Skip to content
Browse the whole research Library · Start page for AI agents ·

Primary-Source Claim Ledger — Turbine Asset Management and Buildout

.md · 1 sections · 11130 characters

Source, owner, and dates

workbench: Research Packages/AI-Enabled Turbine Asset Management and US Power Buildout 2025-2026/PRIMARY_SOURCE_CLAIM_LEDGER.md

Canonical source SHA-256: 355da3fba386bf77b81f26af6fac7f26b4c91a1f873710c21303919a473f6fce

Served copy SHA-256: 355da3fba386bf77b81f26af6fac7f26b4c91a1f873710c21303919a473f6fce

Owner evidence cutoffs: {"ai-turbine-asset-management-power-buildout": "2026-08-09"}

These are package-level cutoffs, not a claim that this source was rechecked on those dates. Use its own publication and capture dates.

Owners: ai-turbine-asset-management-power-buildout

Opening section

Section 1 of 1

# Primary-Source Claim Ledger

This ledger holds the atomic factual spine. A source is primary for the state its author can establish: EIA for reported generator inventory, a regulator for an order, an owner for its project state, an OEM for its products and backlog, and a test organization for its own demonstration. Vendor benefits remain vendor-reported.

ID Atomic claim at cutoff Grade Direct primary source State / boundary
B-01 Developers planned 86 GW of U.S. utility-scale additions in 2026: 51% solar, 28% batteries, 14% wind and 6.3 GW gas. A EIA Plan from a preliminary inventory; not guaranteed completion.
B-02 Planned 2026 gas additions comprised 3.3 GW combined cycle and 2.8 GW combustion turbine. A EIA Planned operating-capacity clock, not order-book size.
B-03 GE Vernova reported 116 GW of gas equipment backlog plus slot reservations at Q2 2026 and targeted at least 125 GW by year-end. B GE Vernova Global mixed commercial state; backlog and reservation are not collapsed.
B-04 GE reported 130 HA units commissioned and another 195 under contract in July 2026. B GE Vernova Frame-family global installed and contract counts.
B-05 Siemens reported 12 GW booked in Q2 FY2026 and 87 GW total gas commitments, including 24 GW data-center related. B Siemens Energy analyst presentation Global commitments; not all U.S. and not all operating.
B-06 MHI booked 35 large-frame gas turbines in FY2025 and reported GTCC backlog above ¥5 trillion. B MHI FY2025 presentation Global unit/order measure; country allocation incomplete.
B-07 NRG placed 415 MW of new T.H. Wharton capacity into commercial operation on May 26, 2026. A/B NRG Q2 2026 results Owner's explicit COD record.
B-08 NRG's Cedar Bayou 5 and Greens Bayou 6 projects remained in construction, with mid-2028 targets. B NRG Q2 2026 results Construction and target clocks only.
B-09 Plant Yates is building three M501JAC simple-cycle units totaling 1.3 GW; Units 8 and 9 had received major equipment by December 2025. A/B Georgia Power Owner project record; all units targeted by end-2027.
B-10 Duke had begun site work at Cayuga; its two new units are targeted for 2029 and 2030. A/B Duke Energy Construction, not operation.
B-11 Project Kilby has a 20-year PPA to serve a Microsoft data center. B Kilby project owner Offtake/development state; not FID or completed capacity.
B-12 Berkeley Lab counted 253 GW of gas in active interconnection queues at year-end 2025, but only 18% had a draft or executed IA. A DOE/LBNL Queue capacity is a developer-activity signal, not buildable or operating capacity.
B-13 Historically, 13% of capacity entering queues in 2000–2020 was operating by end-2025; median request-to-operation exceeded five years. A DOE/LBNL Historical conversion constraint, not a deterministic project forecast.
B-14 Pin Oak Creek Energy Center reached commercial operation on April 30, 2026. A/B Constellation Q1 2026 results Owner's explicit COD record.
B-15 Homer City's seven GE 7HA.02 turbines were converted to firm order, while Pennsylvania DEP records later permitting/site activity. A/B GE Vernova, Pennsylvania DEP Firm order and site activity; not operating capacity.
T-01 GE says its generation M&D service monitors 1,000+ plants and processes tens of billions of data points per day. C GE Vernova APM Vendor-reported scale; proves commercial offering, not independent benefits.
T-02 Siemens says 800+ power units use its monitoring/optimization expertise and 260+ plants use performance monitoring. C Siemens Energy Vendor-reported service scale.
T-03 MHI reported 144 TOMONI-connected thermal units by August 2023, operating anomaly detection and specialist review. R/C MHI Technical Review Named internal system record; specialists remained in the judgment loop.
T-04 EPRI describes fault-inference digital twins as implemented at several gas and nuclear plants, with typical implementation of six to twelve months. R EPRI Plant Modernization Toolbox Broad-use readiness with recorded model and sensor failure modes; not a universal twin.
T-05 GE Autonomous Tuning changes LM2500/LM6000 combustion targets every two seconds within existing safety-critical control logic. C GE product page, launch record Real bounded closed loop; not authority over trips, life extension or return to service.
T-06 MHI identifies autonomous combustion-dynamics and cooling-air optimization at T-Point 2. R/C Mitsubishi Power TOMONI Selected process functions, not general autonomous plant operation.
T-07 Siemens and Volkswagen completed a certified 72-hour unattended gas-and-steam plant test in October 2025. R Siemens Energy reference Plant-specific hazard analysis and retained protection; exceptional reference case.
T-08 GE reports an ANYmal robot collecting inspection data from 15+ assets at a named Irish thermal plant and feeding APM. C GE Vernova case study Named commercial deployment; outcome remains vendor-reported.
T-09 GE says more than 9,000 wind blades had received Digital Blade Certificates after robotic and AI-assisted inspection by April 2026. C GE Vernova review Manufacturing QA scale; humans review flagged areas.
T-10 IBM launched Condition Insight in December 2025 and Maximo 9.2 agentic workflows in June 2026. C IBM Condition Insight, IBM Maximo 9.2 Product availability, not proof of owner adoption or safety authority.
T-11 DOE CESER released Stormbreaker in July 2026 to test LLM and agent failure modes in dynamic power and OT environments. R DOE CESER Evaluation need is evidence against assuming generic-agent readiness.
W-01 Vestas reports more than 128 GW and 55,000 turbines on its Scipher platform. C Vestas Scipher Vendor-reported platform scale; multi-function fleet software is commercial.
W-02 RWE says TPA Next Evolution has been implemented across its full OPEA wind fleet and assists analysts across multiple condition-data modules. C RWE digital energy production Operator-reported deployment; assists rather than replaces analysts.
W-03 An autonomous drone inspection of an operating, rotating offshore turbine was demonstrated at Rødsand 2 in January 2026. R RWE AQUADA-GO Completed demonstration; not broad fleet deployment.
W-04 NREL's wtDigiTwin estimates turbine loads, motion and environment from SCADA plus a turbine model. R NREL wtDigiTwin Purpose-specific research software, not a universal lifecycle twin.
W-05 DOE/NREL's 2024 offshore O&M roadmap places fully autonomous inspection/intervention in its long-term 2032–2036 horizon. R DOE/NREL roadmap R&D roadmap, not deterministic market forecast.

## Claims not supported by this record