Data-center electricity already in use and the ERCOT Batch Zero connection queue

Full saved reading

View cited sources (12)

These are the sources cited by this reading. Each source keeps its own date and scope.

Optional file downloads
For AI readers: complete text and record details

Saved research reading. Its original dates and claim limits control; the export date does not refresh the evidence.

Saved source details

---

title: "Data-center electricity already in use and the ERCOT Batch Zero connection queue"

research_id: data-center-federal-legal-spine

evidence_cutoff: 2026-11-11

status: current

---

Data-center electricity already in use and the ERCOT Batch Zero connection queue

The federal legal return covers named site and tariff decisions. The grid operators' data show where demand was already observable and how Texas treated projects seeking new service. The measures below retain their reported populations.

Electricity the operators observed

ERCOT's February 4, 2026 revision for its February board meeting analyzes roughly 400 cloud-based data-center sites of at least 1 MW, including AI computing, cloud storage and colocation and excluding cryptocurrency mining. ERCOT reported 15.5% growth in actual demand in MW between January 2025 and January 2026. The chart uses average daily MW. The separately stated 9,850 MW combines capacity approved to energize in the large-load process and operating sites outside that process. ERCOT System Operations Update, slide 16

ERCOT's April 2026 monthly report separates 5.9 GW of large loads classified as observed energized from 3.2 GW approved to energize with operation still unobserved. The large-load interconnection population also includes customers outside the data-center category. Its recorded stages and the February cloud-site usage measure answer different questions. ERCOT April 2026 Monthly, p. 4

PJM's May 29, 2026 accuracy report gives observed July 2025 data-center peak values from utility and load-serving-entity submissions. The table reports 5,563 MW in the Dominion zone, 1,726 MW in AEP, 623 MW in ComEd and 255 MW in PSEG. The Dominion zone has the largest disclosed value. PJM suppressed a value attributable to one customer, and historical values appear where submitting entities supplied them. The zone peaks give regional evidence of use and leave individual first-service dates, facility demand and total MWh open. PJM report, pp. 3 and 6

Texas eligibility, study and approval to energize

On June 18, 2026, the Public Utility Commission of Texas approved ERCOT's Batch Zero process for qualifying projects of at least 75 MW. ERCOT reported more than 438 GW of tracked large-load requests, nearly 89% from data centers. The total describes requests across the region. ERCOT approval announcement · Planning Guide revision PGRR145

On August 3, 2026, Governor Abbott directed a verification and audit. ERCOT delayed final classification and told its September board it had paused approvals to energize new large data centers and crypto mines of at least 75 MW until verification and community-impact review were complete. On September 3, 2026, ERCOT sent utilities conditional classifications. Its board deck counts 204 base-load and 158 studied-load projects, 362 total. Base load includes more than the already-energized categories. The deck gives 66.4 GW for base load and shows two figures for the studied cohort, 127.9 GW in the opening summary and 125.4 GW in the slide 6 graphic. The project counts agree. The material supplied gives no reconciliation of the two studied-GW figures. August market notice · September classification notice · Board deck, slides 1 and 3–6

ERCOT began issuing eligibility-verification requests on September 9, 2026 and issued a separate community-impact request on September 14, 2026. Its board deck sets December 10, 2026 as the due date for both reports and places final classifications in December. The scoped November 11, 2026 check located no posted final Batch Zero classification or formal lifting of the energization pause. PJM reported on September 29, 2026 that it had begun vetting utility submissions for its 2027 forecast and that PJM itself maintains no load interconnection queue. A forecast adjustment and an ERCOT Batch Zero classification remain different objects. ERCOT eligibility notice · ERCOT impact notice · ERCOT verification page · PJM forecast vetting

A utility's service commencement record or a dated meter disclosure would establish a named facility's draw. A classification, permit, request or projected load establishes its own stage. These regional records do not identify a first-service day for an individual site.