.md · 1 sections · 11130 characters
workbench: Research Packages/AI-Enabled Turbine Asset Management and US Power Buildout 2025-2026/PRIMARY_SOURCE_CLAIM_LEDGER.md
Canonical source SHA-256: 355da3fba386bf77b81f26af6fac7f26b4c91a1f873710c21303919a473f6fce
Served copy SHA-256: 355da3fba386bf77b81f26af6fac7f26b4c91a1f873710c21303919a473f6fce
Owner evidence cutoffs: {"ai-turbine-asset-management-power-buildout": "2026-08-09"}
These are package-level cutoffs, not a claim that this source was rechecked on those dates. Use its own publication and capture dates.
Owners: ai-turbine-asset-management-power-buildout
Section 1 of 1
This ledger holds the atomic factual spine. A source is primary for the state its author can establish: EIA for reported generator inventory, a regulator for an order, an owner for its project state, an OEM for its products and backlog, and a test organization for its own demonstration. Vendor benefits remain vendor-reported.
| ID | Atomic claim at cutoff | Grade | Direct primary source | State / boundary |
|---|---|---|---|---|
B-01 |
Developers planned 86 GW of U.S. utility-scale additions in 2026: 51% solar, 28% batteries, 14% wind and 6.3 GW gas. | A | EIA | Plan from a preliminary inventory; not guaranteed completion. |
B-02 |
Planned 2026 gas additions comprised 3.3 GW combined cycle and 2.8 GW combustion turbine. | A | EIA | Planned operating-capacity clock, not order-book size. |
B-03 |
GE Vernova reported 116 GW of gas equipment backlog plus slot reservations at Q2 2026 and targeted at least 125 GW by year-end. | B | GE Vernova | Global mixed commercial state; backlog and reservation are not collapsed. |
B-04 |
GE reported 130 HA units commissioned and another 195 under contract in July 2026. | B | GE Vernova | Frame-family global installed and contract counts. |
B-05 |
Siemens reported 12 GW booked in Q2 FY2026 and 87 GW total gas commitments, including 24 GW data-center related. | B | Siemens Energy analyst presentation | Global commitments; not all U.S. and not all operating. |
B-06 |
MHI booked 35 large-frame gas turbines in FY2025 and reported GTCC backlog above ¥5 trillion. | B | MHI FY2025 presentation | Global unit/order measure; country allocation incomplete. |
B-07 |
NRG placed 415 MW of new T.H. Wharton capacity into commercial operation on May 26, 2026. | A/B | NRG Q2 2026 results | Owner's explicit COD record. |
B-08 |
NRG's Cedar Bayou 5 and Greens Bayou 6 projects remained in construction, with mid-2028 targets. | B | NRG Q2 2026 results | Construction and target clocks only. |
B-09 |
Plant Yates is building three M501JAC simple-cycle units totaling 1.3 GW; Units 8 and 9 had received major equipment by December 2025. | A/B | Georgia Power | Owner project record; all units targeted by end-2027. |
B-10 |
Duke had begun site work at Cayuga; its two new units are targeted for 2029 and 2030. | A/B | Duke Energy | Construction, not operation. |
B-11 |
Project Kilby has a 20-year PPA to serve a Microsoft data center. | B | Kilby project owner | Offtake/development state; not FID or completed capacity. |
B-12 |
Berkeley Lab counted 253 GW of gas in active interconnection queues at year-end 2025, but only 18% had a draft or executed IA. | A | DOE/LBNL | Queue capacity is a developer-activity signal, not buildable or operating capacity. |
B-13 |
Historically, 13% of capacity entering queues in 2000–2020 was operating by end-2025; median request-to-operation exceeded five years. | A | DOE/LBNL | Historical conversion constraint, not a deterministic project forecast. |
B-14 |
Pin Oak Creek Energy Center reached commercial operation on April 30, 2026. | A/B | Constellation Q1 2026 results | Owner's explicit COD record. |
B-15 |
Homer City's seven GE 7HA.02 turbines were converted to firm order, while Pennsylvania DEP records later permitting/site activity. | A/B | GE Vernova, Pennsylvania DEP | Firm order and site activity; not operating capacity. |
T-01 |
GE says its generation M&D service monitors 1,000+ plants and processes tens of billions of data points per day. | C | GE Vernova APM | Vendor-reported scale; proves commercial offering, not independent benefits. |
T-02 |
Siemens says 800+ power units use its monitoring/optimization expertise and 260+ plants use performance monitoring. | C | Siemens Energy | Vendor-reported service scale. |
T-03 |
MHI reported 144 TOMONI-connected thermal units by August 2023, operating anomaly detection and specialist review. | R/C | MHI Technical Review | Named internal system record; specialists remained in the judgment loop. |
T-04 |
EPRI describes fault-inference digital twins as implemented at several gas and nuclear plants, with typical implementation of six to twelve months. | R | EPRI Plant Modernization Toolbox | Broad-use readiness with recorded model and sensor failure modes; not a universal twin. |
T-05 |
GE Autonomous Tuning changes LM2500/LM6000 combustion targets every two seconds within existing safety-critical control logic. | C | GE product page, launch record | Real bounded closed loop; not authority over trips, life extension or return to service. |
T-06 |
MHI identifies autonomous combustion-dynamics and cooling-air optimization at T-Point 2. | R/C | Mitsubishi Power TOMONI | Selected process functions, not general autonomous plant operation. |
T-07 |
Siemens and Volkswagen completed a certified 72-hour unattended gas-and-steam plant test in October 2025. | R | Siemens Energy reference | Plant-specific hazard analysis and retained protection; exceptional reference case. |
T-08 |
GE reports an ANYmal robot collecting inspection data from 15+ assets at a named Irish thermal plant and feeding APM. | C | GE Vernova case study | Named commercial deployment; outcome remains vendor-reported. |
T-09 |
GE says more than 9,000 wind blades had received Digital Blade Certificates after robotic and AI-assisted inspection by April 2026. | C | GE Vernova review | Manufacturing QA scale; humans review flagged areas. |
T-10 |
IBM launched Condition Insight in December 2025 and Maximo 9.2 agentic workflows in June 2026. | C | IBM Condition Insight, IBM Maximo 9.2 | Product availability, not proof of owner adoption or safety authority. |
T-11 |
DOE CESER released Stormbreaker in July 2026 to test LLM and agent failure modes in dynamic power and OT environments. | R | DOE CESER | Evaluation need is evidence against assuming generic-agent readiness. |
W-01 |
Vestas reports more than 128 GW and 55,000 turbines on its Scipher platform. | C | Vestas Scipher | Vendor-reported platform scale; multi-function fleet software is commercial. |
W-02 |
RWE says TPA Next Evolution has been implemented across its full OPEA wind fleet and assists analysts across multiple condition-data modules. | C | RWE digital energy production | Operator-reported deployment; assists rather than replaces analysts. |
W-03 |
An autonomous drone inspection of an operating, rotating offshore turbine was demonstrated at Rødsand 2 in January 2026. | R | RWE AQUADA-GO | Completed demonstration; not broad fleet deployment. |
W-04 |
NREL's wtDigiTwin estimates turbine loads, motion and environment from SCADA plus a turbine model. | R | NREL wtDigiTwin | Purpose-specific research software, not a universal lifecycle twin. |
W-05 |
DOE/NREL's 2024 offshore O&M roadmap places fully autonomous inspection/intervention in its long-term 2032–2036 horizon. | R | DOE/NREL roadmap | R&D roadmap, not deterministic market forecast. |
## Claims not supported by this record