NARA compute and infrastructure supplier map
Full saved reading
View cited sources (16)
These are the sources cited by this reading. Each source keeps its own date and scope.
- PICARD parent
- current AWS call
- current Azure EOP 46 call
- current GCP sandbox call
- Fearless ERA 2.0
- AccelGov NITTSS
- Skylight EOP 46 core
- Hitachi EOP 46
- USAspending API
- NARA AI use-case inventory
- NARA ERA 2.0 overview
- NARA cloud-to-cloud transfer FAQ
- NARA Information Services directive
- NARA 2025 AI Compliance Plan
- NARA FY 2027 Congressional Justification
- NARA OIG audit of ERA 2.0
Saved research reading. Its original dates and claim limits control; the export date does not refresh the evidence.
Saved source details
---
title: NARA Compute and Infrastructure Supplier Map 2026-08-23
status: current
cutoff: 2026-08-23
artifact_role: supplier-control-map
disposition: retained-research-desk-reference
---
NARA compute and infrastructure supplier map
November 18 dated return: later ERA implementation orders and exact continuity checks extend the August award picture. Historical end dates below do not establish a service shutdown, and the later orders do not prove a complete contractor/workload transfer.
Bottom line
NARA is not building its electronic-record and AI transition on one vertically
integrated vendor. It is assembling a brokered, multi-cloud, hybrid stack:
- Amazon Web Services (AWS) is the strongest disclosed candidate for the
dominant enterprise and ERA 2.0 compute plane. NARA's ERA 2.0 architecture
put development, pilot and planned production in AWS, and the current annual
PICARD call for AWS is the largest named cloud-platform order. The current
award is enterprise-wide, however, and does not publish the ERA 2.0 share.
- Microsoft Azure is directly identified as the cloud beneath the EOP 46
Presidential-record holding and is also named in NARA's A1 Museum and Azure
AI/ML work.
- Google Cloud Platform (GCP) supplies a current development sandbox;
NARA's AI inventory separately identifies Vertex AI in ArchiAI and EOP 42
work. Google Workspace, supplied through DH Technologies, is the route by
which Gemini is available to employees.
- Communications Training Analysis Corporation (CTAC) is the contractual
cloud broker. NARA generally obligates money to CTAC under the single-award
PICARD BPA rather than directly to Amazon, Microsoft or Google.
- Fearless Solutions is the disclosed ERA 2.0 managed-services and DevOps
carrier. AccelGov carries the broader NITTSS program-management,
quality-control and IT O&M layer.
- Skylight is a major application and processing integrator around EOP 46,
PERMA and ERA discovery. Hitachi Vantara, with support supplied through
ThunderCat, provides an identified storage/content layer inside the
Azure-based EOP 46 holding.
- The local and network side remains material: NARA is buying or renewing
NetApp storage, VMware virtualization, F5 load balancing, Infoblox network
services, switches, DCIM and network-monitoring tools through federal
resellers and integrators.
The material control point is therefore not simply “which cloud?” It is the
chain from NARA to its broker, hyperscaler, integrator, application and storage
suppliers—and whether those layers preserve exportable, auditable records as
the archive becomes more cloud- and AI-dependent.
Supplier topology
NARA / OCIO / Electronic Records Initiative
|
+-- cloud procurement rail: CTAC / PICARD BPA
| |
| +-- AWS IaaS and PaaS
| | +-- strongest disclosed compute substrate for ERA 2.0
| | +-- broader enterprise cloud workloads
| |
| +-- Microsoft Azure
| | +-- EOP 46 Presidential-record holding
| | +-- Azure AI and ML sandbox / A1 Museum AI route
| |
| +-- Google Cloud Platform
| +-- development sandbox
| +-- Vertex AI-linked archival experiments in NARA inventory
|
+-- archival and application operations
| +-- Fearless Solutions: ERA 2.0 managed services and DevOps
| +-- AccelGov: NITTSS enterprise program management and IT O&M
| +-- Skylight: EOP 46, PERMA, AI-search and ERA-discovery work
| +-- Hitachi Vantara / ThunderCat: EOP 46 storage-content components
| +-- Cortina Productions: A1 Museum renovation and experience layer
| +-- Forum One: Archives.gov redesign and migration
|
+-- enterprise software and user-facing AI
| +-- DH Technologies -> Google Workspace Enterprise -> Gemini access
| +-- Regan Technologies -> Microsoft enterprise subscriptions
| +-- Carahsoft -> Alfresco Enterprise for ERA 2.0
| +-- Regan Technologies -> RemedyForce
| +-- Advanced Computer Concepts -> ServiceNow
|
+-- transport, local storage and hybrid infrastructure
+-- Manhattan Telecommunications: EIS network and voice
+-- ThunderCat -> NetApp maintenance
+-- V3Gate -> switches and VMware
+-- Alvarez -> F5 and Infoblox refreshes
+-- GovSmart -> Sunbird DCIM
+-- Sterling Computers -> network-monitoring SaaSThis is a responsibility map, not proof that every product is installed,
accepted or serving every NARA workload. Reseller identity and underlying
technology provider are preserved separately.
The cloud procurement rail: CTAC and PICARD
NARA awarded CTAC the single-award **Platform and Infrastructure Cloud for
Archives and Records Depositories (PICARD)** blanket purchase agreement in
2021. Its published base-and-options value is $86 million, which is a
ceiling—not an obligation. The parent period of performance runs through
September 29, 2026.
The relevant cloud-platform calls located under PICARD total
$47,169,095.24 in obligations:
| Platform family | Located calls | Obligations | What the public award record proves |
|---|---|---|---|
| AWS IaaS/PaaS | 5 annual calls | $43,572,356.61 | AWS is by far the largest named PICARD platform family; the current $7,872,100 call ends September 29, 2026. |
| Azure for EOP 46 | 2 calls | $3,327,750.00 | Azure is the named EOP 46 cloud platform; the current $1.4 million call runs through December 8, 2026. |
| GCP sandbox | 4 calls | $174,535.83 | GCP sandbox capacity is a small but persistent experimentation rail; the current $60,000 call runs through July 26, 2027. |
| Azure AI/ML sandbox | 2 calls | $94,452.80 | A small Azure AI/ML development lane existed; the most recent located call expired August 20, 2026 and no successor was located by cutoff. |
This comparison is not a total-cloud-spend statement. It is the sum of the
named platform calls located under the PICARD award family. It excludes
application integrators, software licenses, network equipment and other
contracts outside the BPA.
What the contract structure means
1. Direct payee is not the compute owner. CTAC is usually the award
recipient; AWS, Microsoft and Google are the underlying service providers.
2. Multi-cloud is asymmetric. The disclosed AWS obligations dwarf the GCP
and Azure-AI sandbox calls. Azure is more consequential when the separate
EOP 46 production holding is included.
3. Broker continuity is a control dependency. The parent PICARD BPA and
current AWS call both end September 29, 2026. No public successor rail was
located by the August 23 cutoff.
4. Cloud portability is unproved. A second cloud provider, sandbox or
alternative instance does not itself establish portable applications,
portable data, tested exit procedures or equivalent operating capability.
Primary award objects: PICARD parent, current AWS call, current Azure EOP 46 call, and current GCP sandbox call.
Compute plane
AWS: dominant disclosed enterprise route
NARA's 2016 ERA 2.0 architecture briefing placed its development, pilot and
to-be-production environments in AWS and described a custom Java/open-source
application using cloud elastic compute and virtual workbenches. The current
annual PICARD AWS order supplies enterprise AWS IaaS and PaaS through September
29, 2026.
The combined evidence makes AWS the strongest disclosed candidate for ERA
2.0's primary compute substrate. It does not prove:
- how much of the current AWS order is assigned to ERA 2.0;
- the AWS regions or availability zones;
- instance, accelerator, chip or storage classes;
- the division between compute, storage, network and managed services; or
- that every ERA 2.0 environment remains architecturally identical to 2016.
Azure: Presidential records and a separate AI route
The Azure evidence is more workload-specific. Current awards identify Azure as
the cloud platform for EOP 46, the electronic Presidential records of the
46th administration. A Hitachi Vantara award describes operations and
maintenance for Hitachi components in the Azure-based Object Based Storage
holding that contains Tier 1 EOP 46 records. Skylight task orders surround that
holding with discovery, transfer, processing, security and performance work.
NARA's AI inventory also names Azure OpenAI in the A1 Museum project, while
PICARD carried a small Azure AI/ML sandbox through August 20, 2026. The Cortina
museum-renovation contract is much broader than AI, so its full value cannot be
treated as Azure or model spend.
Google: Workspace AI and experimental archival workloads
There are two distinct Google paths:
- Workspace/Gemini: DH Technologies supplies Google Workspace Enterprise.
NARA's inventory says Gemini is available in Workspace; the award does not
itemize Gemini's price or establish how extensively employees use it.
- GCP/Vertex AI: CTAC supplies the active GCP sandbox. NARA's inventory
names Vertex AI in ArchiAI and EOP 42 work and describes an AWS-versus-GCP
PII pilot. Inventory naming proves the declared development route, not
production acceptance or durable portability.
Archive, application and operations plane
| Supplier | Identified role | Published obligation / current horizon | Proof boundary |
|---|---|---|---|
| Fearless Solutions | ERA 2.0 managed services and DevOps | $21,031,027.25; through Sep. 28, 2026 | Does not disclose accepted capabilities, SLA performance or a successor award. |
| AccelGov | NITTSS program management, quality control and enterprise IT O&M | $40,761,448.17; through Aug. 27, 2027 | Enterprise support is not dedicated AI compute. |
| Skylight | EOP 46 core, transfer/processing, modernization; PERMA/AI-search and ERA discovery work | Multiple task orders; core vehicle through Mar. 31, 2030 | Task-order descriptions do not prove launch, accuracy or complete project scope. |
| Hitachi Vantara | O&M for Hitachi components in Azure-based EOP 46 object storage | $1,026,612.20; through Jan. 5, 2027 | Does not allocate the award among storage, software and services. |
| ThunderCat | Hitachi HCP/HCI support; separate NetApp maintenance | $171,000 EOP support through Jul. 31, 2027; $263,322.74 NetApp through Oct. 31, 2026 | ThunderCat is the award recipient/reseller, not the underlying manufacturer. |
| Cortina Productions | A1 Museum and Learning Center renovation | $5,978,807; ended Dec. 31, 2025 | NARA's inventory names Cortina/Azure OpenAI, but the full renovation value is not AI spend. |
| Forum One | Archives.gov redesign and migration | $686,122.38; through Nov. 30, 2026 | Website migration does not prove general AI search launch. |
Key award objects: Fearless ERA 2.0, AccelGov NITTSS, Skylight EOP 46 core, and Hitachi EOP 46.
Historical execution warning
NARA OIG's 2023 audit found that ERA 2.0 had been delayed and inadequately
planned, lacked a complete overall program plan, schedule and baseline, and had
incomplete documentation showing deliverable acceptance. The report described
programming and development as outsourced and reported $94.577 million in ERA
2.0 costs from FY 2015 through FY 2022.
That is a historical audit finding. It is evidence for why acceptance records,
baselines and contractor accountability matter; it is not proof that every
finding remained unresolved at the August 2026 cutoff.
Storage, transport and hybrid infrastructure
NARA's budget documents show why cloud transition is not simply a model or
search project. The agency has described on-premises storage as nearing
capacity, staged more than 80 million files and nearly 2,000 TB in interim
cloud storage for future ERA 2.0 ingest, and planned a second ERA 2.0 instance
in an alternative cloud service provider with copies across regions.
The FY 2027 request retains that alternative-provider plan but rebases the
published transfer targets sharply: the FY 2026 plan showed a 2026 target of
510 TB / 101 million files, while the FY 2027 plan shows 200 TB / 24 million
files for 2026. The public documents reviewed do not state whether that change
reflects scope, timing, measurement or another cause. It should be monitored as
a target-definition or execution question, not labeled a failure without the
supporting explanation.
The disclosed hybrid/local supply chain includes:
| Layer | Direct award recipient | Underlying technology / role | Current horizon |
|---|---|---|---|
| Network transport | Manhattan Telecommunications | NARA EIS network and voice | Jul. 15, 2027 |
| On-prem storage | ThunderCat | NetApp maintenance for NARANET/NISP | Oct. 31, 2026 |
| Virtualization | V3Gate | VMware renewal | Jul. 4, 2027 |
| Switching | V3Gate | Access/core-layer switches | Sep. 12, 2026 |
| Load balancing | Alvarez | F5 BIG-IP refresh | Aug. 30, 2026 |
| DNS/DHCP/IPAM | Alvarez | Infoblox refresh | Sep. 6, 2027 |
| Data-center management | GovSmart | Sunbird DCIM | Sep. 26, 2026 |
| Network monitoring | Sterling Computers | Unnamed monitoring SaaS | Aug. 30, 2027 |
These awards prove procurement and published scope. They do not expose rack
locations, owned-versus-colocation capacity, power providers, hyperscaler
facilities, network topology, installation acceptance or workload placement.
Near-term contract and return-object watch
| Date | Object | Why it matters | Exact return object |
|---|---|---|---|
| Aug. 30, 2026 | F5 refresh order ends | Very short refresh window at the hybrid edge | Acceptance record, extension or successor award |
| Sep. 7, 2026 | Skylight PERMA / NEEMO tasks end | Application discovery and processing lane may roll into a successor task | Modification, completion/acceptance record or successor task order |
| Sep. 12, 2026 | Switch refresh ends | Physical/network modernization checkpoint | Delivery and acceptance or modification |
| Sep. 26, 2026 | Sunbird DCIM renewal ends | Local data-center management continuity | Renewal or successor product/award |
| Sep. 28, 2026 | Fearless ERA 2.0 award ends | Primary disclosed ERA 2.0 DevOps/managed-services cliff | Successor award, bridge, insourcing record or accepted closeout |
| Sep. 29, 2026 | PICARD BPA and current AWS call end | Cloud-broker and largest named platform lane expire together | Successor vehicle/call, extension, migration or recompete outcome |
| Dec. 8, 2026 | Current Azure EOP 46 call ends | Presidential-record hosting continuity | Renewal/successor or accepted transfer to another rail |
| Dec. 14, 2026 | Google Workspace award ends | Gemini/Workspace enterprise route | Renewal, product change or separate AI license disclosure |
No successor should be inferred from continued service, a solicitation, an
option, or a new umbrella vehicle. The return object must identify the award or
accepted operating change.
Observatory joins
This supplier map overlaps earlier Observatory research but adds a missing
federal-customer layer:
1. The data-center and compute buildout: existing work maps land, power,
chips, facilities and sovereign-compute projects. NARA adds a demand-side
institution whose archival mission is pushing records into hyperscale and
hybrid storage without publicly exposing the underlying region, chip or
facility map.
2. The AI build-out: existing work tracks models, scientific compute and
federal AI policy. NARA shows the documentary infrastructure underneath AI:
search, ingest, metadata, preservation, logs and retention all depend on the
cloud and contractor chain.
3. Government control and evidence: NARA both depends on commercial
platforms and sets the government-wide records boundary for AI material.
Supplier contracts therefore become part of the evidence-control plane:
custody, export, logging, retention and audit access matter as much as model
performance.
4. Concentration and transition risk: “multi-cloud” does not remove
concentration. CTAC is a broker chokepoint; AWS is the largest named cloud
lane; and workload-specific integrators hold operational knowledge above
the hyperscalers.
What remains unresolved
The reviewed public record does not establish:
- physical data-center, colocation or hyperscaler region locations;
- power utilities or generation contracts serving NARA's cloud workloads;
- CPU, GPU, accelerator, server or storage-instance types;
- NARA's exact per-workload AWS/Azure/GCP cost allocation;
- the identity of the planned second ERA 2.0 cloud provider;
- tested recovery time, cross-cloud failover or accepted portability;
- complete subcontractor chains beneath every prime/reseller;
- whether the August 20 Azure AI/ML sandbox was renewed through another award;
- the successor to PICARD, its current AWS order or the Fearless ERA 2.0 task;
- or acceptance of the FY 2026–2027 ingest, storage and application milestones.
Safe material claim
> NARA's electronic-record and AI transition is being supplied through a
> layered hybrid stack: CTAC brokers AWS, Azure and GCP capacity; AWS is the
> largest named cloud lane and the historically disclosed ERA 2.0 platform;
> Azure carries EOP 46; Google supports Workspace/Gemini and GCP/Vertex
> experiments; and specialist integrators and storage/network vendors operate
> the archival applications above and beside those clouds. Several of the
> largest disclosed continuity objects reach contract cliffs in September
> 2026, while the successor cloud and ERA 2.0 operating rails remain unresolved
> in the public award record reviewed through August 23.
Source shelf and method
The supplier ledger preserves direct recipient, underlying platform, award ID,
period, value type, state, proof level and proof limit. Dollar figures are
obligations unless explicitly labeled as a ceiling. Award dates and values were
checked against the official USAspending API,
whose last-update endpoint reported August 23, 2026 at the research cutoff.
Primary non-award sources:
- NARA cloud-to-cloud transfer FAQ
- NARA Information Services directive
- NARA 2025 AI Compliance Plan