Section context and qualifications
Uncertainty
  • The map keeps operating, building, pilot, awarded and proposed sites apart; an incentive, permit or power allocation is not production.
  • The editorial review counted 22 under-construction or proposed sites from the old map's filter; the registry has 18 with these three statuses (plus 9 research or pilot sites, not shown). The registry count is used here.
  • Target dates in the scale text (for example 2027 openings) are the companies' own targets.
  • Project-state labels are saved registry classifications. For Chobani Rome, the linked April22,2025 announcement alone does not establish later construction; its saved stage and September4,2026 cutoff remain separate from that source proof.
SectionRecordSaved detailsSources and dates
Site by site · Under construction or commissioningRegeneron Rensselaer
Sub
Rensselaer · Capital Region
Badge
Text
Under construction or commissioning
Scale
350,000-square-foot fill/finish addition
What
Operating biologics campus; new fill/finish facility validating
Sector
biotech
Infrastructure
Hudson corridor, I-90 rail corridor
Ownership
Not recorded in the registry
What the record does not prove
Physical completion and validation do not equal approved commercial production.
Site by site · Under construction or commissioningRegeneron Tarrytown R&D expansion
Sub
Tarrytown · Hudson Valley
Badge
Text
Under construction or commissioning
Scale
Multi-phase expansion scheduled through 2027
What
Laboratory, preclinical manufacturing and process-development expansion
Sector
biotech
Infrastructure
power grid, Hudson corridor
Ownership
Not recorded in the registry
What the record does not prove
The operating R&D headquarters and unfinished expansion capacity are separate clocks.
Site by site · Under construction or commissioningSouth Brooklyn Marine Terminal
Sub
Brooklyn · New York City
Badge
Text
Under construction or commissioning
Scale
810 MW project; 2027 target operation
What
Empire Wind 1 staging, preassembly and O&M base
Sector
port logistics
Infrastructure
waterborne freight, power grid
Ownership
Not recorded in the registry
What the record does not prove
Port assembly/logistics, not turbine manufacturing.
Site by site · Under construction or commissioningMenlo Micro Ideal Fab
Sub
Ithaca · Southern Tier
Badge
Text
Under construction or commissioning
Scale
Company materials target the New York fab online in 2027
What
RF MEMS Ideal Switch fab startup and retrofit
Sector
semiconductors
Infrastructure
power grid
Ownership
Not recorded in the registry
What the record does not prove
The Ithaca site is real; commercial New York wafer output is not yet proven.
Site by site · Under construction or commissioningBattery-NY Prototyping Center
Sub
Johnson City / Binghamton · Southern Tier
Badge
Text
Under construction or commissioning
Scale
97,000 square feet; first sample cells expected around end-2026
What
Industry-scale cell development and prototyping center
Sector
energy storage
Infrastructure
power grid, I-90 rail corridor
Ownership
Not recorded in the registry
What the record does not prove
Not a commercial gigafactory; coalition award is not all assigned to this building.
Site by site · Under construction or commissioningMoog Niagara Falls
Sub
Niagara Falls · Western New York
Badge
Text
Under construction or commissioning
Scale
New propulsion cleanroom under construction at an existing production site
What
Operating propulsion site with satellite and missile cleanroom expansion
Sector
aerospace defense
Infrastructure
power grid, I-90 rail corridor
Ownership
Not recorded in the registry
What the record does not prove
Existing propulsion production is operating; expanded cleanroom output is not yet established.
Site by site · Awarded, not yet builtCorning semiconductor-glass expansion
Sub
Canton · North Country
Badge
Text
Awarded, not yet built
Scale
Up to $315M; up to $32M final CHIPS award
What
High-purity fused-silica and ULE glass expansion
Sector
semiconductors
Infrastructure
hydropower
Ownership
Not recorded in the registry
What the record does not prove
Awarded expansion is not yet verified production capacity.
Site by site · Awarded, not yet builtonsemi / Stony Brook SiC Research Center
Sub
Stony Brook · Long Island
Badge
Text
Awarded, not yet built
Scale
$20 million project with $8 million onsemi commitment
What
Public-private silicon-carbide research facility
Sector
semiconductors
Infrastructure
power grid
Ownership
Not recorded in the registry
What the record does not prove
The award and site are established; construction, opening and active tool use were not verified in this pass.
Site by site · Awarded, not yet builtNiagara Bottling / Adirondack Bottling Works
Sub
Tryon Technology Park / Perth · Fulton County
Badge
Text
Awarded, not yet built
Scale
Phase-one proposal: approximately 362,440 square feet, two bottling lines and 55 jobs
What
Proposed automated purified-water and bottle-manufacturing plant
Sector
food bioprocessing
Infrastructure
power grid, water, wastewater, road freight
Ownership
No public-company ticker identified.
What the record does not prove
A land transaction, incentives and preliminary site work are established; no completed plant, installed line or operating production was verified by the cutoff.
Site by site · Proposed or in permittingProject Double Reed
Sub
Town of Alabama / STAMP · Western New York
Badge
Text
Proposed or in permitting
Scale
2.2M square feet; $19.46B developer proposal
What
Proposed 500 MW data-center campus
Sector
compute
Infrastructure
power grid, brownfield site
Ownership
Not recorded in the registry
What the record does not prove
SEQRA/site-plan stage; no verified construction or energization.
Site by site · Proposed or in permittingAperam Recycling Titanium Solids Center of Excellence
Sub
Frankfort · Mohawk Valley
Badge
Text
Proposed or in permitting
Scale
Up to 50 planned jobs; company target to become operational January 1, 2027
What
Company-announced automated titanium-solids processing center
Sector
advanced materials
Infrastructure
power grid, Erie Canal corridor, I-90 rail corridor
Ownership
Aperam Recycling is a division of Aperam S.A.
What the record does not prove
This is a named company project with a stated locality and operating target; the reviewed source does not establish construction completion or operating output.
Site by site · Proposed or in permittingNCCS/NYDIG Massena expansion
Sub
Massena · North Country
Badge
Text
Proposed or in permitting
Scale
Large-load local review
What
Proposed roughly 635 MW expansion on former industrial land
Sector
compute
Infrastructure
power grid, brownfield site
Ownership
Not recorded in the registry
What the record does not prove
No verified construction; power source unresolved; Mohawk Council of Akwesasne opposes.