.html · 1 sections · 2816 characters
workbench: Research Packages/FORTRESS America and Military Installation Energy Independence 2026-09-30/FORTRESS_AMERICA_PROGRAM_TO_PROVED_RESILIENCE_INFOGRAPHIC.html
Canonical source SHA-256: b9227b8d5c542fed9c4910c2f46eeb08b41c11d4b3ef959d9e742b4de46c32c5
Served copy SHA-256: b9227b8d5c542fed9c4910c2f46eeb08b41c11d4b3ef959d9e742b4de46c32c5
Owner evidence cutoffs: {"fortress-america-installation-energy-independence": "2026-09-30T23:59:59-04:00"}
These are package-level cutoffs, not a claim that this source was rechecked on those dates. Use its own publication and capture dates.
Owners: fortress-america-installation-energy-independence
Section 1 of 1
What FORTRESS America promises—and what is not proved
Program → portfolio → operating proof
What FORTRESS America promises—and what is not proved
In plain English
What FORTRESS America promises—and what is not proved
Compare the program's five parts with the separate legal requirement for critical loads, then see which bases have plans, funded work, completed systems or tested results.
A five-pillar resilience program whose installation-power objective is real—but whose technical constitution and delivered portfolio still have to be proved.
Current evidence state: program established → implementation constitution not yet public → fleet-wide delivery unproven.
Five mutually dependent pillars
Energy independenceIndependent power for every major U.S. installation
Supply chain + industrial baseMaterials, components, production and skilled capacity
Strategic defense reserveMunitions, fuel, medicine and blood through disruption
Installation hardening + cyberProtection against intrusion, sabotage and drones
Space + spectrumAssured sensing, navigation and communications
Three statements that must not be collapsed
Object Covered boundary Evidence state
FORTRESS Every major U.S. installation; “independent power” undefined Program objective established
10 U.S.C. §2920 Each installation’s critical-mission load 99.9% minimum annual availability required by end FY2030
Next Great American Base One future model installation Completely off-grid design objective, not an operating site
Evidence ladder
Select a state to see the receipt required before a claim can move.
P0Direction
P1Scope
P2Money
P3Design
P4Built
P5Commissioned
P6Island test
P7Endurance
P8Recurring
Where the public record stops
Program direction FORTRESS AmericaSite list, definition and funding unresolved
Selection / negotiation Army SCISix conditional pairings Janus + NWS CranePairings and planned 2028 deployment EielsonNotice of intent; up to 5 MW critical load
Prototype lane Project PeleINL demonstration, not base service
Operational description MCAS YumaFull-load backup described SUBASE New LondonEssential functions McCoy + SigonellaGate / tenant-facility scope
Island test observed MCAS MiramarMission-critical islanding; endurance still separate
Decision rule: an independence claim is only as strong as its load boundary + duration + operating-test receipt.
Evidence cutoff: September 30, 2026 ET. This visual is a governed synthesis of the package record, not a site-readiness certification.