title: "Finance-Close Deep Dives — CP2, Rio Grande Train 5, and Thacker Pass"
status: current
artifact_role: source-bearing financing and draw cards
evidence_cutoff: 2026-07-31
---

# Finance-Close Deep Dives — CP2, Rio Grande Train 5, and Thacker Pass

## Why these three

These are deliberately not a representative sample of every announced project. They are three disclosure-rich cases that show the capital stack in action: ring-fenced project debt, sponsor/holding-company leverage, committed equity, public credit, offtake, actual advances and observed construction spend. They answer the bank-liquidity question with legal instruments rather than a macro intuition.

Do not add project cost, debt commitments, equity commitments, loan advances and construction spend; they are different clocks of the same project.

## 1. Venture Global CP2 LNG Phase 1 — Louisiana

| Field | Evidence |
|---|---|
| Borrower / structure | **Venture Global CP2 LNG, LLC** is project borrower; CP2 Procurement, LLC and Venture Global CP Express, LLC are guarantors. **CP2 LNG Holdings, LLC** is the separate parent-level equity-bridge borrower. CP2 is an indirect wholly owned Venture Global subsidiary. |
| FID and financial close | July 28, 2025; Phase 1 only. Disclosed closing total: **$15.1B**. |
| Project-level debt | CP2: $11.25B senior-secured first-lien construction term facility plus $850M senior-secured first-lien working-capital revolver/letter-of-credit facility. |
| Holding-company layer | CP2 Holdings: $2.809B secured equity bridge plus $191M three-year interest-reserve facility. The $2.809B bridge was fully drawn at closing to make indirect equity contributions to CP2's construction account; it is **debt funding the equity layer**, not proof of an external equity contribution. |
| Draw clock | The construction-term facility allows drawings subject to conditions through the earlier of January 23, 2030 or Phase 1 completion. Its commitment is not evidence that the $11.25B was fully drawn. A pre-FID $3.0B bridge existed in May 2025; $1.1B outstanding was prepaid from equity-bridge proceeds in July. |
| Build clock | Site work began June 2025 after FERC final approval/NTP. The 2025 10-K says Phase 1 construction was under way, with targeted COD late 2029. Reported $7.6B paid across CP2 Phases 1 and 2 at September 30, 2025 is not attributable Phase-1 spend. |
| Boundary | Keep Phase 2 separate: its cost range and later financing do not establish Phase-1 draws. Long-term LNG contracts support expected project revenue; they are not an up-front customer cash contribution. |

Sources: [Venture Global July 2025 8-K](https://www.sec.gov/Archives/edgar/data/2007855/000200785525000036/vg-20250728.htm); [2025 10-K](https://www.sec.gov/Archives/edgar/data/2007855/000200785526000013/vg-20251231.htm); [equity-bridge credit agreement](https://www.sec.gov/Archives/edgar/data/2007855/000200785525000066/exhibit103-q32025.htm).

## 2. NextDecade Rio Grande LNG Train 5 — Texas

| Field | Evidence |
|---|---|
| Borrower / structure | **Rio Grande LNG Train 5, LLC** is the indirect NextDecade project borrower. Rio Grande LNG Train 5 Holdings, LLC is the pledgor. The equity JV is **Train 5 JVCo**, with NextDecade affiliate ND Member (Class A) and GIP V Velocity Aggregator T5 LP (Class B). Financial investors named: GIP/BlackRock, GIC and Mubadala. |
| FID / close / NTP | October 16, 2025: FID, financial close and final Bechtel notice to proceed. Estimated total cost **$6.66–6.7B**, including $4.36B lump-sum EPC price. |
| Project stack | $3.59B senior-secured term loan plus $500M senior-secured private-placement notes at Train 5 LLC; $1.29B NextDecade equity commitment plus $1.29B GIP/GIC/Mubadala equity commitments. That is about 61% debt / 39% committed equity, not bank balance-sheet funding of the entire project. |
| Sponsor stack | NextDecade funded its $1.29B equity commitment with $233M cash, $729M delayed-draw FinCo bank facility, and $600M SuperFinCo term loan, disbursed at close and 13% PIK until one year after completion. Project equity and sponsor borrowing are distinct layers. |
| Draw clock | At close, Train 5 paid NextDecade LLC $117M ($17M reimbursed pre-FID development and $100M management-services fee). The public record establishes facilities and commitments, not aggregate construction term-loan draws through March 31, 2026. |
| Build / revenue-support clocks | Construction commenced October 2025; site preparation was under way March 2026; first commercial delivery targeted H1 2031. 4.5 MTPA of 20-year SPAs with JERA, EQT and ConocoPhillips provide commercial support, not construction capital. |
| Boundary | Do not call the full $6.7B cash paid or treat SPAs as funded equity. Equity obligations are backstopped by qualified guarantee, bank LC or cash collateral. |

Sources: [NextDecade October 2025 8-K](https://www.sec.gov/Archives/edgar/data/1612720/000161272025000021/next-20251013.htm); [closing release and sponsor financing](https://www.sec.gov/Archives/edgar/data/1612720/000161272025000021/a20251016pressrelease.htm); [Q1 2026 10-Q](https://www.sec.gov/Archives/edgar/data/1612720/000161272026000026/next-20260331.htm).

## 3. Lithium Americas Thacker Pass Phase 1 — Nevada

| Field | Evidence |
|---|---|
| Owner / borrower | **Lithium Nevada Ventures LLC** is the LAC–GM JV and owns 100% of Lithium Nevada LLC (LN), which owns Thacker Pass. **Lithium Nevada LLC** is the DOE ATVM borrower. LAC controls/manages the JV at 62%; GM holds 38%, subject to a DOE JV warrant. |
| Public-credit stack | DOE ATVM loan closed October 28, 2024: original maximum $1.97B principal plus capitalized interest; amended October 2025 to expected $2.23B (principal unchanged, estimated $256M capitalized interest). Funds are restricted LN accounts under collateral agent Citibank. |
| Actual advances | First-advance conditions were satisfied through the October 10, 2025 operating-work completion agreement. DOE advanced **$435M on October 20, 2025** and **$432M on February 24, 2026**—$867M total. Further advances remain subject to usual conditions. |
| JV equity / support | GM: $330M JV cash at December 2024 close; $100M at April 2025 FID; $195M LC for DOE reserves, posted then released August 2025. LAC: $138.3M at JV close and $191.6M at FID. GM offtake covers up to 100% of Phase 1. |
| Additional corporate capital | At April 2025 Orion closing, LAC received $195M senior unsecured convertible notes and $25M production-payment cash; $30M delayed-draw notes remained contingent/not issued year-end. Public common-equity raises are corporate capital and cannot be allocated asset-by-asset without sources-and-uses evidence. |
| FID / build / spend | Phase-1 FID April 1, 2025. As of March 31, 2026: cumulative capitalized construction/project cost **$1.277B**; $1.138B within the $2.93B Phase-1 construction-capex estimate; engineering more than 95% and procurement more than 70%; mechanical completion targeted late 2027. |
| Boundary | "Fully funded for construction" is company language; draw conditions, completion guarantees and DOE liens remain material. DOE warrants are not construction cash; offtake is demand/revenue support, separate from loan/equity proceeds. |

Sources: [Lithium Americas 2025 10-K](https://www.sec.gov/Archives/edgar/data/1966983/000119312526115081/lac-20251231.htm); [Q1 2026 10-Q](https://www.sec.gov/Archives/edgar/data/1966983/000119312526222727/lac-20260331.htm); [2024 10-K](https://www.sec.gov/Archives/edgar/data/1966983/000095017025046424/lac-20241231.htm).

## Cross-case finding

The money is neither a one-for-one pool of bank liquidity nor a mystery residual. These cases show: project borrowers; secured and non-recourse facilities; sponsor/holding-company debt used to meet equity obligations; government credit; reserve/collateral conditions; and offtake that helps make debt service credible. Only Thacker Pass in this set has both publicly identified loan advances and a clear cumulative-spend figure.

There is no reviewed crypto, stablecoin, tokenized-loan or tokenized-bond instrument in these stacks.

## 4. BlueOval SK — Tennessee and Kentucky battery plants

| Field | Evidence |
|---|---|
| Original borrower / owners | **BlueOval SK LLC (BOSK)**, the Ford / SK On / SK Battery America JV, built one Tennessee and two Kentucky plants. |
| Facility and advances | DOE/FFB multi-draw facility, maximum **$9.63304B**, under December 2024 loan agreement. Ford's May 2026 8-K reports **$7.83554B in actual advances** to BOSK. |
| Original sponsor support | Ford guaranteed 50% of BOSK payment obligations and had an up-to-$6.6B capital-contribution obligation through 2026. BOSK had distributed $3.1B of loan proceeds back to Ford as returns of capital by June 2025; that is not evidence of plant spend. |
| Material 2026 change | On May 20, 2026 Ford's BOSK interest was redeemed. Ford Energy Battery acquired the two Kentucky plants, subject to DOE liens, and assumed the **$3.80504B** DOE note associated with the Kentucky plant that had advances. Ford's up-to-$6.6B contribution obligation ended; SK Battery America controls BOSK and the Tennessee plant. |
| Build clock / boundary | Kentucky Facility 1 had a certificate of occupancy and the Facility 2 building was constructed by May 2026. Production/operations and post-restructure draws need separate proof. This is a successor-borrower map, not a static "$9.6B BlueOval loan" row. |

Sources: [Ford May 2026 8-K](https://www.sec.gov/Archives/edgar/data/37996/000003799626000093/f-20260520.htm); [Ford June 2025 10-Q](https://www.sec.gov/Archives/edgar/data/37996/000003799625000147/f-20250630.htm); [DOE loan close](https://www.energy.gov/edf/articles/doe-announces-963-billion-loan-blueoval-sk-further-expand-us-manufacturing-electric).

## 5. TSMC Arizona — foreign parent, public support and unobserved draw

| Field | Evidence |
|---|---|
| Owner / borrower | **TSMC Arizona Corporation**, wholly owned by Taiwan Semiconductor Manufacturing Company; Fab 21 is the manufacturing entity. |
| Public support | November 2024 direct-funding agreement: up to **$6.6B**, subject to milestones/compliance. Connected loan agreements permit up to **$5B** in government-loan draws. Parent guarantee to Commerce is irrevocable, absolute and unconditional. |
| Parent / capital-markets layer | TSMC Arizona board authorized a capital increase of up to **$20B** from the parent in May 2026—authorization, not proof paid in. TSMC Arizona issued **$4.5B** parent-guaranteed notes in 2021; do not allocate them to the later $65B/three-fab plan without use-of-proceeds evidence. |
| Build clock | Fab 1 entered high-volume production end-2024; Fab 2 is under construction; Fab 3 began 2025; additional Arizona land acquired 2026. |
| Boundary | Current public record proves foreign parent ownership/guarantee, award and loan availability, bond issuance and future equity authorization. It does **not** prove a total-project funding schedule, Commerce-loan draw or direct-funding disbursement. |

Sources: [TSMC 2025 20-F](https://www.sec.gov/Archives/edgar/data/1046179/000162828026025362/tsm-20251231.htm); [May 2026 capital-increase resolution](https://www.sec.gov/Archives/edgar/data/1046179/000104617926000275/a20260512boardofdirectorsr.htm); [Arizona notes prospectus](https://www.sec.gov/Archives/edgar/data/1046179/000119312521303601/d133627d424b2.htm).

## 6. Stargate I / Abilene — platform headline versus property borrower

| Field | Evidence |
|---|---|
| Actual property borrower | **Abilene DC 1 LLC**, formed May 2024 to own, develop, lease and operate two buildings/eight data halls plus power station. It is wholly owned by Longhorn JV LLC: BOREC Longhorn Member LLC 92.3%; Crusoe Abilene 7.7% at 2025 year-end. |
| Equity and debt disclosed | Audited SPV statements show **$926.847M total equity contributions** at December 31, 2025. A December 16, 2024 construction loan permits up to **$2.288B**, interest-only, SOFR + 2.5% / alternate rate options, maturity 2028. Lender and text-extractable draw are not public. Loan proceeds are restricted for development costs. |
| Tenant / revenue support | Campus is 100% leased to one hyperscale tenant; Blue Owl identifies **Oracle America**. Building-1 rent began March 18, 2025 and Building-2 rent July 1, 2025; tenant construction costs are reimbursable under the lease. |
| Build clock | Buildings substantially completed/delivered by end-2025; power station remained under development. OpenAI said portions were running in July 2025. |
| Boundary | Blue Owl's $15B Abilene "transaction" is a broader campus/program figure. It cannot replace the auditable DC1 SPV stack. The $500B Stargate platform names initial funders but does not prove they contributed equity or lent directly to DC1. |

Sources: [audited Abilene DC1 statements](https://www.sec.gov/Archives/edgar/data/1944366/000194436626000020/exhibit993-2025abelinedc1l.htm); [Blue Owl 10-Q](https://www.sec.gov/Archives/edgar/data/1944366/000194436625000100/osnl-20250630.htm); [Blue Owl $15B statement](https://www.blueowl.com/insights/2025-midyear-outlook); [Stargate launch](https://openai.com/index/announcing-the-stargate-project/).