Rochester and Quinn timetables identify review and permit gates

Evidence through 2026-11-22

The official Permitting Dashboard, read November 22, reports Rochester’s rare-earth separation project and the Quinn Fluorspar exploration project as In Progress, with respectively zero of two and zero of three environmental-review/permitting actions complete. Their overall estimated completion dates are January 5, 2027 and March 1, 2027. These are permitting schedules, not dates of plant production or completed exploration. Rochester project · Quinn project

This answers the timetable-publication question left in the November 16 FAST-41 return, which recorded planned status and a November 20 timetable target. The original posting time and exact project-status transition date are not established here. The dates below are the agencies’ reported milestone dates or targets, not events inferred from this inspection.

Rochester — project 128316

The Department of War is responsible for both listed actions. Its categorical-exclusion action 128361 is in progress. The dataset records initial application submission on November 5 and the application being deemed complete on November 12. Its final decision/agency action is targeted for January 5, 2027, with the actual-completion field empty. Section 106 action 128366 remains planned: consultation initiation is targeted for December 8 and consultation conclusion for December 29. Both actual dates remain empty. Exact project rows

Quinn — project 128321

The U.S. Forest Service is responsible for three planned actions:

ActionReported prior stepNext targets; no actual completion recorded for these targets
Plan of Operations, 128481Draft initial plan submitted September 11Complete initial plan submission November 30; agency acceptance December 4; final plan and financial assurance February 22, 2027; final approval March 1
Section 106, 128486No completed consultation milestone in the reached rowsInitiation January 11, 2027; conclusion January 19
Categorical exclusion, 128496Initial application submitted September 11Application deemed complete December 4; final decision/agency action February 12, 2027

The two September 11 entries are preliminary applicant milestones, not completion of either permitting action. The project remains the proposed exploration programme described in the earlier owner. Exact project rows

Source and next evidence

The static project headers were readable, but their timetable bodies remained “Loading” in the web extraction. A direct project-page request returned 403 and was not retried. The independently linked official Data Portal supplied the public dataset, schema and exact project-filtered rows. The reading ledger records all 9 Rochester and 14 Quinn rows inspected, their action/milestone identifiers, dates and completion flags. Its source-fetch field is not a milestone or publication date.

The original timetable return is resolved. The successor question is whether the named milestones become actual completed agency actions, and what final decision or authorization follows. The nearest scheduled return is Quinn’s November 30 complete-plan submission, followed by December 4 acceptance/deemed-complete targets. Actual agency instruments, conditions, later schedule revisions and any construction, exploration or production activity retain separate records. No signed final permit or production result is established by this schedule reading.

Sources

Document details and formats

Saved research reading. Its original dates and claim limits control; the export date does not refresh the evidence.

Saved source details

---

title: Rochester and Quinn timetables identify review and permit gates

research_id: government-hidden-control-surfaces-2026

artifact_role: answer

status: current

evidence_cutoff: 2026-11-22

observed_on: 2026-11-22

---