DOE Reactor Pilot Program (Executive Order 14301, section 5) and its criticality demonstrations

Under EO 14301 the Department of Energy opened an outside-laboratory test-reactor pilot, selected eleven projects and reported five criticality demonstrations between June 4 and August 5, 2026; the NRC's rule letting applicants use prior DOE or War authorizations takes effect November 25, 2026.

Where it sits: The Technology Transition › Energy: power, fuel, nuclear and the grid › Nuclear: licensing, new reactors, restarts and fuel

How it entered the Observatory

The saved starting points
Earliest thread file
Date
2026-07-25
File
Federal Government Website Sweep 2026-07-25/Domestic Systems Wave 7/DOMESTIC_SYSTEMS_WAVE_7_PRIMARY_OBJECT_LEDGER.md
Note
The July 25 website sweep records the Unity and Aalo-X criticality releases.
Requests
  • Id
    K02-020
    When
    2026-07-25
    Her words
    I want this to be comprehensive FULL sweep, not a blanket of forced brevity.
    Why quote
    We haven't done a real 'government website sweep' in a bit - I'm thinking we should!!
    Package
    Federal Government Website Sweep 2026-07-25
  • Id
    K03-012
    When
    2026-08-08
    Her words
    I'm thinking we should plan another government wide sweep to see what took place this past week.
    Package
    Federal Government Weekly Delta 2026-08-08
    Note
    The weekly delta recorded the Groves criticality.
  • Id
    K07-072
    When
    2026-09-23 18:25 UTC
    Her words
    I think the government is building a quantum resistant financial rail (or outsourcing the building of the actual technology) based on the science & technology strategy documents and the GENESIS mission
    Files
    • Economic Institution Legitimacy Crisis 2025-2026/WAVE_3_SCIENCE_TECHNOLOGY_MISSION_TO_MACHINE_EVIDENCE_LEDGER_2026-09-24.md
Request source
Obsidian vault: 00 - Index/Operation Inch by Inch/Katie's Words 2026-11-13/ORIGINS_BY_PACKAGE.json

The dated steps

2025-05-23 Turning pointUnder EO 14301 §5(a), the President directed the Secretary of Energy to create a pilot outside national laboratories and approve at least three test reactors with a goal of criticality by July 4, 2026.

Under EO 14301 §5(a), the President directed the Secretary of Energy to create a pilot outside national laboratories and approve at least three test reactors with a goal of criticality by July 4, 2026.

Who acted: The President (Donald J. Trump)

Stage: signed

Under EO 14301 §5(a), the President directed the Secretary of Energy to create a pilot outside national laboratories and approve at least three test reactors with a goal of criticality by July 4, 2026.

FEDERAL_SCIENCE_OPERATING_SYSTEM_FACTUAL_SPINE_2025-2026.md

2025-06-18DOE opened applications for construction and operation of qualified test reactors outside the national laboratories.

DOE opened applications for construction and operation of qualified test reactors outside the national laboratories. The initial window ran through July 21, with later applications on a rolling basis.

Who acted: U.S. Department of Energy, Office of Nuclear Energy

Stage: request for information or comment

DOE opened applications for construction and operation of qualified test reactors outside the national laboratories. The initial window ran through July 21, with later applications on a rolling basis.

FEDERAL_SCIENCE_OPERATING_SYSTEM_FACTUAL_SPINE_2025-2026.md

2025-08-12 Turning pointDOE announced eleven initial projects across ten companies, including two Oklo projects, for work through its authorization process; the companies bear project costs.

DOE announced eleven initial projects across ten companies, including two Oklo projects, for work through its authorization process; the companies bear project costs. The announcement set July 4, 2026 as the criticality goal.

Who acted: U.S. Department of Energy

Stage: approved or adopted

DOE announced eleven initial projects across ten companies, including two Oklo projects, for work through its authorization process.

FEDERAL_SCIENCE_OPERATING_SYSTEM_FACTUAL_SPINE_2025-2026.md

2026-04-02The NRC proposed letting its reviews of reactor designs previously authorized by DOE or the Department of War reuse the tested safety evidence, mapped to NRC requirements and changed conditions.

The NRC proposed letting its reviews of reactor designs previously authorized by DOE or the Department of War reuse the tested safety evidence, mapped to NRC requirements and changed conditions. Comments were due May 4, 2026.

Who acted: U.S. Nuclear Regulatory Commission

Stage: proposed

Dated 2026-03-31; filed 2026-04-01 08:45; published 2026-04-02, 91 FR 16584–16588. Comments due 2026-05-04.

FEDERAL_SCIENCE_OPERATING_SYSTEM_FACTUAL_SPINE_2025-2026.md

2026-06-04 Turning pointDOE reported that Antares Nuclear’s Mark-0 completed a zero-power fueled criticality demonstration at Idaho National Laboratory.

DOE reported that Antares Nuclear’s Mark-0 completed a zero-power fueled criticality demonstration at Idaho National Laboratory.

Who acted: Antares Nuclear (operator; the files do not give the legal entity form); U.S. Department of Energy (authorizer and publisher)

Stage: first use

DOE reported that Antares Nuclear’s Mark-0 completed a zero-power fueled criticality demonstration at Idaho National Laboratory.

FEDERAL_SCIENCE_OPERATING_SYSTEM_FACTUAL_SPINE_2025-2026.md

2026-06-18DOE reported that Ward 250 completed its zero-power fueled criticality demonstration at the Utah San Rafael Energy Lab in Emery County.

DOE reported that Ward 250 completed its zero-power fueled criticality demonstration at the Utah San Rafael Energy Lab in Emery County. DOE described it as the first DOE-authorized reactor built outside a national laboratory.

Who acted: U.S. Department of Energy (the files do not name the Ward 250 operator)

Stage: in operation

DOE reported that Ward 250 completed its zero-power fueled criticality demonstration at the Utah San Rafael Energy Lab in Emery County. DOE described it as the first DOE-authorized reactor built outside a national laboratory.

FEDERAL_SCIENCE_OPERATING_SYSTEM_FACTUAL_SPINE_2025-2026.md

2026-06-30Deployable Energy’s Unity reached zero-power fueled criticality at Idaho National Laboratory.

Deployable Energy’s Unity reached zero-power fueled criticality at Idaho National Laboratory. DOE announced it July 1 and counted it as the third demonstration.

Who acted: Deployable Energy (operator); U.S. Department of Energy

Stage: in operation

Deployable Energy’s Unity reached zero-power fueled criticality at Idaho National Laboratory. DOE announced it July 1 and counted it as the third demonstration.

FEDERAL_SCIENCE_OPERATING_SYSTEM_FACTUAL_SPINE_2025-2026.md

2026-07-04Aalo-X completed a zero-power fueled criticality demonstration at Idaho National Laboratory.

Aalo-X completed a zero-power fueled criticality demonstration at Idaho National Laboratory. DOE announced it July 6 and counted it as the fourth DOE-authorized advanced reactor to reach criticality.

Who acted: Aalo Atomics (operator); U.S. Department of Energy

Stage: in operation

Where the files differ: Not a disagreement between files. DOE counts Mark-0, Unity and Aalo-X (Idaho National Laboratory) and Ward 250 (Utah) in its four-by-July-4 total; EO 14301 section 5(a) calls for a pilot outside the national laboratories.

Aalo-X completed a zero-power fueled criticality demonstration at Idaho National Laboratory. DOE announced it July 6 and counted it as the fourth DOE-authorized advanced reactor to reach criticality.

FEDERAL_SCIENCE_OPERATING_SYSTEM_FACTUAL_SPINE_2025-2026.md

2026-08-05The Groves Isotope Test Reactor reached criticality in Lockhart, Texas.

The Groves Isotope Test Reactor reached criticality in Lockhart, Texas. DOE reported the result the next day and identified it as the fifth DOE-authorized advanced reactor to reach criticality that summer.

Who acted: Oklo (operator; the files do not give the legal entity form); U.S. Department of Energy, Office of Nuclear Energy (authorizer and publisher)

Stage: in operation

The Groves Isotope Test Reactor reached criticality in Lockhart, Texas. DOE reported the result the next day and identified it as the fifth DOE-authorized advanced reactor to reach criticality that summer.

FEDERAL_SCIENCE_OPERATING_SYSTEM_FACTUAL_SPINE_2025-2026.md

2026-10-26 Turning pointThe NRC published a final rule adding to 10 CFR Parts 50 and 53 a route for applicants to use a prior Department of Energy or Department of War authorization to show specified safety functions.

The NRC published a final rule adding to 10 CFR Parts 50 and 53 a route for applicants to use a prior Department of Energy or Department of War authorization to show specified safety functions. The applicant must identify how the earlier authorization meets NRC requirements; a commercial licence still needs NRC review and decision. Effective November 25, 2026.

Who acted: U.S. Nuclear Regulatory Commission

Stage: published

The applicant must identify how the earlier authorization satisfies applicable NRC requirements.

FEDERAL_SCIENCE_OPERATING_SYSTEM_FACTUAL_SPINE_2025-2026.md

Where it stands

As of 15 November 2026: DOE has reported five advanced-reactor criticality demonstrations under its Reactor Pilot Program, the fourth on July 4, 2026 and the fifth (Oklo's Groves Isotope Test Reactor, Lockhart, Texas) on August 5, 2026. Three of the four counted by July 4 were at Idaho National Laboratory and one (Ward 250) at the Utah San Rafael Energy Lab. The NRC's final rule on designs previously authorized by DOE or the Department of War was published October 26, 2026 (91 FR 67195) and takes effect November 25, 2026. The notes record no commercial NRC application relying on a pilot authorization as of 15 November 2026.

What comes next

What the notes do not record

What it touches