Sets the policy of nuclear leadership, new reactor deployment, expanding capacity from about 100 GW in 2024 to 400 GW by 2050, faster design approval, fleet extensions and reactivations, and safety. No separate result assessment recorded
Sets the policy of nuclear leadership, new reactor deployment, expanding capacity from about 100 GW in 2024 to 400 GW by 2050, faster design approval, fleet extensions and reactivations, and safety.
Addressed to
- not stated (policy of the United States)
Order text
Facilitate the expansion of American nuclear energy capacity from approximately 100 GW in 2024 to 400 GW by 2050;
The NRC's mission is to include facilitating nuclear power while ensuring safety, and in licensing it is to weigh the economic and national-security benefits of nuclear power along with safety, health and environment. No separate result assessment recorded
The NRC's mission is to include facilitating nuclear power while ensuring safety, and in licensing it is to weigh the economic and national-security benefits of nuclear power along with safety, health and environment.
Addressed to
- the NRC (Nuclear Regulatory Commission)
Order text
When carrying out its licensing and related regulatory functions, the NRC shall consider the benefits of increased availability of, and innovation in, nuclear power to our economic and national security in addition to safety, health, and environmental considerations.
The NRC is to reorganize to speed license processing, undertake reductions in force (new reactor licensing may grow), and create a team of at least 20 officials to draft the Sec. 5 regulations. Not found in the notes
The NRC is to reorganize to speed license processing, undertake reductions in force (new reactor licensing may grow), and create a team of at least 20 officials to draft the Sec. 5 regulations.
Addressed to
- the NRC (in consultation with the NRC's DOGE Team)
What the notes record
- Searched
- stories
- thread-register
- research-files
- Pass
- 2
- Deadline passed
- False
Order text
The NRC shall undertake reductions in force in conjunction with this reorganization, though certain functions may increase in size consistent with the policies in this order, including those devoted to new reactor licensing.
ACRS personnel and functions are to be reduced to the statutory minimum and its review focused on truly novel or noteworthy issues. Found in part
ACRS personnel and functions are to be reduced to the statutory minimum and its review focused on truly novel or noteworthy issues.
Addressed to
- not stated (passive: ACRS personnel and functions 'shall be reduced')
What the notes record
- What it shows
- NRC's ACRS page (September 30, 2026) says ACRS is implementing the order (announced); no figures on any reduction are recorded
- Pass
- 2
- Evidence kind
- formal step toward the result
- Deadline passed
- False
read in the rendered browser and dated September 30, 2026, says it is implementing Executive Order 14300.NRC_COMMITTEE_MEETINGS_SCOPE_AND_RECORD_GAPS_2026-10-31.md
Order text
The personnel and functions of the Advisory Committee on Reactor Safeguards (ACRS) shall be reduced to the minimum necessary to fulfill ACRS's statutory obligations.
The NRC is to revise its regulations and guidance wholesale, with proposed rules within 9 months and final rules and guidance within 18 months. Found in part
The NRC is to revise its regulations and guidance wholesale, with proposed rules within 9 months and final rules and guidance within 18 months.
Addressed to
- the NRC (working with its DOGE Team, the Office of Management and Budget, and other executive departments and agencies)
Deadline
- Words
- proposed rules within 9 months (2026-02-23); final rules and guidance within 18 months (2026-11-23) of the date of this order
- Date
- 2026-02-23
What the notes record
- What it shows
- NRC proposed rule 'Regulatory Enhancements for Reactor Licensing, Decommissioning, and Operational Oversight' announced September 11 (release 26-077) and published September 24, 2026 (FR Doc. 2026-19568); proposed only. the order's 9-month proposed-rule date (2026-02-23) has passed; its 18-month final-rule date (2026-11-23) has not
- Pass
- 2
- Evidence kind
- formal step toward the result
- Date
- 2026-02-23
- Kind of date
- deadline on an officer or body
- Deadline passed
- True
The proposal is framed as EO 14300 implementation.WAVE_3D_INDEPENDENTS_SCIENCE_SAFETY_ECON.md
Order text
The NRC shall issue final rules and guidance to conclude this revision process within 18 months of the date of this order.
The NRC is to set fixed, fee-cap-enforced deadlines for licensing actions, at most 18 months for a new reactor and 1 year for continued operation, with shorter ones where appropriate. Found in part
The NRC is to set fixed, fee-cap-enforced deadlines for licensing actions, at most 18 months for a new reactor and 1 year for continued operation, with shorter ones where appropriate.
Addressed to
- the NRC (in the wholesale revision of its regulations)
Deadline
- Words
- proposed rules within 9 months; final rules and guidance within 18 months of the date of this order
- Date
- 2026-11-23
What the notes record
- What it shows
- NRC FY2026 final fee rule published June 16, 2026 sets fixed fee caps from October 1, 2026; decision deadlines are deferred, so the deadline part of Sec. 5(a) is not recorded
- Pass
- 2
- Evidence kind
- formal step toward the result
- Date
- 2026-11-23
- Kind of date
- deadline on an officer or body
- Deadline passed
- False
Final fee rule generally effective August 17; fixed caps begin October 1. Hourly billing remains.FEDERAL_SCIENCE_OPERATING_SYSTEM_FACTUAL_SPINE_2025-2026.md
Order text
(1) a deadline of no more than 18 months for final decision on an application to construct and operate a new reactor of any type, commencing with the first required step in the regulatory process, and (2) a deadline of no more than 1 year for final decision on an application to continue operating an existing reactor of any type,
The NRC is to reconsider the linear no-threshold model and ALARA standard and consider determinate radiation limits, consulting DOD, DOE and EPA. Not found in the notes
The NRC is to reconsider the linear no-threshold model and ALARA standard and consider determinate radiation limits, consulting DOD, DOE and EPA.
Addressed to
- the NRC (in the wholesale revision of its regulations)
Deadline
- Words
- proposed rules within 9 months; final rules and guidance within 18 months of the date of this order
- Date
- 2026-11-23
What the notes record
- Searched
- stories
- thread-register
- research-files
- Deadline note
- the order's 9-month proposed-rule date (2026-02-23) has passed; its 18-month final-rule date (2026-11-23) has not
- Pass
- 2
- Date
- 2026-11-23
- Kind of date
- deadline on an officer or body
- Deadline passed
- False
Order text
In particular, the NRC shall reconsider reliance on the linear no-threshold (LNT) model for radiation exposure and the ``as low as reasonably achievable'' standard, which is predicated on LNT.
The NRC is to revise its NEPA regulations, with CEQ, to reflect the 2023 NEPA amendments and EO 14154. Not found in the notes
The NRC is to revise its NEPA regulations, with CEQ, to reflect the 2023 NEPA amendments and EO 14154.
Addressed to
- the NRC (in the wholesale revision of its regulations)
Deadline
- Words
- proposed rules within 9 months; final rules and guidance within 18 months of the date of this order
- Date
- 2026-11-23
What the notes record
- Searched
- stories
- thread-register
- research-files
- Deadline note
- the order's 9-month proposed-rule date (2026-02-23) has passed; its 18-month final-rule date (2026-11-23) has not
- Pass
- 2
- Date
- 2026-11-23
- Kind of date
- deadline on an officer or body
- Deadline passed
- False
Order text
Revise, in consultation with the Council on Environmental Quality, NRC regulations governing NRC's compliance with the National Environmental Policy Act
The NRC is to establish an expedited pathway for designs DOD or DOE have tested, reviewing only new risks. Found
The NRC is to establish an expedited pathway for designs DOD or DOE have tested, reviewing only new risks.
Addressed to
- the NRC (in the wholesale revision of its regulations)
Deadline
- Words
- proposed rules within 9 months; final rules and guidance within 18 months of the date of this order
- Date
- 2026-11-23
What the notes record
- What it shows
- NRC final rule 'NRC Reviews of Reactor Designs Previously Authorized by U.S. Department of Energy or Department of War' published October 26, 2026, effective November 25, 2026
- Pass
- 2
- Date
- 2026-11-23
- Kind of date
- deadline on an officer or body
- Deadline passed
- False
This rulemaking addresses section 5(d), which contemplates an expedited pathway to approve reactor designs that the U.S. Department of Energy (DOE) or the Department of War (DOW) have tested and that have demonstrated the ability to function safely.2026-21801.txt
Order text
Establish an expedited pathway to approve reactor designs that the DOD or the DOE have tested and that have demonstrated the ability to function safely.
The NRC is to establish high-volume licensing for microreactors and modular reactors, considering general licenses. Found in part
The NRC is to establish high-volume licensing for microreactors and modular reactors, considering general licenses.
Addressed to
- the NRC (in the wholesale revision of its regulations)
Deadline
- Words
- proposed rules within 9 months; final rules and guidance within 18 months of the date of this order
- Date
- 2026-11-23
What the notes record
- What it shows
- proposed Part 57 microreactor licensing rule published May 1, 2026 (proposed only); the files do not tie Part 57 to the order in words
- Pass
- 2
- Evidence kind
- formal step toward the result
- Date
- 2026-11-23
- Kind of date
- deadline on an officer or body
- Deadline passed
- False
Proposed optional microreactor path for qualifying designs, with conditional construction permission and separate operating approval.FEDERAL_SCIENCE_OPERATING_SYSTEM_FACTUAL_SPINE_2025-2026.md
Order text
Establish a process for high-volume licensing of microreactors and modular reactors,
The NRC is to set stringent thresholds for demanding design changes once construction is underway. Not found in the notes
The NRC is to set stringent thresholds for demanding design changes once construction is underway.
Addressed to
- the NRC (in the wholesale revision of its regulations)
Deadline
- Words
- proposed rules within 9 months; final rules and guidance within 18 months of the date of this order
- Date
- 2026-11-23
What the notes record
- Searched
- stories
- thread-register
- research-files
- Deadline note
- the order's 9-month proposed-rule date (2026-02-23) has passed; its 18-month final-rule date (2026-11-23) has not
- Pass
- 2
- Date
- 2026-11-23
- Kind of date
- deadline on an officer or body
- Deadline passed
- False
Order text
Establish stringent thresholds for circumstances in which the NRC may demand changes to reactor design once construction is underway.
The NRC is to revise the Reactor Oversight Process and security rules to cut unnecessary burdens. Not found in the notes
The NRC is to revise the Reactor Oversight Process and security rules to cut unnecessary burdens.
Addressed to
- the NRC (in the wholesale revision of its regulations)
Deadline
- Words
- proposed rules within 9 months; final rules and guidance within 18 months of the date of this order
- Date
- 2026-11-23
What the notes record
- Searched
- stories
- thread-register
- research-files
- Deadline note
- the order's 9-month proposed-rule date (2026-02-23) has passed; its 18-month final-rule date (2026-11-23) has not
- Pass
- 2
- Date
- 2026-11-23
- Kind of date
- deadline on an officer or body
- Deadline passed
- False
Order text
Revise the Reactor Oversight Process and reactor security rules and requirements to reduce unnecessary burdens and be responsive to credible risks.
The NRC is to adopt revised, determinate, data-backed safety thresholds focused on credible risks. Not found in the notes
The NRC is to adopt revised, determinate, data-backed safety thresholds focused on credible risks.
Addressed to
- the NRC (in the wholesale revision of its regulations)
Deadline
- Words
- proposed rules within 9 months; final rules and guidance within 18 months of the date of this order
- Date
- 2026-11-23
What the notes record
- Searched
- stories
- thread-register
- research-files
- Deadline note
- the order's 9-month proposed-rule date (2026-02-23) has passed; its 18-month final-rule date (2026-11-23) has not
- Pass
- 2
- Date
- 2026-11-23
- Kind of date
- deadline on an officer or body
- Deadline passed
- False
Order text
Adopt revised and, where feasible, determinate and data-backed thresholds to ensure that reactor safety assessments focus on credible, realistic risks.
The NRC is to reconsider and, as appropriate, extend the effective period of renewed licenses. Not found in the notes
The NRC is to reconsider and, as appropriate, extend the effective period of renewed licenses.
Addressed to
- the NRC (in the wholesale revision of its regulations)
Deadline
- Words
- proposed rules within 9 months; final rules and guidance within 18 months of the date of this order
- Date
- 2026-11-23
What the notes record
- Searched
- stories
- thread-register
- research-files
- Deadline note
- the order's 9-month proposed-rule date (2026-02-23) has passed; its 18-month final-rule date (2026-11-23) has not
- Pass
- 2
- Date
- 2026-11-23
- Kind of date
- deadline on an officer or body
- Deadline passed
- False
Order text
Reconsider the regulations governing the time period for which a renewed license remains effective, and extend that period as appropriate based on available technological and safety data.
The NRC is to streamline the public hearings process. Found in part
The NRC is to streamline the public hearings process.
Addressed to
- the NRC (in the wholesale revision of its regulations)
Deadline
- Words
- proposed rules within 9 months; final rules and guidance within 18 months of the date of this order
- Date
- 2026-11-23
What the notes record
- What it shows
- NRC proposed rule 'Streamlining Contested Adjudications in Licensing Proceedings' published March 3, 2026 (proposed only), and a modernized mandatory-hearing framework scheduled for first use August 13, 2026
- Pass
- 2
- Evidence kind
- formal step toward the result
- Date
- 2026-11-23
- Kind of date
- deadline on an officer or body
- Deadline passed
- False
Proposed changes to merits submissions, discovery and contested proceedings.FEDERAL_SCIENCE_OPERATING_SYSTEM_FACTUAL_SPINE_2025-2026.md
Order text
Streamline the public hearings process.