Skip to content
Freedom 250 · Order map

EO 14262 — Strengthening the Reliability and Security of the United States Electric Grid

The order states a policy that the grid must use all available generation, and directs the Secretary of Energy to streamline DOE's Federal Power Act section 202(c) emergency-order process, develop within 30 days and publish within 90 days a uniform reserve-margin methodology, and establish a protocol to identify critical generation resources and keep them from leaving the bulk-power system.

Signed 2025-04-08 · published 2025-04-14

Sec. 2 Declares the policy of grid reliability, resilience and security and that, to address the national energy emergency declared in EO 14156, the grid must use all available generation resources, particularly secure, redundant fuel supplies. No separate result assessment recorded

Declares the policy of grid reliability, resilience and security and that, to address the national energy emergency declared in EO 14156, the grid must use all available generation resources, particularly secure, redundant fuel supplies.

Addressed to

  • the President
Order text
It is the policy of the United States to ensure the reliability, resilience, and security of the electric power grid.
Sec. 3(a) The Energy Secretary is to streamline and expedite DOE's process for issuing section 202(c) Federal Power Act orders when a grid operator forecasts a temporary supply interruption is needed to prevent grid failure, including approving applications by generators to run at maximum capacity. Not found in the notes

The Energy Secretary is to streamline and expedite DOE's process for issuing section 202(c) Federal Power Act orders when a grid operator forecasts a temporary supply interruption is needed to prevent grid failure, including approving applications by generators to run at maximum capacity.

Addressed to

  • the Secretary of Energy

What the notes record

Searched
  • 1. stories (batch 3, batch 4, upgraded): order number
  • 2. thread register: order number and words: grid reliab, 202(c), resource adequacy
  • 3. research files: grep EO/Executive Order/E.O. 14262 (md, json, csv), passages read; also words: Resource Adequacy, reserve margin
Pass
2
Deadline passed
False
Order text
shall, to the maximum extent permitted by law, streamline, systemize, and expedite the Department of Energy's processes for issuing orders under section 202(c) of the Federal Power Act during the periods of grid operations described above
Sec. 3(b) The Energy Secretary is to develop a uniform methodology for current and anticipated reserve margins in all FERC-regulated regions of the bulk power system and use it to identify regions below acceptable thresholds. Found in part

The Energy Secretary is to develop a uniform methodology for current and anticipated reserve margins in all FERC-regulated regions of the bulk power system and use it to identify regions below acceptable thresholds.

Addressed to

  • the Secretary of Energy

Deadline

Words
Within 30 days of the date of this order
Date
2025-05-08
Counted
Within 30 days of the date of this order counted from signing 2025-04-08
Type
deadline

What the notes record

What it shows
published: the DOE July 2025 Resource Adequacy Report is recorded as made to implement the order; the file does not date the 30-day methodology itself
Pass
2
Evidence kind
formal step toward the result
Date
2025-05-08
Kind of date
deadline on an officer or body
Deadline passed
True
DOE forward-looking empirical/modeling analysis, created to implement EO 14262
REFERENCE_COVERAGE.json
Order text
Within 30 days of the date of this order, the Secretary of Energy shall develop a uniform methodology for analyzing current and anticipated reserve margins for all regions of the bulk power system regulated by the Federal Energy Regulatory Commission and shall utilize this methodology to identify current and anticipated regions with reserve margins below acceptable thresholds as identified by the Secretary of Energy.
Sec. 3(b)(iii) The methodology and any analysis it produces are to be published on DOE's website. Found

The methodology and any analysis it produces are to be published on DOE's website.

Addressed to

  • the Secretary of Energy

Deadline

Words
within 90 days of the date of this order
Date
2025-07-07
Counted
within 90 days of the date of this order counted from signing 2025-04-08
Type
deadline

What the notes record

What it shows
published: DOE July 2025 Resource Adequacy Report on energy.gov (file URL reads FINAL JULY 7); the full report was not read in the file
Pass
2
Date
2025-07-07
Kind of date
deadline on an officer or body
Deadline passed
True
DOE forward-looking empirical/modeling analysis, created to implement EO 14262
REFERENCE_COVERAGE.json
Order text
be published, along with any analysis it produces, on the Department of Energy's website within 90 days of the date of this order.
Sec. 3(c) The Energy Secretary is to set up a process for regular assessment of the methodology and its results and a protocol to identify generation resources critical to reliability in a region. Not found in the notes

The Energy Secretary is to set up a process for regular assessment of the methodology and its results and a protocol to identify generation resources critical to reliability in a region.

Addressed to

  • The Secretary of Energy

What the notes record

Searched
  • 1. stories (batch 3, batch 4, upgraded): order number
  • 2. thread register: order number and words: grid reliab, 202(c), resource adequacy
  • 3. research files: grep EO/Executive Order/E.O. 14262 (md, json, csv), passages read; also words: Resource Adequacy, reserve margin
Pass
2
Deadline passed
False
Order text
The Secretary of Energy shall establish a process by which the methodology described in subsection (b) of this section, and any analysis and results it produces, are assessed on a regular basis, and a protocol to identify which generation resources within a region are critical to system reliability.
Sec. 3(c)(i)-(ii) The protocol is to use all lawful mechanisms, including section 202(c), to retain critical resources in at-risk regions and to prevent an identified resource over 50 MW from leaving the bulk-power system or converting fuel where that would cut accredited capacity. Found in part

The protocol is to use all lawful mechanisms, including section 202(c), to retain critical resources in at-risk regions and to prevent an identified resource over 50 MW from leaving the bulk-power system or converting fuel where that would cut accredited capacity.

Addressed to

  • the Secretary of Energy

What the notes record

What it shows
issued: 2026 section 202(c) orders keeping named plants available; the story does not tie them to an EO 14262 protocol and records no protocol
Pass
2
Evidence kind
formal step toward the result
Deadline passed
False
roughly 90-day orders keeping named plants that were due to retire available
doe-202c-orders.json
Order text
prevent, as the Secretary of Energy deems appropriate and consistent with applicable law, including section 202 of the Federal Power Act, an identified generation resource in excess of 50 megawatts of nameplate capacity from leaving the bulk-power system