11-16": {
        "field": "what",
        "was": "the notes record no selection or lease between the Portsmouth categorical exclusion and the March 20 Portsmouth announcement",
        "now": "Portsmouth lease entered February 26, 2026",
        "file": "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_RETURN_REFRESH_2026-10-05.md",
        "quote": "SB Energy’s September S-1/A identifies Pike County Portsmouth DC LLC as the subsidiary that entered into a DOE lease on February 26, 2026. GAO records 189 acres."
      }
    },
    {
      "from": "2026-01-30",
      "to": "2026-07-29",
      "what": "Paducah offers were due January 30, 2026; the notes record the April 29 and May 4 categorical exclusions and then DOE's July 29 selections."
    },
    {
      "from": "2025-09-30",
      "to": "2026-07-20",
      "what": "Savannah River: the notes record no step between NNSA's request for proposals and the Amentum selection."
    },
    {
      "from": "2025-09-09",
      "to": "2026-11-15",
      "what": "Idaho National Laboratory and Oak Ridge: the notes record no selection after the September 2025 solicitations."
    },
    {
      "from": "2026-07-29",
      "to": "2026-11-15",
      "what": "After the July 29 Paducah selections, the notes record the July 2026 Paducah lease reported to GAO (step 40, no day), the September Paducah advisory board binder, and the refresh through November 15, 2026, which records no executed lease at Savannah River.",
      "was_2026-11-14": "The notes record one later dated step on any site (the September Paducah advisory board binder) and the October 5, 2026 check, which records no executed lease at Savannah River or Paducah."
    }
  ],
  "same_days": {
    "2025-07-23 (EO 14318 signed)": [
      {
        "date": "2025-07-23",
        "body": "White House (publication)",
        "line": "Released 'Winning the AI Race: America's AI Action Plan', with building AI infrastructure as one of three pillars.",
        "file": "Sovereign Compute/FEDERAL_TRIBAL_COMPUTE_MOBILIZATION_TIMELINE.md"
      },
      {
        "date": "2025-07-23",
        "body": "The President",
        "line": "Signed EO 14319, which expressly builds on EO 13960.",
        "file": "Executive Order Source Library/Biden Backfill 2026-10-30/WAVE_8B3_AI_INFRASTRUCTURE.md"
      },
      {
        "date": "2025-07-23",
        "body": "not named in the record",
        "line": "A Japan investment vehicle of more than $550 billion was announced.",
        "file": "US Inbound Investment and Industrial Capex Funding Map 2025-2026/FROZEN_CLAIM_BOOK_WAVE_1.md"
      },
      {
        "date": "2025-07-24",
        "body": "Congress (Public Law 119-28)",
        "line": "The Rescissions Act of 2025 rescinded unobligated USAID, IAF, USADF and USIP balances.",
        "file": "Federal Government Entity Library Harvest 2026-08-22/waves/WAVE_1A_LEGAL.md"
      }
    ],
    "2026-03-20 (Portsmouth lease announced)": [
      {
        "date": "2026-03-20",
        "body": "White House",
        "line": "Sent Congress National Policy Framework legislative recommendations for a uniform federal AI framework.",
        "file": "Federal Agency AI Plans and Infrastructure 2025-2026/OVERALL_AI_TRANSITION_PROPOSAL_TO_OPERATION_MAP_2026-09-28.md"
      },
      {
        "date": "2026-03-19",
        "body": "International Energy Agency member governments",
        "line": "Oil-stock contribution plans under the collective action totaled 426 million barrels.",
        "file": "G7 and G20 Coordination Architecture 2025-2026/G7_G20_PHYSICAL_POWER_AND_INDUSTRIAL_SYSTEMS_2025-2026.md"
      },
      {
        "date": "2026-03-17",
        "body": "DOE (Office of Science; Genesis Mission)",
        "line": "Announced a Genesis request for applications with an anticipated $293.76 million.",
        "file": "Federal Science Operating System/FEDERAL_SCIENCE_OPERATING_SYSTEM_FACTUAL_SPINE_2025-2026.md"
      }
    ],
    "2026-03-26 (Army conditional selections)": [
      {
        "date": "2026-03-26",
        "body": "The President",
        "line": "EO 14398 directed contract clauses and declared compliance material to False Claims Act payment decisions.",
        "file": "Fraud and Payment Integrity/False Claims Act and Treasury Consolidation 2026-10-20/FALSE_CLAIMS_ACT_MAP.md"
      },
      {
        "date": "2026-03-25",
        "body": "DOE Office of Indian Energy",
        "line": "Announced the $50 million 'Unleashing Tribal Energy Development' funding opportunity.",
        "file": "Sovereign Compute/FEDERAL_TRIBAL_COMPUTE_MOBILIZATION_TIMELINE.md"
      },
      {
        "date": "2026-03-26",
        "body": "South Carolina regulators (not named in the file)",
        "line": "Approved Duke Energy's about 1.365 GW combined-cycle project in Anderson County.",
        "file": "AI-Enabled Turbine Asset Management and US Power Buildout 2025-2026/US_TURBINE_BUILDOUT_AND_ADOPTION_CLOCKS_2026-08-09.md"
      }
    ],
    "2026-07-20 (Savannah River selection)": [
      {
        "date": "2026-07-20",
        "body": "Economic Development Administration (Commerce)",
        "line": "Said Commerce intends to award $169 million across six selected Tech Hubs.",
        "file": "Federal Government Website Sweep 2026-07-25/Domestic Systems Wave 7/DOMESTIC_SYSTEMS_WAVE_7_PRIMARY_OBJECT_LEDGER.md"
      },
      {
        "date": "2026-07-22",
        "body": "DOE (Genesis Mission)",
        "line": "Selected 278 projects for award negotiations.",
        "file": "Federal Government Whole-Site Recertification 2026-08-01/lanes/TRUMP_AI_EXECUTIVE_ORDER_OFFICIAL_INVENTORY_2026-08-01.md"
      },
      {
        "date": "2026-07-23",
        "body": "White House (publication)",
        "line": "Widened the voluntary Ratepayer Protection Pledge on data-center electricity costs to utilities, cooperatives, developers and 23 governors.",
        "file": "Federal Government Website Sweep 2026-07-25/Executive Office Wave 2/EXECUTIVE_OFFICE_WAVE_2_PRIMARY_OBJECT_LEDGER.md"
      }
    ],
    "2026-07-29 (Paducah selections)": [
      {
        "date": "2026-07-29",
        "body": "Congressional Budget Office",
        "line": "Published a working paper modelling how longer and less certain permitting raises the cost of capital.",
        "file": "Federal Government Whole-Site Recertification 2026-08-01/lanes/CONGRESS_JUDICIARY_GOVERNMENT_RECORDS_DELTA_2026-08-01.md"
      },
      {
        "date": "2026-07-28",
        "body": "DOE",
        "line": "Order 4410-B extended Gulf LNG's non-free-trade-agreement export start deadline to July 31, 2031.",
        "file": "Federal Government Whole-Site Recertification 2026-08-01/Physical Production Systems Full-Surface Wave 2026-08-04/PHYSICAL_PRODUCTION_SYSTEMS_FULL_SURFACE_WAVE_2026-08-04.md"
      },
      {
        "date": "2026-07-31",
        "body": "Department of War, Office of Strategic Capital",
        "line": "Signed a conditional loan commitment of up to $820 million with Performance Drone Works.",
        "file": "Federal Government Whole-Site Recertification 2026-08-01/lanes/DEFENSE_INTELLIGENCE_FOREIGN_AFFAIRS_DELTA_2026-08-01.md"
      }
    ]
  },
  "where_it_stands": "As of 2026-11-15 (latest research file: the Federal Data Center Return Refresh, with federal land and permitting checked through November 15, 2026): EO 14318 is in force and EO 14141 is revoked. On DOE land, Pike County Portsmouth DC LLC, an SB Energy subsidiary, entered a DOE lease at Portsmouth on February 26, 2026 (189 acres; groundbreaking March 20, 2026); DOE officials told GAO that DOE signed a lease with a private company in July 2026 for the 785-acre Parcel B at Paducah, where Brookfield and NextEra are the selected developers and the power-service agreement awaits Kentucky Public Service Commission approval; Amentum is selected to negotiate at Savannah River; Idaho National Laboratory remains at the previously recorded solicitation stage. A November 18 check of GAO's October 16 report adds DOE officials' statement that the separate Oak Ridge commercial AI data-center solicitation was paused; the report gives no pause day or restart decision. On military land, Carlyle (Fort Bliss) and CyrusOne (Dugway) are in exclusive Army negotiations; the Air Force solicitations at five installations and in Alaska have no recorded selection, and Arnold received no proposal. BLM's Townsite right-of-way was in its appeal period at the August 20 check. QTS Richmond and PORTS are FAST-41 covered projects in progress. Nationwide Permit 39 is in effect; EPA's NSR construction rule is proposed with comments closed. DOE calls its site-reuse work the American Energy Hubs initiative. The notes record no section 3 financial-support initiative from Commerce or OSTP as of 2026-11-15.",
  "next_dated": [
    {
      "when": "2026-12-23",
      "what": "Estimated completion of the PORTS Technology Campus FAST-41 schedule (as shown at the August 20 check).",
      "stage": "scheduled",
      "files": [
        "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md"
      ]
    },
    {
      "when": "2027-06-11",
      "what": "Estimated completion of the QTS Richmond Data Center 5 FAST-41 schedule.",
      "stage": "scheduled",
      "files": [
        "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md"
      ]
    },
    {
      "when": "FY2027",
      "what": "Projected initial operation at Fort Bliss (Carlyle).",
      "stage": "projected by the Army",
      "files": [
        "Data Center Federal Legal Spine 2025-2026/PUBLIC_MILITARY_COMPUTE_AND_DATA_CENTER_OVERLAP_MAP_2026-08-20.md"
      ]
    },
    {
      "when": "FY2029",
      "what": "Projected initial operation at Dugway (CyrusOne).",
      "stage": "projected by the Army",
      "files": [
        "Data Center Federal Legal Spine 2025-2026/PUBLIC_MILITARY_COMPUTE_AND_DATA_CENTER_OVERLAP_MAP_2026-08-20.md"
      ]
    },
    {
      "when": "no date given",
      "what": "Kentucky Public Service Commission decision on the Paducah power-service agreement; lease negotiations at Savannah River, Fort Bliss and Dugway; end of the Townsite appeal period; rolling review at Idaho National Laboratory.",
      "stage": "pending",
      "files": [
        "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_RETURN_REFRESH_2026-10-05.md",
        "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md",
        "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_CLAIM_FIREWALL_AND_WATCHBOARD_2026-08-20.md"
      ]
    }
  ],
  "not_shown": [
    "The notes do not record a Commerce or OSTP section 3 initiative document, an agency inventory of existing support sent to OSTP, or any loan, guarantee, grant, tax incentive or offtake agreement under section 3.",
    "The notes do not record the agencies' 10-day categorical exclusion submissions to CEQ, or a new categorical exclusion written for data centers.",
    "The notes do not record a FAST-41 transparency-project designation by the Permitting Council's Executive Director under section 6(a).",
    "The notes do not record a list of Brownfield or Superfund sites identified by EPA for qualifying projects under section 7(b).",
    "The notes do not record programmatic Endangered Species Act consultation under section 8(a).",
    "The notes do not record a review or decision by the Assistant Secretary of the Army for Civil Works under section 8(b).",
    "The notes do not record an Interior list of sites or a Secretary's designation of a Qualifying Project.",
    "The notes do not record the rent, duration or renewal terms of the Portsmouth lease.",
    "The notes do not record an executed lease at Savannah River, Fort Bliss or Dugway, or a selection at Idaho National Laboratory, Oak Ridge, the four other Air Force installations or Alaska. For Paducah, the notes do not record the lessee's legal name, the signing day or the lease terms.",
    "The notes do not record the end of the Townsite appeal period or the right-of-way acreage.",
    "The notes do not record a final NSR 'Begin Actual Construction' rule.",
    "The notes do not record any result of EO 14141's 2025 dates.",
    "The notes do not record the date of Arnold's no-proposal notice."
  ],
  "where_the_files_stop_top5": [
    "A Commerce or OSTP section 3 initiative document or award.",
    "The Portsmouth lease terms (rent, duration, renewal).",
    "Executed leases at Savannah River, Fort Bliss and Dugway; the Paducah lessee's legal name, signing day and terms.",
    "The Kentucky Public Service Commission decision on the Paducah power-service agreement.",
    "Selections under the Air Force five-installation and Alaska solicitations."
  ],
  "touches": [
    {
      "thread": "ai-datacenter-power (batch 5 story)",
      "at_step": "step 37",
      "how": "Grid side of the same projects. Its step 12 is EPA's July 16, 2026 Acid Rain Program memo on islanded generators; its touches list EO 14318.",
      "file": "Stories 2026-11-14/batch 5/ai-datacenter-power.json"
    },
    {
      "thread": "army-strategic-capital-initiatives (batch 4 story)",
      "at_step": "step 25",
      "how": "The Army's Strategic Capital Initiative leases installation land for power plants under 10 U.S.C. section 2667 (requests June 15, 2026; conditional awards September 18, 2026). No file used here links it to the Fort Bliss and Dugway selections.",
      "file": "Stories 2026-11-14/batch 4/army-strategic-capital-initiatives.json"
    },
    {
      "thread": "fortress-america (batch 4 story)",
      "at_step": "none",
      "how": "Department of Defense program announced September 30, 2026 with an independent-power goal for major installations. No file used here mentions it.",
      "file": "Stories 2026-11-14/batch 4/fortress-america.json"
    },
    {
      "thread": "federal-land-datacenters",
      "at_step": "steps 7-41",
      "how": "Folded in: its files are the land steps of this story."
    },
    {
      "thread": "savannah-river-datacenter",
      "at_step": "step 38",
      "how": "Folded in: its file records the Amentum selection.",
      "file": "Trump Davos Address 2026-01-21/HINDSIGHT_LEDGER_THROUGH_2026-07-31.md"
    },
    {
      "thread": "military-microreactors (EO 14299)",
      "at_step": "step 38",
      "how": "The Savannah River release cites EO 14299 (May 23, 2025), which directs DOE to start critical-defense-facility designation for qualifying AI data centers at or coordinated with DOE facilities.",
      "file": "Data Center Federal Legal Spine 2025-2026/PUBLIC_MILITARY_COMPUTE_AND_DATA_CENTER_OVERLAP_MAP_2026-08-20.md"
    },
    {
      "thread": "ndaa-datacenter-duties",
      "at_step": "none",
      "how": "FY2026 NDAA (Public Law 119-60, enacted December 18, 2025): section 321 Navy nuclear pilot to start by December 18, 2026; section 1531 military data-center estimates, first update March 1, 2027.",
      "file": "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_LEGAL_SPINE_2025-2026.md"
    },
    {
      "thread": "datacenter-legislation",
      "at_step": "none",
      "how": "H.R.9939, No AI Data Centers on Federal Lands Act, introduced July 23, 2026 and referred to House Natural Resources.",
      "file": "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_LEGISLATION_REGISTRY_119TH_CONGRESS_2026-08-20.md"
    },
    {
      "thread": "nepa-permitting-changes",
      "at_step": "steps 27, 32, 36",
      "how": "CEQ removed its government-wide NEPA regulations (interim final February 25, 2025; final January 8, 2026). The CEQ guidance and the EPA NSR proposal are also in that thread.",
      "file": "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md"
    },
    {
      "thread": "jan-2025-mass-revocation",
      "at_step": "steps 1 and 6",
      "how": "EO 14141 was not among the January 20, 2025 rescissions; EO 14318 section 4 revoked it.",
      "file": "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md"
    },
    {
      "thread": "doe-indian-energy-datacenters",
      "at_step": "none",
      "how": "DOE Office of Indian Energy data-center publications and events for Tribes (January 20, 2026 onward). The Sovereign Compute timeline says EO 14318 does not designate tribal land.",
      "file": "Sovereign Compute/FEDERAL_TRIBAL_COMPUTE_MOBILIZATION_TIMELINE.md"
    },
    {
      "thread": "doe-speed-to-power",
      "at_step": "step 39",
      "how": "The October 5 refresh says DOE's Speed to Power page separately lists large-load, transmission, technical-assistance and Tribal-energy actions.",
      "file": "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_RETURN_REFRESH_2026-10-05.md"
    },
    {
      "thread": "xai-southaven-suit",
      "at_step": "none",
      "how": "DOJ moved on June 15, 2026 to intervene in and dismiss a private Clean Air Act suit over the Southaven, Mississippi xAI/MZX Tech facility.",
      "file": "Data Center Federal Legal Spine 2025-2026/DATA_CENTER_WAR_LANDSCAPE_FRESH_ORIENTATION_2026-08-20.md"
    }
  ],
  "foundation": [
    {
      "file": "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md",
      "why": "One table per instruction of EO 14318, with what agencies issued by August 20, 2026, and the site-by-site land ledger."
    },
    {
      "file": "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_RETURN_REFRESH_2026-10-05.md",
      "why": "The October 5, 2026 check of Savannah River, Paducah, the section 3 initiative and DOE's American Energy Hubs name."
    },
    {
      "file": "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_LEGAL_SPINE_2025-2026.md",
      "why": "Section 1 gives the order's definitions and instructions; section 2 gives each land and permit step by stage."
    }
  ],
  "interpretation": [
    {
      "claim": "Codex's reading of the federal side",
      "quote": "federal agencies can accelerate their own procedures and property, while many decisive retail-power, water and land-use decisions remain state or local.",
      "file": "Data Center Federal Legal Spine 2025-2026/DATA_CENTER_WAR_LANDSCAPE_FRESH_ORIENTATION_2026-08-20.md"
    },
    {
      "claim": "Codex's ruling on environmental law",
      "quote": "some federal review pathways have been accelerated or clarified; ordinary project-level environmental gates remain unless a competent authority has issued the relevant instrument.",
      "file": "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_LEGAL_SPINE_2025-2026.md"
    },
    {
      "claim": "Codex's summary of implementation",
      "quote": "Executive implementation is real but decentralized.",
      "file": "Data Center Federal Legal Spine 2025-2026/README.md"
    },
    {
      "claim": "Codex's reading of military land leases",
      "quote": "Federal real estate is becoming a commercial capacity lane",
      "file": "Data Center Federal Legal Spine 2025-2026/PUBLIC_MILITARY_COMPUTE_AND_DATA_CENTER_OVERLAP_MAP_2026-08-20.md"
    },
    {
      "claim": "Codex's reading of DOE's American Energy Hubs name",
      "quote": "DOE's named lane is real; it is not a government-wide fund, entitlement or single approval path.",
      "file": "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_RETURN_REFRESH_2026-10-05.md"
    },
    {
      "claim": "Codex's thesis reading of EO 14318 in the AI transition register",
      "quote": "Makes compute policy inseparable from land, power, and permitting.",
      "file": "Federal Agency AI Plans and Infrastructure 2025-2026/FEDERAL_AI_TRANSITION_PROPOSAL_REGISTER_2026-09-28.json"
    }
  ],
  "left_out": [
    "EPA's July 16, 2026 islanded-generator Acid Rain Program memo: step 12 of the ai-datacenter-power story.",
    "FERC's large-load cases and the Ratepayer Protection Pledge: in the ai-datacenter-power story.",
    "Project Skye individual section 404 permit notice (Corps Norfolk District, June 29, 2026; comments closed July 28): a private project's permit application that no file ties to EO 14318.",
    "CEQ's removal of its NEPA regulations (February 25, 2025 and January 8, 2026): under touches (nepa-permitting-changes).",
    "State and local steps in the landscape file (Texas SB 6, Oregon HB 3546, Virginia GS-5, Georgia, New York EO 62, Loudoun, Prince William, Illinois): not federal.",
    "Kentucky PSC's June 1, 2026 EKPC Data Center Power tariff: the refresh file says it is not the Paducah approval.",
    "Savannah River nuclear-cleanup contracts of September 2026: the refresh file says they belong to the site's other missions.",
    "Military cloud and AI procurements (JWCC, DISA Cloud Instance, CDAO frontier-AI agreements): not land or permitting steps.",
    "The White House AI Action Plan of July 23, 2025: under same_days.",
    "Federal Register notice of a Paducah Environmental Management Site-Specific Advisory Board meeting (public inspection August 21, 2026, published August 24): the notice does not say it concerns the data center.",
    "EO 14141's other instructions (security, power, chips, budget scoring, geothermal, transmission): no dated result in the notes; four of its dates are steps 2-5."
  ],
  "open_points": [
    {
      "kind": "missing fact",
      "what": "The notes record no Commerce or OSTP section 3 initiative, agency inventory or support award as of 2026-11-15.",
      "where": "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_RETURN_REFRESH_2026-10-05.md, section 1; Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_CLAIM_FIREWALL_AND_WATCHBOARD_2026-08-20.md, watchboard",
      "settled": "no",
      "fix": ""
    },
    {
      "kind": "missing fact",
      "what": "The rent, duration and renewal terms of the Portsmouth lease are not given. The lessee (Pike County Portsmouth DC LLC) and date (February 26, 2026) are in the November 15 refresh.",
      "where": "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_RETURN_REFRESH_2026-10-05.md, 'Federal land and permitting through November 15, 2026'",
      "settled": "no",
      "fix": ""
    },
    {
      "kind": "disagreement",
      "what": "The object registry dates QTS Richmond DC5's FAST-41 coverage 2026-04-01; the Sovereign Compute timeline's open questions refer to a FAST-41 data-center project 'approved in April 2025' without naming it.",
      "where": "Data Center Federal Legal Spine 2025-2026/DATA_CENTER_FEDERAL_LEGAL_OBJECT_REGISTRY_2026-08-20.json (FAST41-QTS-RIC5); Sovereign Compute/FEDERAL_TRIBAL_COMPUTE_MOBILIZATION_TIMELINE.md, open questions",
      "settled": "no",
      "fix": ""
    },
    {
      "kind": "missing fact",
      "what": "The FAST-41 coverage dates (2026-04-01 QTS; 2026-06-11 PORTS) appear in the object registry; the markdown files give no coverage dates.",
      "where": "Data Center Federal Legal Spine 2025-2026/DATA_CENTER_FEDERAL_LEGAL_OBJECT_REGISTRY_2026-08-20.json",
      "settled": "no",
      "fix": ""
    },
    {
      "kind": "missing fact",
      "what": "The day of EPA's Superfund and Brownfield guidance is not given; the registry uses the order's January 19, 2026 date and says the document is dated January 2026.",
      "where": "Data Center Federal Legal Spine 2025-2026/DATA_CENTER_FEDERAL_LEGAL_OBJECT_REGISTRY_2026-08-20.json (EPA-CERCLA-BROWNFIELDS-GUIDANCE)",
      "settled": "no",
      "fix": ""
    },
    {
      "kind": "missing fact",
      "what": "The date of Arnold Air Force Base's no-proposal notice is not given.",
      "where": "Data Center Federal Legal Spine 2025-2026/PUBLIC_MILITARY_COMPUTE_AND_DATA_CENTER_OVERLAP_MAP_2026-08-20.md; Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md",
      "settled": "no",
      "fix": ""
    },
    {
      "kind": "missing fact",
      "what": "The Townsite right-of-way acreage; the files say public sources differ.",
      "where": "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md, DOD and DOI ledger",
      "settled": "no",
      "fix": ""
    },
    {
      "kind": "missing fact",
      "what": "The notes record no selection or lease at Idaho National Laboratory, Oak Ridge, the four other Air Force installations or Alaska as of 2026-11-15.",
      "where": "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md; Data Center Federal Legal Spine 2025-2026/PUBLIC_MILITARY_COMPUTE_AND_DATA_CENTER_OVERLAP_MAP_2026-08-20.md",
      "settled": "no",
      "fix": ""
    },
    {
      "kind": "missing fact",
      "what": "The notes record no executed lease at Savannah River and no Kentucky PSC order on the Paducah power agreement as of 2026-11-15. For Paducah, DOE officials told GAO a lease was signed in July 2026; the notes do not record the lessee's legal name, signing day or terms.",
      "where": "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_RETURN_REFRESH_2026-10-05.md, 'Federal land and permitting through November 15, 2026' and sections 2 and 3",
      "settled": "no",
      "fix": ""
    },
    {
      "kind": "missing fact",
      "what": "The notes record no result of EO 14141's February 28, March 15, March 31 and June 30, 2025 dates.",
      "where": "Executive Order Source Library/Biden Backfill 2026-10-30/WAVE_8B3_MAP_SOURCE_SNAPSHOT.json",
      "settled": "no",
      "fix": ""
    },
    {
      "kind": "missing fact",
      "what": "The year of EO 14141's March 15, March 31 and June 30 dates is not written in the order map labels.",
      "where": "Executive Order Source Library/Biden Backfill 2026-10-30/WAVE_8B3_MAP_SOURCE_SNAPSHOT.json (eo-14141-p03, p04)",
      "settled": "no",
      "fix": ""
    },
    {
      "kind": "missing fact",
      "what": "The notes do not name the DOE office or official that signed the site selection, the solicitations or the Paducah selection.",
      "where": "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md",
      "settled": "no",
      "fix": ""
    },
    {
      "kind": "lead",
      "what": "The DOE categorical exclusion index for Portsmouth and Paducah may hold determinations after May 4, 2026.",
      "where": "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md, project-specific DOE categorical-exclusion returns",
      "settled": "no",
      "fix": ""
    },
    {
      "kind": "lead",
      "what": "A Federal Register notice of a Paducah Environmental Management Site-Specific Advisory Board meeting was on public inspection August 21, 2026; the September binder (step 41) may be from that board.",
      "where": "Federal Government Full Freshness Sweep 2026-08-22/source_snapshots/2026-08-22__public-inspection-current.json",
      "settled": "no",
      "fix": ""
    }
  ],
  "files_used": {
    "thread_files": [
      "Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md",
      "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_LEGAL_SPINE_2025-2026.md",
      "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_CLAIM_FIREWALL_AND_WATCHBOARD_2026-08-20.md",
      "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_RETURN_REFRESH_2026-10-05.md",
      "Data Center Federal Legal Spine 2025-2026/DATA_CENTER_WAR_LANDSCAPE_FRESH_ORIENTATION_2026-08-20.md",
      "Data Center Federal Legal Spine 2025-2026/README.md",
      "Executive Order Source Library/Biden Backfill 2026-10-30/WAVE_8B3_AI_INFRASTRUCTURE.md",
      "Sovereign Compute/FEDERAL_TRIBAL_COMPUTE_MOBILIZATION_TIMELINE.md"
    ],
    "folded_thread_files": [
      "Data Center Federal Legal Spine 2025-2026/PUBLIC_MILITARY_COMPUTE_AND_DATA_CENTER_OVERLAP_MAP_2026-08-20.md",
      "Federal Science Operating System/NSSTS Technology-to-Company Map 2026-08-18/NSSTS_WAVE_2_ENERGY_MANUFACTURING_CRITICAL_MATERIALS_MAP_2026-08-18.md",
      "Trump Davos Address 2026-01-21/HINDSIGHT_LEDGER_THROUGH_2026-07-31.md"
    ],
    "related_files": [
      "Data Center Federal Legal Spine 2025-2026/DATA_CENTER_FEDERAL_LEGAL_OBJECT_REGISTRY_2026-08-20.json",
      "Executive Order Source Library/Biden Backfill 2026-10-30/WAVE_8B3_MAP_SOURCE_SNAPSHOT.json",
      "Federal Government Website Sweep 2026-07-25/Domestic Systems Wave 7/DOMESTIC_SYSTEMS_WAVE_7_PRIMARY_OBJECT_LEDGER.md",
      "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_LEGISLATION_REGISTRY_119TH_CONGRESS_2026-08-20.md",
      "Federal Science Operating System/FEDERAL_SCIENCE_OPERATING_SYSTEM_FACTUAL_SPINE_2025-2026.md",
      "Federal Government Whole-Site Recertification 2026-08-01/lanes/TRUMP_AI_EXECUTIVE_ORDER_OFFICIAL_INVENTORY_2026-08-01.md",
      "Federal Government Movement Atlas/generated/COVERAGE_GAP_AUDIT.json",
      "US Inbound Investment and Industrial Capex Funding Map 2025-2026/WAVE_1_PROJECT_LEDGER.md",
      "Federal Science Operating System/NSSTS Technology-to-Company Map 2026-08-18/NSSTS_WAVE_2_CLAIM_AUDIT_AND_WATCHBOARD_2026-08-18.md",
      "Federal Agency AI Plans and Infrastructure 2025-2026/FEDERAL_AI_TRANSITION_PROPOSAL_REGISTER_2026-09-28.json",
      "Data Center Federal Legal Spine 2025-2026/DOE_LAND_REUSE_AND_OAK_RIDGE_PAUSE_2026-11-18.md"
    ],
    "vault_files": [
      "03 - Executive Orders/2025-07-23 - EO 14318 - Accelerating Federal Permitting of Data Center Infrastructure.md",
      "00 - Index/Operation Inch by Inch/Executive Order Map 2026-11-14/ORDER_MAP_MERGED.json"
    ]
  },
  "register_records_used": [
    "AIR-FORCE-RFLP-ALASKA",
    "AIR-FORCE-RFLP-FIVE",
    "ARMY-FORT-BLISS-DUGWAY",
    "BLM-TOWNSITE-ROW",
    "DOE-CX-270875",
    "DOE-CX-270900",
    "DOE-CX-270955",
    "DOE-CX-270956",
    "DOE-CX-270971",
    "DOE-FOUR-SITES",
    "DOE-INL-RFA",
    "DOE-OAK-RIDGE-RFP",
    "DOE-PADUCAH-RFO",
    "DOE-PADUCAH-SELECTION",
    "DOE-PORTSMOUTH-LEASE",
    "DOE-SRS-AMENTUM-SELECTION",
    "DOE-SRS-RFP",
    "EO 14141",
    "EO 14141 status 1",
    "EO-14318",
    "EPA-CERCLA-BROWNFIELDS-GUIDANCE",
    "EPA-NSR-BEGIN-CONSTRUCTION",
    "EPA-TSCA-PRIORITY",
    "FAST41-PORTS",
    "FAST41-QTS-RIC5",
    "GAP-CEQ-CE-INVENTORY",
    "GAP-COMMERCE-OSTP-SECTION-3",
    "USACE-NWP-39",
    "ai-transition-eo-14318-data-centers",
    "eo-14141-p02",
    "eo-14141-p03",
    "eo-14141-p04",
    "fgm-2025-01-14-eo-14141-federal-site-lease-security-cost-framework"
  ],
  "counts": {
    "thread_files": 8,
    "folded_thread_files": 3,
    "raw_happenings_in_thread_files": 83,
    "raw_happenings_in_folded_thread_files": "20 (overlap map 9, NSSTS wave 2 11); the Davos ledger has no reader record",
    "happenings_kept": "about 45 (not counted one by one)",
    "steps": 42,
    "turning_points": 7,
    "steps_with_disagreement": 3,
    "steps_with_saved_original": 0,
    "steps_from_register_only": 4,
    "open_points": 14,
    "open_points_missing_fact": 11,
    "open_points_error_under_four_tests": 0
  },
  "builder_notes": "Scope. The register gives 8 thread files. Folded in: federal-land-datacenters (possible_same_as; adds the military overlap map and the NSSTS wave 2 map) and savannah-river-datacenter (adds the Davos hindsight ledger). Read and not folded: powering-datacenters-authorities and ferc-large-load-proceedings (in the batch 5 ai-datacenter-power story), nepa-permitting-changes (CEQ rule removal kept under touches), datacenter-legislation, ndaa-datacenter-duties. A search of all research files for the order number and the site and company names found 167 files; the markdown files with steps on this story were read. The object registry JSON in the same package supplies dates for the FAST-41 listings and two solicitation quotes. Steps 2-5 come from the order map snapshot in the Executive Order Source Library (register records eo-14141-p02 to p04); their year is not written in the labels and is recorded in date_note. No step is called the carrying-out of an EO 14318 instruction unless a file places it under that instruction; where the audit file lists a step under a section, the step's note says so, and where the audit file says a notice does not cite the order (step 17), the note says that. The order map was used for each instruction; its found and found-in-part entries are steps 17 (section 8(b)), 20 (7(b)), 24 (9(b)), 25 and 33 (6(b)), 26 (5(b)), 31 (7(a)) and 34 with the DOE land steps (9(a)). The EPA 16 July 2026 islanded-generator memo is left to the ai-datacenter-power story. Quote check: 50 of 50 found word for word (39 step quotes, 6 interpretation quotes, 5 of Katie's recorded words), after removing markdown marks and collapsing whitespace; JSON files checked as raw text. Step pointers checked by script after the last numbering. Hard: many land objects have their own clocks and several dates appear in one file only; the FAST-41 listing dates come from the object registry alone.",
  "checks_applied_2026-11-14": [
    {
      "where": "all quotes",
      "why": "Batch 6 rule: checked by script against research files; 50 of 50 found.",
      "evidence_file": "scratch check.py"
    }
  ],
  "renumbered_2026-11-16": {
    "22": 23,
    "23": 24,
    "24": 25,
    "25": 26,
    "26": 27,
    "27": 28,
    "28": 29,
    "29": 30,
    "30": 31,
    "31": 32,
    "32": 33,
    "33": 34,
    "34": 35,
    "35": 36,
    "36": 37,
    "37": 38,
    "38": 39,
    "39": 41,
    "new": "New steps 22 (2026-02-26, Portsmouth lease) and 40 (2026-07, Paducah lease)."
  },
  "filled_2026-11-16": [
    {
      "from": "not_shown",
      "was": "The notes do not record the date, terms or legal party of the Portsmouth lease, or how much of the announced 10 GW campus is on DOE land.",
      "fact": "Pike County Portsmouth DC LLC, an SB Energy subsidiary, entered into a DOE lease on February 26, 2026 (SB Energy's September S-1/A); GAO records 189 acres; SB Energy expects one data-center building on DOE land and most campus buildings on private land.",
      "file": "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_RETURN_REFRESH_2026-10-05.md",
      "quote": "SB Energy’s September S-1/A identifies Pike County Portsmouth DC LLC as the subsidiary that entered into a DOE lease on February 26, 2026. GAO records 189 acres.",
      "quote_2": "SB Energy expects one data-center building on DOE land and most campus buildings on private land."
    },
    {
      "from": "not_shown (part)",
      "was": "The notes do not record an executed lease at Savannah River, Paducah, Fort Bliss or Dugway, or a selection at Idaho National Laboratory, Oak Ridge, the four other Air Force installations or Alaska.",
      "fact": "Paducah: DOE officials told GAO that DOE signed a lease with a private company in July 2026 for the 785-acre Parcel B; GAO's appendix lists Brookfield/NextEra.",
      "file": "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_RETURN_REFRESH_2026-10-05.md",
      "quote": "DOE officials told GAO that DOE signed a lease with a private company in July 2026 for the 785-acre Parcel B. GAO’s appendix lists Brookfield/NextEra."
    },
    {
      "from": "open_points",
      "was": "The date, terms and legal party of the Portsmouth lease are not given; DOE's March 20, 2026 statement names 'an SB Energy affiliate'.",
      "fact": "Lease entered February 26, 2026 by Pike County Portsmouth DC LLC (SB Energy subsidiary); 189 acres.",
      "file": "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_RETURN_REFRESH_2026-10-05.md",
      "quote": "SB Energy’s September S-1/A identifies Pike County Portsmouth DC LLC as the subsidiary that entered into a DOE lease on February 26, 2026. GAO records 189 acres."
    },
    {
      "from": "open_points (part)",
      "was": "The notes record no executed lease at Savannah River or Paducah and no Kentucky PSC order on the Paducah power agreement as of the October 5, 2026 check.",
      "fact": "DOE officials told GAO that DOE signed a lease for the 785-acre Parcel B at Paducah in July 2026.",
      "file": "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_RETURN_REFRESH_2026-10-05.md",
      "quote": "DOE officials told GAO that DOE signed a lease with a private company in July 2026 for the 785-acre Parcel B. GAO’s appendix lists Brookfield/NextEra."
    }
  ],
  "update_2026-11-16": {
    "by": "G09",
    "research_file_changed": [
      "Data Center Federal Legal Spine 2025-2026/FEDERAL_DATA_CENTER_RETURN_REFRESH_2026-10-05.md (modified 2026-11-15; steps 38, 39, 41 re-read; new steps 22 and 40)",
      "Federal Science Operating System/FEDERAL_SCIENCE_OPERATING_SYSTEM_FACTUAL_SPINE_2025-2026.md (modified 2026-11-15; step 6 re-read, no change)"
    ],
    "handoff": "The 15 November handoff's story_updates does not name this story."
  },
  "extended_2026-11-18": {
    "where_it_stands": "As of 2026-11-15 (latest research file: the Federal Data Center Return Refresh, with federal land and permitting checked through November 15, 2026): EO 14318 is in force and EO 14141 is revoked. On DOE land, Pike County Portsmouth DC LLC, an SB Energy subsidiary, entered a DOE lease at Portsmouth on February 26, 2026 (189 acres; groundbreaking March 20, 2026); DOE officials told GAO that DOE signed a lease with a private company in July 2026 for the 785-acre Parcel B at Paducah, where Brookfield and NextEra are the selected developers and the power-service agreement awaits Kentucky Public Service Commission approval; Amentum is selected to negotiate at Savannah River; Idaho National Laboratory and Oak Ridge are at the solicitation stage. On military land, Carlyle (Fort Bliss) and CyrusOne (Dugway) are in exclusive Army negotiations; the Air Force solicitations at five installations and in Alaska have no recorded selection, and Arnold received no proposal. BLM's Townsite right-of-way was in its appeal period at the August 20 check. QTS Richmond and PORTS are FAST-41 covered projects in progress. Nationwide Permit 39 is in effect; EPA's NSR construction rule is proposed with comments closed. DOE calls its site-reuse work the American Energy Hubs initiative. The notes record no section 3 financial-support initiative from Commerce or OSTP as of 2026-11-15."
  },
  "changes": [
    {
      "date": "2026-11-18",
      "by": "Codex",
      "what": "Added the October 16 GAO report of the Oak Ridge commercial AI data-center solicitation pause as step 42. Updated that component of the current position; all earlier steps and numbering retained."
    }
  ],
  "movement_types_added_2026-11-24": {
    "by": "Claude, with Katie",
    "what": "Added movement_type to every step. No other field was changed.",
    "vocabulary": "00 - Index/Operation Inch by Inch/Stories 2026-11-14/MOVEMENT TYPES — for any system.md",
    "how": "Each step was read. The type follows the step's own stage wording and what it records."
  }
}