--- title: "Primary-Source Claim Ledger — Turbine Asset Management and Buildout" status: current Workbench control artifact_role: atomic claim ledger evidence_cutoff: 2026-08-09 ET --- # Primary-Source Claim Ledger This ledger holds the atomic factual spine. A source is primary for the state its author can establish: EIA for reported generator inventory, a regulator for an order, an owner for its project state, an OEM for its products and backlog, and a test organization for its own demonstration. Vendor benefits remain vendor-reported. | ID | Atomic claim at cutoff | Grade | Direct primary source | State / boundary | |---|---|---:|---|---| | `B-01` | Developers planned 86 GW of U.S. utility-scale additions in 2026: 51% solar, 28% batteries, 14% wind and 6.3 GW gas. | A | [EIA](https://www.eia.gov/todayinEnergy/detail.php?id=67205) | Plan from a preliminary inventory; not guaranteed completion. | | `B-02` | Planned 2026 gas additions comprised 3.3 GW combined cycle and 2.8 GW combustion turbine. | A | [EIA](https://www.eia.gov/todayinEnergy/detail.php?id=67205) | Planned operating-capacity clock, not order-book size. | | `B-03` | GE Vernova reported 116 GW of gas equipment backlog plus slot reservations at Q2 2026 and targeted at least 125 GW by year-end. | B | [GE Vernova](https://www.gevernova.com/news/articles/ge-vernova-releases-second-quarter-2026-financial-results) | Global mixed commercial state; backlog and reservation are not collapsed. | | `B-04` | GE reported 130 HA units commissioned and another 195 under contract in July 2026. | B | [GE Vernova](https://www.gevernova.com/news/articles/ge-vernova-releases-second-quarter-2026-financial-results) | Frame-family global installed and contract counts. | | `B-05` | Siemens reported 12 GW booked in Q2 FY2026 and 87 GW total gas commitments, including 24 GW data-center related. | B | [Siemens Energy analyst presentation](https://assets.siemens-energy.com/dam/41a65182-38a3-48d9-a4ee-b4480041e3f9/2026-05-12_Q2_Analyst_presentation_final-pdf_Original%20file.pdf) | Global commitments; not all U.S. and not all operating. | | `B-06` | MHI booked 35 large-frame gas turbines in FY2025 and reported GTCC backlog above ¥5 trillion. | B | [MHI FY2025 presentation](https://www.mhi.com/finance/library/result/pdf/fy20254q/presentation.pdf) | Global unit/order measure; country allocation incomplete. | | `B-07` | NRG placed 415 MW of new T.H. Wharton capacity into commercial operation on May 26, 2026. | A/B | [NRG Q2 2026 results](https://investors.nrg.com/news-releases/news-release-details/nrg-energy-reports-second-quarter-2026-results-and-reaffirms) | Owner's explicit COD record. | | `B-08` | NRG's Cedar Bayou 5 and Greens Bayou 6 projects remained in construction, with mid-2028 targets. | B | [NRG Q2 2026 results](https://investors.nrg.com/news-releases/news-release-details/nrg-energy-reports-second-quarter-2026-results-and-reaffirms) | Construction and target clocks only. | | `B-09` | Plant Yates is building three M501JAC simple-cycle units totaling 1.3 GW; Units 8 and 9 had received major equipment by December 2025. | A/B | [Georgia Power](https://www.georgiapower.com/news-hub/press-releases/turbine-generator-unit-9-plant-yates.html) | Owner project record; all units targeted by end-2027. | | `B-10` | Duke had begun site work at Cayuga; its two new units are targeted for 2029 and 2030. | A/B | [Duke Energy](https://news.duke-energy.com/releases/duke-energy-breaks-ground-on-cayuga-energy-complex-project-in-vermillion-county) | Construction, not operation. | | `B-11` | Project Kilby has a 20-year PPA to serve a Microsoft data center. | B | [Kilby project owner](https://kilby.com/project/) | Offtake/development state; not FID or completed capacity. | | `B-12` | Berkeley Lab counted 253 GW of gas in active interconnection queues at year-end 2025, but only 18% had a draft or executed IA. | A | [DOE/LBNL](https://emp.lbl.gov/news/backlog-power-plants-seeking-transmission-grid-connection-eased-somewhat-2025-amidst) | Queue capacity is a developer-activity signal, not buildable or operating capacity. | | `B-13` | Historically, 13% of capacity entering queues in 2000–2020 was operating by end-2025; median request-to-operation exceeded five years. | A | [DOE/LBNL](https://emp.lbl.gov/news/backlog-power-plants-seeking-transmission-grid-connection-eased-somewhat-2025-amidst) | Historical conversion constraint, not a deterministic project forecast. | | `B-14` | Pin Oak Creek Energy Center reached commercial operation on April 30, 2026. | A/B | [Constellation Q1 2026 results](https://investors.constellationenergy.com/news-releases/news-release-details/constellation-reports-first-quarter-2026-results) | Owner's explicit COD record. | | `B-15` | Homer City's seven GE 7HA.02 turbines were converted to firm order, while Pennsylvania DEP records later permitting/site activity. | A/B | [GE Vernova](https://www.gevernova.com/news/press-releases/ge-vernova-adding-250-new-jobs-part-pennsylvania-factory-expansion-manufacture-more), [Pennsylvania DEP](https://www.pa.gov/agencies/dep/dep-regions/northwest-regional-office/homer-city-generation-redevelopment) | Firm order and site activity; not operating capacity. | | `T-01` | GE says its generation M&D service monitors 1,000+ plants and processes tens of billions of data points per day. | C | [GE Vernova APM](https://www.gevernova.com/software/products/asset-performance-management/cloud-edge) | Vendor-reported scale; proves commercial offering, not independent benefits. | | `T-02` | Siemens says 800+ power units use its monitoring/optimization expertise and 260+ plants use performance monitoring. | C | [Siemens Energy](https://www.siemens-energy.com/global/en/home/products-services/product/omnivise-performance-monitoring.html) | Vendor-reported service scale. | | `T-03` | MHI reported 144 TOMONI-connected thermal units by August 2023, operating anomaly detection and specialist review. | R/C | [MHI Technical Review](https://www.mhi.co.jp/technology/review/pdf/e604/e604030.pdf) | Named internal system record; specialists remained in the judgment loop. | | `T-04` | EPRI describes fault-inference digital twins as implemented at several gas and nuclear plants, with typical implementation of six to twelve months. | R | [EPRI Plant Modernization Toolbox](https://nuclearplantmod.epri.com/MTA-EN-015) | Broad-use readiness with recorded model and sensor failure modes; not a universal twin. | | `T-05` | GE Autonomous Tuning changes LM2500/LM6000 combustion targets every two seconds within existing safety-critical control logic. | C | [GE product page](https://www.gevernova.com/software/products/asset-performance-management/gas-turbine-tuning), [launch record](https://www.gevernova.com/news/press-releases/ge-digitals-autonomous-tuning-accelerates-the-energy-transition-with-ai-ml) | Real bounded closed loop; not authority over trips, life extension or return to service. | | `T-06` | MHI identifies autonomous combustion-dynamics and cooling-air optimization at T-Point 2. | R/C | [Mitsubishi Power TOMONI](https://power.mhi.com/service/tomoni/smarter) | Selected process functions, not general autonomous plant operation. | | `T-07` | Siemens and Volkswagen completed a certified 72-hour unattended gas-and-steam plant test in October 2025. | R | [Siemens Energy reference](https://www.siemens-energy.com/global/en/home/references/vw-power-plant-autonomy72.html) | Plant-specific hazard analysis and retained protection; exceptional reference case. | | `T-08` | GE reports an ANYmal robot collecting inspection data from 15+ assets at a named Irish thermal plant and feeding APM. | C | [GE Vernova case study](https://www.gevernova.com/software/customer-stories/robotic-inspection-data-apm-improves-safety-availability-and-efficiency) | Named commercial deployment; outcome remains vendor-reported. | | `T-09` | GE says more than 9,000 wind blades had received Digital Blade Certificates after robotic and AI-assisted inspection by April 2026. | C | [GE Vernova review](https://www.gevernova.com/news/articles/two-years-ge-vernova-reshaping-energy-future) | Manufacturing QA scale; humans review flagged areas. | | `T-10` | IBM launched Condition Insight in December 2025 and Maximo 9.2 agentic workflows in June 2026. | C | [IBM Condition Insight](https://www.ibm.com/new/announcements/maximo-condition-insight), [IBM Maximo 9.2](https://www.ibm.com/new/announcements/introducing-maximo-application-suite-9-2) | Product availability, not proof of owner adoption or safety authority. | | `T-11` | DOE CESER released Stormbreaker in July 2026 to test LLM and agent failure modes in dynamic power and OT environments. | R | [DOE CESER](https://www.energy.gov/ceser/articles/ceser-releases-new-testbed-advance-llm-and-agentic-ai-evaluation-critical) | Evaluation need is evidence against assuming generic-agent readiness. | | `W-01` | Vestas reports more than 128 GW and 55,000 turbines on its Scipher platform. | C | [Vestas Scipher](https://www.vestas.com/en/energy-solutions/service/digital-services/scipher) | Vendor-reported platform scale; multi-function fleet software is commercial. | | `W-02` | RWE says TPA Next Evolution has been implemented across its full OPEA wind fleet and assists analysts across multiple condition-data modules. | C | [RWE digital energy production](https://www.rwe.com/en/research-and-development/digitalisation-at-rwe/digital-energy-production/) | Operator-reported deployment; assists rather than replaces analysts. | | `W-03` | An autonomous drone inspection of an operating, rotating offshore turbine was demonstrated at Rødsand 2 in January 2026. | R | [RWE AQUADA-GO](https://dk.rwe.com/en/press-and-news/2026-01-15-first-autonomous-inspection-of-operational-offshore-wind-turbines-demonstrated/) | Completed demonstration; not broad fleet deployment. | | `W-04` | NREL's wtDigiTwin estimates turbine loads, motion and environment from SCADA plus a turbine model. | R | [NREL wtDigiTwin](https://www.nrel.gov/research/software/wtdigitwin-wind-turbine-digital-twin) | Purpose-specific research software, not a universal lifecycle twin. | | `W-05` | DOE/NREL's 2024 offshore O&M roadmap places fully autonomous inspection/intervention in its long-term 2032–2036 horizon. | R | [DOE/NREL roadmap](https://www.energy.gov/sites/default/files/2024-05/operations-maintenance-roadmap-us-offshore-wind.pdf) | R&D roadmap, not deterministic market forecast. | ## Claims not supported by this record - “AI is now running U.S. turbine fleets autonomously.” - “The 116 GW, 87 GW and MHI unit totals can be added into one U.S. buildout number.” - “A reserved manufacturing slot is a plant under construction.” - “Every new turbine includes an APM platform, digital twin or LTSA.” - “A digital twin provides one complete, authoritative representation of the asset.” - “Predictive maintenance eliminates inspections or transfers engineering authority to a model.” - “A product launch proves adoption, savings or safe control-room use.” - “Interconnection-queue capacity is a construction or completion forecast.”