Which big New York factory and lab projects are still under construction or only proposed? — saved evidence, page 1

Saved evidence through 2026-09-04. This table projects the linked graphic data; it does not refresh the underlying research.

Return to the graphic · Complete saved JSON

Rows 1–20 of 32. Page 1 of 2.

Section context and qualifications
Uncertainty
  • The map keeps operating, building, pilot, awarded and proposed sites apart; an incentive, permit or power allocation is not production.
  • The editorial review counted 22 under-construction or proposed sites from the old map's filter; the registry has 18 with these three statuses (plus 9 research or pilot sites, not shown). The registry count is used here.
  • Target dates in the scale text (for example 2027 openings) are the companies' own targets.
  • Project-state labels are saved registry classifications. For Chobani Rome, the linked April22,2025 announcement alone does not establish later construction; its saved stage and September4,2026 cutoff remain separate from that source proof.
SectionRecordSaved detailsSources and dates
At a glanceUnder construction or commissioning
Value
12
Note
Physical build, installation, commissioning, or validation underway.
For this row’s sourcing, see the saved details, section context and linked research.
At a glanceAwarded, not yet built
Value
3
Note
Formal award, financing, or site-readiness commitment without verified construction/operation.
For this row’s sourcing, see the saved details, section context and linked research.
At a glanceProposed or in permitting
Value
3
Note
MOU, proposal, permit, review, or demand-conditioned plan.
For this row’s sourcing, see the saved details, section context and linked research.
At a glanceSites on the whole map
Value
156
Note
Registry evidence cutoff 2026-09-04 ET
For this row’s sourcing, see the saved details, section context and linked research.
By regionWestern New York
Value
4
Display
4
For this row’s sourcing, see the saved details, section context and linked research.
By regionSouthern Tier
Value
3
Display
3
For this row’s sourcing, see the saved details, section context and linked research.
By regionLong Island
Value
2
Display
2
For this row’s sourcing, see the saved details, section context and linked research.
By regionMohawk Valley
Value
2
Display
2
For this row’s sourcing, see the saved details, section context and linked research.
By regionNorth Country
Value
2
Display
2
For this row’s sourcing, see the saved details, section context and linked research.
By regionCapital Region
Value
1
Display
1
For this row’s sourcing, see the saved details, section context and linked research.
By regionCentral New York
Value
1
Display
1
For this row’s sourcing, see the saved details, section context and linked research.
By regionFulton County
Value
1
Display
1
For this row’s sourcing, see the saved details, section context and linked research.
By regionHudson Valley
Value
1
Display
1
For this row’s sourcing, see the saved details, section context and linked research.
By regionNew York City
Value
1
Display
1
For this row’s sourcing, see the saved details, section context and linked research.
Site by site · Under construction or commissioningMicron White Pine campus
Sub
Clay · Central New York
Badge
Text
Under construction or commissioning
Scale
Up to $100B / four-fab, 20+ year New York vision
What
First fab in vertical construction; production target 2030
Sector
semiconductors
Infrastructure
process water, wastewater, power grid, I-90 rail corridor
Ownership
Not recorded in the registry
What the record does not prove
Long-range program value is not current spend or operating output.
Site by site · Under construction or commissioningChobani Rome megafactory
Sub
Rome · Mohawk Valley
Badge
Text
Under construction or commissioning
Scale
$1.2B; 1.4M square feet
What
Large dairy-processing plant and utility build
Sector
food bioprocessing
Infrastructure
process water, wastewater, I-90 rail corridor
Ownership
Not recorded in the registry
What the record does not prove
No direct Erie Canal freight link documented.
Proof boundary
The linked April 22, 2025 investment announcement alone does not prove later construction. The project-state label is the saved September 4 registry classification.
Site by site · Under construction or commissioningEdwards Vacuum dry-pump plant
Sub
Town of Alabama / STAMP · Western New York
Badge
Text
Under construction or commissioning
Scale
$319M; up to $18M final CHIPS award
What
Plant and equipment installed; late-2026 opening/commissioning lane
Sector
semiconductors
Infrastructure
hydropower, power grid, I-90 rail corridor
Ownership
Not recorded in the registry
What the record does not prove
Sustained production and shipment not yet proven.
Site by site · Under construction or commissioningOrbic Electronics Manufacturing
Sub
Hauppauge · Long Island
Badge
Text
Under construction or commissioning
Scale
$110 million; 144,500 square feet; designed for up to five million devices annually
What
Connected-device electronics manufacturing hub under buildout
Sector
communications
Infrastructure
power grid
Ownership
Not recorded in the registry
What the record does not prove
The 2025 announcement projected early-2026 production, but no later opening or first-output receipt was found.
Site by site · Under construction or commissioningElectrovaya Jamestown
Sub
Jamestown · Western New York
Badge
Text
Under construction or commissioning
Scale
$50.8M EXIM loan; state commitments
What
Pack assembly operating; cell line in acceptance testing
Sector
energy storage
Infrastructure
power grid
Ownership
Not recorded in the registry
What the record does not prove
Domestic cell production expected late 2026/early 2027, not yet verified.
Site by site · Under construction or commissioningRaymond Energy Solutions Manufacturing Center
Sub
Kirkwood · Southern Tier
Badge
Text
Under construction or commissioning
Scale
$15.6 million project; up to 45 jobs
What
Lithium-ion solution assembly center for material-handling equipment
Sector
energy storage
Infrastructure
power grid
Ownership
Not recorded in the registry
What the record does not prove
The physical project is established; current utilization and sustained output remain unverified.