Implementation Transition Timeline

.md · 1 sections · 3666 characters

Source, owner, and dates

workbench: Research Packages/FORTRESS America and Military Installation Energy Independence 2026-09-30/IMPLEMENTATION_TRANSITION_TIMELINE.md

Canonical source SHA-256: 7146af0f38170b308c4a04f29e7a04bd08442239bfceb911743d169ded08d993

Served copy SHA-256: 7146af0f38170b308c4a04f29e7a04bd08442239bfceb911743d169ded08d993

Owner evidence cutoffs: {"fortress-america-installation-energy-independence": "2026-09-30T23:59:59-04:00"}

These are package-level cutoffs, not a claim that this source was rechecked on those dates. Use its own publication and capture dates.

Owners: fortress-america-installation-energy-independence

Implementation Transition Timeline

Section 1 of 1

# Implementation Transition Timeline

Status: current Cutoff: 2026-09-30 ET Rule: direction, finance, selection, award, construction, commissioning, test and sustained readiness are separate clocks

## Occurred

Date State Object Event Boundary
2016-12-15 operational_public_description MCAS Yuma utility-partner microgrid ribbon cutting; 100% current/projected base requirement backup capacity described no current exercise result reviewed
2021-01-01 statutory 10 U.S.C. §2920 FY2030 critical-mission availability requirement enacted requirement is not compliance
2021-03 operational_test MCAS Miramar microgrid completed after full-scale resilience exercise reported exercise proved mission-critical islanding; do not inflate to every load for 21 days
2024-09-24 under_construction Project Pele INL groundbreaking announced prototype, not installation service
2024-10 operational SUBASE New London ribbon cutting for islanded microgrid essential-function boundary
2025-05 notice_of_intent Eielson microreactor Oklo negotiation path announced final award and NRC licensing remain
2025-05-23 directed EO 14299 Army made executive agent; first domestic-installation reactor directed by Sep. 30, 2028 executive direction is not reactor operation
2026-01-15 activated DLA Sigonella tenant-facility solar/storage microgrid activation ceremony DLA facilities, not complete NAS load
2026-05-19 operational_scope_limited Fort McCoy Main Gate microgrid opened gate/nearby facilities, not full post
2026-06-15 solicited Army SCI energy seven-installation solicitation issued lease and delivery clocks remain
2026-08-27 selected Army Janus five vendor/site pairings announced authorization, build and operation remain
2026-09-09 deployment_announced NWS Crane MMR joint Navy/Army Janus commercial reactor planned no later than September 2028 agreement, authorization, build, criticality and accepted power remain
2026-09-18 conditional Army SCI energy six developer/site pairings announced executed lease and financing remain
2026-09-30 established FORTRESS America five-pillar program and major-installation independent-power objective announced scope, standard, money and delivery undefined

## Directed and future gates

Date/window Object Gate Proof required
by 2026-10-30 FORTRESS program office stand-up named lead/adviser, charter, organization and operative work
within months FORTRESS full operating capability published duties, staff, portfolio controls and first outputs; phrase comes from memorandum text in access hold
FY2027–FY2031 Janus milestone awards obligation by milestone, authorization, construction and delivery
by 2028-09-30 domestic reactor first directed reactor operation legal authorization, criticality and accepted electricity delivery
by end FY2030 §2920 critical-mission energy availability site-level standards, measurements and compliance evidence
by FY2035 major-installation net-zero note at least 10% objective installation-level annual energy and water/waste accounting

## Timeline ruling

The September 30 action starts a program-office and implementation clock. It does not reset older statutory clocks or upgrade conditional site projects. The first material FORTRESS delta will be a binding crosswalk among the new office, existing owners, covered installations, technical requirements and resources.