Finance-Close Deep Dives — CP2, Rio Grande Train 5, and Thacker Pass

.md · 2 sections · 13230 characters

Source, owner, and dates

workbench: Research Packages/US Inbound Investment and Industrial Capex Funding Map 2025-2026/FINANCE_CLOSE_DEEP_DIVES.md

Canonical source SHA-256: bafe4e5d9db0f72df6b71eab90e87dd91f2947cd37ebb44cf6d800d7683a2cef

Served copy SHA-256: bafe4e5d9db0f72df6b71eab90e87dd91f2947cd37ebb44cf6d800d7683a2cef

Owner evidence cutoffs: {"us-inbound-investment-industrial-capex": "2026-07-31", "ai-infrastructure-capital-stack-risk-transfer": "2026-08-10", "industrial-project-finance-digital-rails": "2026-07-31"}

These are package-level cutoffs, not a claim that this source was rechecked on those dates. Use its own publication and capture dates.

Owners: us-inbound-investment-industrial-capex, ai-infrastructure-capital-stack-risk-transfer, industrial-project-finance-digital-rails

Opening section

Section 1 of 2

# Finance-Close Deep Dives — CP2, Rio Grande Train 5, and Thacker Pass

## Why these three

These are deliberately not a representative sample of every announced project. They are three disclosure-rich cases that show the capital stack in action: ring-fenced project debt, sponsor/holding-company leverage, committed equity, public credit, offtake, actual advances and observed construction spend. They answer the bank-liquidity question with legal instruments rather than a macro intuition.

Do not add project cost, debt commitments, equity commitments, loan advances and construction spend; they are different clocks of the same project.

## 1. Venture Global CP2 LNG Phase 1 — Louisiana

Field Evidence
Borrower / structure Venture Global CP2 LNG, LLC is project borrower; CP2 Procurement, LLC and Venture Global CP Express, LLC are guarantors. CP2 LNG Holdings, LLC is the separate parent-level equity-bridge borrower. CP2 is an indirect wholly owned Venture Global subsidiary.
FID and financial close July 28, 2025; Phase 1 only. Disclosed closing total: $15.1B.
Project-level debt CP2: $11.25B senior-secured first-lien construction term facility plus $850M senior-secured first-lien working-capital revolver/letter-of-credit facility.
Holding-company layer CP2 Holdings: $2.809B secured equity bridge plus $191M three-year interest-reserve facility. The $2.809B bridge was fully drawn at closing to make indirect equity contributions to CP2's construction account; it is debt funding the equity layer, not proof of an external equity contribution.
Draw clock The construction-term facility allows drawings subject to conditions through the earlier of January 23, 2030 or Phase 1 completion. Its commitment is not evidence that the $11.25B was fully drawn. A pre-FID $3.0B bridge existed in May 2025; $1.1B outstanding was prepaid from equity-bridge proceeds in July.
Build clock Site work began June 2025 after FERC final approval/NTP. The 2025 10-K says Phase 1 construction was under way, with targeted COD late 2029. Reported $7.6B paid across CP2 Phases 1 and 2 at September 30, 2025 is not attributable Phase-1 spend.
Boundary Keep Phase 2 separate: its cost range and later financing do not establish Phase-1 draws. Long-term LNG contracts support expected project revenue; they are not an up-front customer cash contribution.

Sources: Venture Global July 2025 8-K; 2025 10-K; equity-bridge credit agreement.

## 2. NextDecade Rio Grande LNG Train 5 — Texas

Field Evidence
Borrower / structure Rio Grande LNG Train 5, LLC is the indirect NextDecade project borrower. Rio Grande LNG Train 5 Holdings, LLC is the pledgor. The equity JV is Train 5 JVCo, with NextDecade affiliate ND Member (Class A) and GIP V Velocity Aggregator T5 LP (Class B). Financial investors named: GIP/BlackRock, GIC and Mubadala.
FID / close / NTP October 16, 2025: FID, financial close and final Bechtel notice to proceed. Estimated total cost $6.66–6.7B, including $4.36B lump-sum EPC price.
Project stack $3.59B senior-secured term loan plus $500M senior-secured private-placement notes at Train 5 LLC; $1.29B NextDecade equity commitment plus $1.29B GIP/GIC/Mubadala equity commitments. That is about 61% debt / 39% committed equity, not bank balance-sheet funding of the entire project.
Sponsor stack NextDecade funded its $1.29B equity commitment with $233M cash, $729M delayed-draw FinCo bank facility, and $600M SuperFinCo term loan, disbursed at close and 13% PIK until one year after completion. Project equity and sponsor borrowing are distinct layers.
Draw clock At close, Train 5 paid NextDecade LLC $117M ($17M reimbursed pre-FID development and $100M management-services fee). The public record establishes facilities and commitments, not aggregate construction term-loan draws through March 31, 2026.
Build / revenue-support clocks Construction commenced October 2025; site preparation was under way March 2026; first commercial delivery targeted H1 2031. 4.5 MTPA of 20-year SPAs with JERA, EQT and ConocoPhillips provide commercial support, not construction capital.
Boundary Do not call the full $6.7B cash paid or treat SPAs as funded equity. Equity obligations are backstopped by qualified guarantee, bank LC or cash collateral.

Sources: NextDecade October 2025 8-K; closing release and sponsor financing; Q1 2026 10-Q.

## 3. Lithium Americas Thacker Pass Phase 1 — Nevada

Field Evidence
Owner / borrower Lithium Nevada Ventures LLC is the LAC–GM JV and owns 100% of Lithium Nevada LLC (LN), which owns Thacker Pass. Lithium Nevada LLC is the DOE ATVM borrower. LAC controls/manages the JV at 62%; GM holds 38%, subject to a DOE JV warrant.
Public-credit stack DOE ATVM loan closed October 28, 2024: original maximum $1.97B principal plus capitalized interest; amended October 2025 to expected $2.23B (principal unchanged, estimated $256M capitalized interest). Funds are restricted LN accounts under collateral agent Citibank.
Actual advances First-advance conditions were satisfied through the October 10, 2025 operating-work completion agreement. DOE advanced $435M on October 20, 2025 and $432M on February 24, 2026—$867M total. Further advances remain subject to usual conditions.
JV equity / support GM: $330M JV cash at December 2024 close; $100M at April 2025 FID; $195M LC for DOE reserves, posted then released August 2025. LAC: $138.3M at JV close and $191.6M at FID. GM offtake covers up to 100% of Phase 1.
Additional corporate capital At April 2025 Orion closing, LAC received $195M senior unsecured convertible notes and $25M production-payment cash; $30M delayed-draw notes remained contingent/not issued year-end. Public common-equity raises are corporate capital and cannot be allocated asset-by-asset without sources-and-uses evidence.
FID / build / spend Phase-1 FID April 1, 2025. As of March 31, 2026: cumulative capitalized construction/project cost $1.277B; $1.138B within the $2.93B Phase-1 construction-capex estimate; engineering more than 95% and procurement more than 70%; mechanical completion targeted late 2027.
Boundary "Fully funded for construction" is company language; draw conditions, completion guarantees and DOE liens remain material. DOE warrants are not construction cash; offtake is demand/revenue support, separate from loan/equity proceeds.

Sources: Lithium Americas 2025 10-K; Q1 2026 10-Q; 2024 10-K.

## Cross-case finding

The money is neither a one-for-one pool of bank liquidity nor a mystery residual. These cases show: project borrowers; secured and non-recourse facilities; sponsor/holding-company debt used to meet equity obligations; government credit; reserve/collateral conditions; and offtake that helps make debt service credible. Only Thacker Pass in this set has both publicly identified loan advances and a clear cumulative-spend figure.

There is no reviewed crypto, stablecoin, tokenized-loan or tokenized-bond instrument in these stacks.

## 4. BlueOval SK — Tennessee and Kentucky battery plants

Field Evidence
Original borrower / owners BlueOval SK LLC (BOSK), the Ford / SK On / SK Battery America JV, built one Tennessee and two Kentucky plants.
Facility and advances DOE/FFB multi-draw facility, maximum $9.63304B, under December 2024 loan agreement. Ford's May 2026 8-K reports $7.83554B in actual advances to BOSK.
Original sponsor support Ford guaranteed 50% of BOSK payment obligations and had an up-to-$6.6B capital-contribution obligation through 2026. BOSK had distributed $3.1B of loan proceeds back to Ford as returns of capital by June 2025; that is not evidence of plant spend.
Material 2026 change On May 20, 2026 Ford's BOSK interest was redeemed. Ford Energy Battery acquired the two Kentucky plants, subject to DOE liens, and assumed the $3.80504B DOE note associated with the Kentucky plant that had advances. Ford's up-to-$6.6B contribution obligation ended; SK Battery America controls BOSK and the Tennessee plant.
Build clock / boundary Kentucky Facility 1 had a certificate of occupancy and the Facility 2 building was constructed by May 2026. Production/operations and post-restructure draws need separate proof. This is a successor-borrower map, not a static "$9.6B BlueOval loan" row.

Sources: Ford May 2026 8-K; Ford June 2025 10-Q; DOE loan close.

## 5. TSMC Arizona — foreign parent, public support and unobserved draw

Field Evidence
Owner / borrower TSMC Arizona Corporation, wholly owned by Taiwan Semiconductor Manufacturing Company; Fab 21 is the manufacturing entity.
Public support November 2024 direct-funding agreement: up to $6.6B, subject to milestones/compliance. Connected loan agreements permit up to $5B in government-loan draws. Parent guarantee to Commerce is irrevocable, absolute and unconditional.
Parent / capital-markets layer TSMC Arizona board authorized a capital increase of up to $20B from the parent in May 2026—authorization, not proof paid in. TSMC Arizona issued $4.5B parent-guaranteed notes in 2021; do not allocate them to the later $65B/three-fab plan without use-of-proceeds evidence.
Build clock Fab 1 entered high-volume production end-2024; Fab 2 is under construction; Fab 3 began 2025; additional Arizona land acquired 2026.
Boundary Current public record proves foreign parent ownership/guarantee, award and loan availability, bond issuance and future equity authorization. It does not prove a total-project funding schedule, Commerce-loan draw or direct-funding disbursement.

Sources: TSMC 2025 20-F; May 2026 capital-increase resolution; Arizona notes prospectus.

6. Stargate I / Abilene — platform headline versus property borrower

Section 2 of 2

## 6. Stargate I / Abilene — platform headline versus property borrower

Field Evidence
Actual property borrower Abilene DC 1 LLC, formed May 2024 to own, develop, lease and operate two buildings/eight data halls plus power station. It is wholly owned by Longhorn JV LLC: BOREC Longhorn Member LLC 92.3%; Crusoe Abilene 7.7% at 2025 year-end.
Equity and debt disclosed Audited SPV statements show $926.847M total equity contributions at December 31, 2025. A December 16, 2024 construction loan permits up to $2.288B, interest-only, SOFR + 2.5% / alternate rate options, maturity 2028. Lender and text-extractable draw are not public. Loan proceeds are restricted for development costs.
Tenant / revenue support Campus is 100% leased to one hyperscale tenant; Blue Owl identifies Oracle America. Building-1 rent began March 18, 2025 and Building-2 rent July 1, 2025; tenant construction costs are reimbursable under the lease.
Build clock Buildings substantially completed/delivered by end-2025; power station remained under development. OpenAI said portions were running in July 2025.
Boundary Blue Owl's $15B Abilene "transaction" is a broader campus/program figure. It cannot replace the auditable DC1 SPV stack. The $500B Stargate platform names initial funders but does not prove they contributed equity or lent directly to DC1.

Sources: audited Abilene DC1 statements; Blue Owl 10-Q; Blue Owl $15B statement; Stargate launch.