workbench: Research Packages/FORTRESS America and Military Installation Energy Independence 2026-09-30/IMPLEMENTATION_TRANSITION_TIMELINE.md
Canonical source SHA-256: 7146af0f38170b308c4a04f29e7a04bd08442239bfceb911743d169ded08d993
Served copy SHA-256: 7146af0f38170b308c4a04f29e7a04bd08442239bfceb911743d169ded08d993
Owner evidence cutoffs: {"fortress-america-installation-energy-independence": "2026-09-30T23:59:59-04:00"}
These are package-level cutoffs, not a claim that this source was rechecked on those dates. Use its own publication and capture dates.
Owners: fortress-america-installation-energy-independence
Section 1 of 1
# Implementation Transition Timeline
Status: current
Cutoff: 2026-09-30 ET
Rule: direction, finance, selection, award, construction, commissioning, test and sustained readiness are separate clocks
| Date | State | Object | Event | Boundary |
|---|---|---|---|---|
| 2016-12-15 | operational_public_description |
MCAS Yuma | utility-partner microgrid ribbon cutting; 100% current/projected base requirement backup capacity described | no current exercise result reviewed |
| 2021-01-01 | statutory |
10 U.S.C. §2920 | FY2030 critical-mission availability requirement enacted | requirement is not compliance |
| 2021-03 | operational_test |
MCAS Miramar | microgrid completed after full-scale resilience exercise | reported exercise proved mission-critical islanding; do not inflate to every load for 21 days |
| 2024-09-24 | under_construction |
Project Pele | INL groundbreaking announced | prototype, not installation service |
| 2024-10 | operational |
SUBASE New London | ribbon cutting for islanded microgrid | essential-function boundary |
| 2025-05 | notice_of_intent |
Eielson microreactor | Oklo negotiation path announced | final award and NRC licensing remain |
| 2025-05-23 | directed |
EO 14299 | Army made executive agent; first domestic-installation reactor directed by Sep. 30, 2028 | executive direction is not reactor operation |
| 2026-01-15 | activated |
DLA Sigonella | tenant-facility solar/storage microgrid activation ceremony | DLA facilities, not complete NAS load |
| 2026-05-19 | operational_scope_limited |
Fort McCoy Main Gate | microgrid opened | gate/nearby facilities, not full post |
| 2026-06-15 | solicited |
Army SCI energy | seven-installation solicitation issued | lease and delivery clocks remain |
| 2026-08-27 | selected |
Army Janus | five vendor/site pairings announced | authorization, build and operation remain |
| 2026-09-09 | deployment_announced |
NWS Crane MMR | joint Navy/Army Janus commercial reactor planned no later than September 2028 | agreement, authorization, build, criticality and accepted power remain |
| 2026-09-18 | conditional |
Army SCI energy | six developer/site pairings announced | executed lease and financing remain |
| 2026-09-30 | established |
FORTRESS America | five-pillar program and major-installation independent-power objective announced | scope, standard, money and delivery undefined |
| Date/window | Object | Gate | Proof required |
|---|---|---|---|
| by 2026-10-30 | FORTRESS | program office stand-up | named lead/adviser, charter, organization and operative work |
| within months | FORTRESS | full operating capability | published duties, staff, portfolio controls and first outputs; phrase comes from memorandum text in access hold |
| FY2027–FY2031 | Janus | milestone awards | obligation by milestone, authorization, construction and delivery |
| by 2028-09-30 | domestic reactor | first directed reactor operation | legal authorization, criticality and accepted electricity delivery |
| by end FY2030 | §2920 | critical-mission energy availability | site-level standards, measurements and compliance evidence |
| by FY2035 | major-installation net-zero note | at least 10% objective | installation-level annual energy and water/waste accounting |
The September 30 action starts a program-office and implementation clock. It does not reset older statutory clocks or upgrade conditional site projects. The first material FORTRESS delta will be a binding crosswalk among the new office, existing owners, covered installations, technical requirements and resources.