| The scorecard | Goal: test reactors critical by July 4, 2026 | - Value
- 3
- Note
- DOE's August 12, 2025 selection announcement.
| For this row’s sourcing, see the saved details, section context and linked research. |
|---|
| The scorecard | Reported critical by that date, in DOE's numbering | - Value
- 4
- Note
- This saved comparison profiles the third and fourth; it does not profile the first and second.
| For this row’s sourcing, see the saved details, section context and linked research. |
|---|
| The scorecard | Pilot criticality events the library names | - Value
- 3
- Note
- Deployable Energy's Unity, Aalo Atomics' Aalo-X, Oklo's Groves Isotope Test Reactor.
| For this row’s sourcing, see the saved details, section context and linked research. |
|---|
| Each reported criticality · In DOE's Reactor Pilot Program | Deployable Energy's Unity | - Sub
- Third reported criticality in DOE's pilot · June 30, 2026
- Badge
- Text
- Before the July 4 goal date
- Text
- Deployable Energy's Unity reached zero-power fueled criticality late Jun 30 and DOE released the result Jul 1.
- Criticality
- June 30, 2026 (late in the day)
- DOE announced it
- July 1, 2026
- Place in DOE's count
- third
- Kind
- zero-power fueled
- What it is not
- Criticality is a real test/operating milestone; it is not an NRC commercial operating license, grid delivery or sustained commercial generation.
- Source file
- Domestic Systems Wave 7 primary-object ledger (status: pending)
| |
|---|
| Each reported criticality · In DOE's Reactor Pilot Program | Aalo Atomics' Aalo-X | - Sub
- Fourth reported criticality in DOE's pilot · July 4, 2026
- Badge
- Text
- On the goal date
- Text
- Aalo Atomics' Aalo-X reached criticality Jul 4 and DOE released the result Jul 6.
- Criticality
- July 4, 2026
- DOE announced it
- July 6, 2026
- Place in DOE's count
- fourth
- Kind
- criticality
- What it is not
- Criticality is a real test/operating milestone; it is not an NRC commercial operating license, grid delivery or sustained commercial generation.
- Source file
- Domestic Systems Wave 7 primary-object ledger (status: pending)
| |
|---|
| Each reported criticality · In DOE's Reactor Pilot Program | Oklo's Groves Isotope Test Reactor | - Sub
- Fifth DOE-authorized advanced reactor to reach criticality that summer · August 5, 2026
- Badge
- Text
- After the goal date
- Text
- DOE's August 6 Groves release reports that Oklo's Groves Isotope Test Reactor reached criticality the previous night in Lockhart, Texas. August 5 is inferred from that relative wording; the exact physical time is unstated. DOE calls it the fifth DOE-authorized advanced reactor to reach criticality that summer. This is an attributed program milestone, not an independently reconstructed census. The release describes a future commercial isotope-producing variant still in development; continuous operation, commercial NRC approval, isotope production and delivery are separate findings.
- Criticality
- August 5, 2026 (inferred from DOE's 'previous night')
- DOE announced it
- August 6, 2026
- Allowed claim (August 8 weekly delta)
- the test reactor reached criticality and became the fifth DOE-authorized advanced reactor reported to do so during summer 2026.
| |
|---|
| Each reported criticality · Other DOE-reported criticality (not described as part of the pilot) | Westinghouse eVinci test article | - Sub
- DOE/NNSA test · September 3, 2026
- Badge
- Text
- Not described as part of the pilot
- Text
- criticality 2026-09-03 at 663 °C; peak 1,011 °C claimed as NCERC reactivity-measurement record. DOE-NE article 2026-09-16. Sep 3 is before exclusive start; the official DOE post is in-window.
- Criticality
- September 3, 2026
- DOE article
- September 16, 2026
- How the September 16 weekly delta files it
- admit_lower_rank / promotion_review as a test-article criticality, not a commercial reactor.
- Claim limit
- Test criticality ≠ NRC license ≠ deployed eVinci. Sep 3 physical event is out of exclusive start; treat the DOE publication as the in-window object.
| |
|---|
| The goal and its legal basis · The program | DOE Announces Initial Selections for New Reactor Pilot Program | - Sub
- U.S. Department of Energy · August 12, 2025
- Badge
- Text
- The goal
- Text
- DOE selected 11 advanced-reactor projects from companies including Oklo, Radiant, Terrestrial Energy, Aalo Atomics, Last Energy, and Valar Atomics to build privately financed test reactors under the EO 14301 authorization process. The stated goal is to have at least three reach criticality by July 4, 2026, with companies bearing all costs and DOE providing a fast-track 'concierge' pathway.
- Clocks (factual spine)
- Official announcement 2025-08-12; no time established. Criticality target 2026-07-04 is prospective in that source.
- What the source establishes (factual spine)
- Eleven projects across ten companies were initially selected; companies bear project costs. Selection and the July 4, 2026 criticality goal do not themselves establish authorization or achievement.
- Goal assessment in the master
- DOE reported the goal met: Unity achieved zero-power fueled criticality late June 30, 2026 as the third DOE-authorized demonstration; Aalo-X reached criticality July 4 as the fourth. This does not establish commercial licensing or grid generation. Answered in the existing Domestic Systems Wave 7 primary-object ledger; DOE releases July 1 and July 6, 2026 were rechecked October 23. Original August 12, 2025 selection record retained.