title: Rochester and Quinn timetables identify review and permit gates
research_id: government-hidden-control-surfaces-2026
artifact_role: answer
status: current
evidence_cutoff: 2026-11-22
observed_on: 2026-11-22
---

# Rochester and Quinn timetables identify review and permit gates

The official Permitting Dashboard, read November 22, reports Rochester’s rare-earth separation project and the Quinn Fluorspar exploration project as **In Progress**, with respectively **zero of two** and **zero of three** environmental-review/permitting actions complete. Their overall estimated completion dates are January 5, 2027 and March 1, 2027. These are permitting schedules, not dates of plant production or completed exploration. [Rochester project](https://www.permits.performance.gov/permitting-project/fast-41-transparency-projects/rochester-rare-earth-separation-facility-project) · [Quinn project](https://www.permits.performance.gov/permitting-project/fast-41-transparency-projects/quinn-fluorspar-project)

This answers the timetable-publication question left in the [November 16 FAST-41 return](FAST41_NAVAJO_BROADBAND_AND_CRITICAL_MINERALS_2026-11-16.md), which recorded planned status and a November 20 timetable target. The original posting time and exact project-status transition date are not established here. The dates below are the agencies’ reported milestone dates or targets, not events inferred from this inspection.

## Rochester — project 128316

The Department of War is responsible for both listed actions. Its categorical-exclusion action **128361** is in progress. The dataset records initial application submission on **November 5** and the application being deemed complete on **November 12**. Its final decision/agency action is targeted for **January 5, 2027**, with the actual-completion field empty. Section 106 action **128366** remains planned: consultation initiation is targeted for **December 8** and consultation conclusion for **December 29**. Both actual dates remain empty. [Exact project rows](https://data.permits.performance.gov/resource/mcm3-xbid.json?project_id=128316&%24limit=100)

## Quinn — project 128321

The U.S. Forest Service is responsible for three planned actions:

| Action | Reported prior step | Next targets; no actual completion recorded for these targets |
|---|---|---|
| Plan of Operations, 128481 | Draft initial plan submitted September 11 | Complete initial plan submission November 30; agency acceptance December 4; final plan and financial assurance February 22, 2027; final approval March 1 |
| Section 106, 128486 | No completed consultation milestone in the reached rows | Initiation January 11, 2027; conclusion January 19 |
| Categorical exclusion, 128496 | Initial application submitted September 11 | Application deemed complete December 4; final decision/agency action February 12, 2027 |

The two September 11 entries are preliminary applicant milestones, not completion of either permitting action. The project remains the proposed exploration programme described in the earlier owner. [Exact project rows](https://data.permits.performance.gov/resource/mcm3-xbid.json?project_id=128321&%24limit=100)

## Source and next evidence

The static project headers were readable, but their timetable bodies remained “Loading” in the web extraction. A direct project-page request returned 403 and was not retried. The independently linked official Data Portal supplied the public dataset, schema and exact project-filtered rows. The [reading ledger](ROCHESTER_QUINN_TIMETABLE_READING_LEDGER_2026-11-22.json) records all 9 Rochester and 14 Quinn rows inspected, their action/milestone identifiers, dates and completion flags. Its source-fetch field is not a milestone or publication date.

The original timetable return is resolved. The successor question is whether the named milestones become actual completed agency actions, and what final decision or authorization follows. The nearest scheduled return is Quinn’s November 30 complete-plan submission, followed by December 4 acceptance/deemed-complete targets. Actual agency instruments, conditions, later schedule revisions and any construction, exploration or production activity retain separate records. No signed final permit or production result is established by this schedule reading.