.md · 1 sections · 4958 characters
workbench: _Working/federal-budget-2026-2027/goal/terra_institutions/gsa/batch3/REPORT.md
Canonical source SHA-256: b37362d523ca545e932633dccc5e8599f017bfaa438f6e46390958efe9e144c9
Served copy SHA-256: b37362d523ca545e932633dccc5e8599f017bfaa438f6e46390958efe9e144c9
Owner evidence cutoffs: {"federal-budget-fy2026-fy2027": "2026-09-11T19:55:13-04:00"}
These are package-level cutoffs, not a claim that this source was rechecked on those dates. Use its own publication and capture dates.
Owners: federal-budget-fy2026-fy2027
Section 1 of 1
# GSA FY2027 CJ: GAO-IG appendix and USDA FCRF evidence chain
I rendered and read the complete GAO-IG Act appendix in GSA’s official FY2027 Congressional Justification, PDF pages 342–396. It is dated March 24, 2026. The appendix contains: the statutory overview (342–344); GAO recommendation status (345–352); OIG recommendation status (353–383); the 2024 OIG semiannual reconciliation (384–394); and acronyms (395–396). The source PDF was rendered because its appendix table text was not reliably extractable. OCR aided transcription, but it did not reliably expose every tiny recommendation-number cell. The JSON inventory names those rows id_unreadable and gives the exact page, rather than guessing a number.
The appendix is prior oversight/status material compiled for the FY2027 CJ: it is dated March 24, 2026, before the April 3 public submission. It says the GAO-IG Act requires qualifying open GAO/OIG recommendations, implementation timelines/explanations, and reconciliation with OIG/GAO reporting. The CJ does not identify it as an analytical model or causal input used to formulate a FY2027 account request.
## Material findings for the budget record
The GAO table includes GAO-14-648, which asks GSA and DHS to develop DHS headquarters consolidation cost and schedule estimates that conform to leading practices and include an independent evaluation. GAO lists it as partially addressed. This is a concrete example of oversight seeking independent estimate review, but it concerns DHS headquarters, not the USDA proposal.
GAO-24-105485 remains partly open on explaining GSA’s deferred-maintenance-and-repair changes and is implementing a request for a funded, time-bounded backlog-reduction plan. GSA’s FCRF request therefore sits beside, rather than resolves, a continuing GAO transparency/control issue.
The OIG table contains current PBS work on water quality, building/child-care safety, roof fall protection, battery storage, ESPC oversight, CMc contracting, indoor firing ranges, and a $13.7 million invalid task order. These are oversight findings/statuses, not inputs cited by the FY2027 FCRF proposal.
The reconciliation table preserves important disagreement: for A150132P4R17001 (Pensacola courthouse), OIG asked for options analysis including appraisals, financial costs, and historically grounded schedules; GSA recorded implementation of a management decision while disagreeing with the recommendation. It is relevant institutional context for assessing the difference between a project assertion and a published independent model, but it is not evidence about Agriculture South.
## USDA consolidation / disposal project
The CJ calls the project the Jamie L. Whitten Federal Building and Sidney R. Yates Federal Building Consolidation and the Agriculture South Federal Building Disposal Project. It proposes to consolidate USDA from Agriculture South into Whitten/Yates and dispose of Agriculture South. The CJ gives a $375,112,500 total up-front amount, a $25,112,500 first installment of 15, and a one-time $112,500 (0.03%) FCRF administrative fee. On FBF-52 (PDF 73–74 in the accessible CJ), GSA specifically asserts that Agriculture South disposal will eliminate over $1 billion in delinquent-maintenance liabilities and $15.2 million in annual O&M costs, while delivering a substantial space reduction.
The reviewed CJ discloses general FBF selection factors such as customer/master plans, building condition/security/functionality/occupancy, utilization, lease avoidance/ROI, and risk/return. It does not publish a project-specific independent appraisal or appraisal review, benefit-cost analysis, ROI/DCF model, lease-avoidance calculation, operating-cost baseline, engineering estimate, condition assessment, utilization study, or USDA occupancy/move plan for this project. A bounded search of the official GSA CJ routes, GSA historic-building material, and targeted official-domain results did not locate one. That is a missing-reference queue, not a conclusion that internal or non-public records do not exist.
The machine-readable recommendation-level inventory, locators, statuses, and missing-reference queue are in GAO_IG_APPENDIX_AND_USDA_SOURCE_CHAIN.json.