# Implementation Transition Timeline

**Status:** `current`
**Cutoff:** 2026-09-30 ET
**Rule:** direction, finance, selection, award, construction, commissioning, test and sustained readiness are separate clocks

## Occurred

| Date | State | Object | Event | Boundary |
|---|---|---|---|---|
| 2016-12-15 | `operational_public_description` | MCAS Yuma | utility-partner microgrid ribbon cutting; 100% current/projected base requirement backup capacity described | no current exercise result reviewed |
| 2021-01-01 | `statutory` | 10 U.S.C. §2920 | FY2030 critical-mission availability requirement enacted | requirement is not compliance |
| 2021-03 | `operational_test` | MCAS Miramar | microgrid completed after full-scale resilience exercise | reported exercise proved mission-critical islanding; do not inflate to every load for 21 days |
| 2024-09-24 | `under_construction` | Project Pele | INL groundbreaking announced | prototype, not installation service |
| 2024-10 | `operational` | SUBASE New London | ribbon cutting for islanded microgrid | essential-function boundary |
| 2025-05 | `notice_of_intent` | Eielson microreactor | Oklo negotiation path announced | final award and NRC licensing remain |
| 2025-05-23 | `directed` | EO 14299 | Army made executive agent; first domestic-installation reactor directed by Sep. 30, 2028 | executive direction is not reactor operation |
| 2026-01-15 | `activated` | DLA Sigonella | tenant-facility solar/storage microgrid activation ceremony | DLA facilities, not complete NAS load |
| 2026-05-19 | `operational_scope_limited` | Fort McCoy Main Gate | microgrid opened | gate/nearby facilities, not full post |
| 2026-06-15 | `solicited` | Army SCI energy | seven-installation solicitation issued | lease and delivery clocks remain |
| 2026-08-27 | `selected` | Army Janus | five vendor/site pairings announced | authorization, build and operation remain |
| 2026-09-09 | `deployment_announced` | NWS Crane MMR | joint Navy/Army Janus commercial reactor planned no later than September 2028 | agreement, authorization, build, criticality and accepted power remain |
| 2026-09-18 | `conditional` | Army SCI energy | six developer/site pairings announced | executed lease and financing remain |
| 2026-09-30 | `established` | FORTRESS America | five-pillar program and major-installation independent-power objective announced | scope, standard, money and delivery undefined |

## Directed and future gates

| Date/window | Object | Gate | Proof required |
|---|---|---|---|
| by 2026-10-30 | FORTRESS | program office stand-up | named lead/adviser, charter, organization and operative work |
| within months | FORTRESS | full operating capability | published duties, staff, portfolio controls and first outputs; phrase comes from memorandum text in access hold |
| FY2027–FY2031 | Janus | milestone awards | obligation by milestone, authorization, construction and delivery |
| by 2028-09-30 | domestic reactor | first directed reactor operation | legal authorization, criticality and accepted electricity delivery |
| by end FY2030 | §2920 | critical-mission energy availability | site-level standards, measurements and compliance evidence |
| by FY2035 | major-installation net-zero note | at least 10% objective | installation-level annual energy and water/waste accounting |

## Timeline ruling

The September 30 action starts a program-office and implementation clock. It does not reset older statutory clocks or upgrade conditional site projects. The first material FORTRESS delta will be a binding crosswalk among the new office, existing owners, covered installations, technical requirements and resources.