Project Ledger — Investment Claims to Funding Evidence
How to read this ledger
This is a deliberately non-additive first wave. It starts with source-rich projects that illustrate the different capital structures hidden inside public investment rhetoric. The absence of a disclosed facility, lender or draw means not publicly stated, not that the project is unfinanced.
Funding evidence reports only what the linked source supports. Public awards are not cash receipts, and parent-level funds are not automatically allocated to the named asset. See `CLAIM_RECONCILIATION_PROTOCOL.md` for non-addition rules and `RESEARCH_DESIGN_AND_EVIDENCE_STANDARD.md` for the evidence ladder.
Semiconductors and advanced manufacturing
| ID | Project / claim | Object and project state | Funding evidence located | Open proof / source |
|---|---|---|---|---|
| F-01 | TSMC Arizona — $165B planned U.S. investment | Multi-fab sponsor program; Fab 1 high-volume production end-2024, Fab 2 under construction, Fab 3 construction began 2025. | Up to $6.6B CHIPS direct funding; eligibility for up to $5B Commerce loans; $8B TSMC Arizona notes outstanding at 2025 year-end, parent-guaranteed. This does not evidence that the full $165B is closed or drawn. | Allocate sponsor equity, federal draws, customer support and notes to each fab. 20-F |
| F-02 | Micron — about $200B U.S. manufacturing and R&D plan | Twenty-year, multi-site parent program: Boise, Clay and Manassas. New York first concrete July 2026; Idaho first fab expected mid-2027. | Up to $6.1B CHIPS direct funding for two Boise and two Clay fabs plus $275M Manassas award; milestone based, not up-front cash. | Site-specific debt/equity and award disbursements not public. Release; agreement disclosure |
| F-03 | Samsung Central Texas — more than $37B | Multi-asset Taylor/Austin program; Taylor construction continued in 2025, target operational end-2026. | Up to $4.745B CHIPS direct funding, milestone payable; Taylor initial minimum investment reported as $17B. | Sponsor debt/equity, draws and allocation among assets not public. Award; update |
| F-04 | Amkor Peoria, Arizona — $7B two-phase campus | Specific advanced-packaging campus; groundbreaking 2025, first production expected 2028. | Up to $407M CHIPS direct funding, conditional on milestones; tax-credit and state/local incentives named but not fully quantified. | Sponsor debt/equity, actual award draws and customer contracts not public. 10-Q; release |
| F-05 | Hyundai Motor Group — $21B, 2025–28 | Parent allocation: $9B auto, $6B parts/logistics/steel and $6B future industry/energy; no single borrower. | Sponsor release states categories and horizon; no project debt facility or full capital-stack record. | Start with each legal entity/site; distinguish group cash from local project debt. Release |
| F-06 | BlueOval SK battery plants, Tennessee/Kentucky | Three Ford–SK On JV plants. | DOE closed a direct loan of up to $9.63B, including principal and capitalized interest, to BlueOval SK LLC—the JV borrower. | Draw schedule, JV equity, state incentives and actual spend remain open. DOE close; project page |
| F-07 | Thacker Pass lithium, Nevada | Phase 1 targets 40,000 tonnes/year battery-grade lithium carbonate. | $2.23B amended DOE construction facility ($1.97B principal plus expected capitalized interest); draws of $435M on 2025-10-20 and $432M on 2026-02-24. JV: 62% Lithium Americas / 38% GM; GM $430M cash + $195M LC; Lithium Americas about $330M cash; GM offtake up to 100% of Phase 1. | Loan closed and drawn; continue draw/use and construction evidence. 2025 10-K; DOE page |
| F-08 | MP Materials 10X / Mountain Pass, California | Multibillion-dollar DoD partnership; project cost not audited in reviewed sources. | DoD bought $400M convertible preferred stock; executed $150M heavy-rare-earth-separation loan; 10-year price floor and 10X offtake. JPMorgan/Goldman $1B debt commitment letter; $650M assigned to 10X, but not proof of final facility/draw. | Separate public equity/loan from revenue support and commercial debt commitment. MP 8-K; DoD loan |
Compute and data-center infrastructure
| ID | Project / claim | Object and project state | Funding evidence located | Open proof / source |
|---|---|---|---|---|
| C-01 | Stargate — $500B over four years / 10GW | Parent-program target across variable sites and entities; not one financing close. | Launch names SoftBank, OpenAI, Oracle and MGX as initial equity funders and says $100B would begin deployment. No $500B credit agreement, equity-call schedule or collateral package disclosed. | Site SPV, binding commitments, calls/draws, debt provider, power and lease docs. Launch |
| C-02 | Stargate I, Abilene — $15B JV | Flagship build-to-suit; Crusoe affiliates and Longhorn JV 3–8 lease additional buildings to Oracle America. First phase live on Oracle Cloud Infrastructure September 2025. | Blue Owl filings identify equity investments in Longhorn JVs with Crusoe affiliates; Crusoe described a $15B JV with Blue Owl and Primary Digital. | JV agreement, debt/equity split, lenders, lease economics and actual contributions. Blue Owl filing; Crusoe update |
| C-03 | Vantage Frontier, Texas — more than $25B / 1.4GW | 1,200-acre, ten-data-center campus; construction started, first building H2 2026, phases through 2028. | Prior platform funding: $9.2B equity and a $3B green loan across at least eight North American sites; neither allocated to Frontier. | Project loan/bond/equity, anchor tenants and power-cost allocation. Frontier; platform funding |
| C-04 | CoreWeave Lancaster, Pennsylvania — up to $6B | Proposed data-center equipment/capacity: initial 100MW, potential 300MW. | $2.6B delayed-draw term loan through CoreWeave Compute Acquisition Co. V and VII; filed materials identify it as financing Pennsylvania development. Corporate stack also includes DDTLs, bonds, converts, OEM/software finance, IPO proceeds and customer cash. | FID, loan draws, project allocation, land/lease, construction and offtake. 2025 10-K |
| C-05 | Google PJM region — more than $25B over two years | Regional corporate capex envelope; no individual campus schedule or SPV named. | Alphabet: 2025 capex $91.4B, operating cash flow $164.7B, $37.3B senior-note net proceeds for general corporate purposes. Separate $3B/20-year Brookfield hydro agreement is power support, not project debt. | Sites, equipment/building split, ownership/lease and project allocation. Announcement; 10-K |
| C-06 | Blackstone/QTS Pennsylvania — more than $25B plus $60B "catalyzed" | Fund-managed digital and energy-infrastructure plan; construction expected by end-2028 subject to approvals. | Blackstone says its managed Infrastructure and Real Estate funds will invest and it formed a PPL JV. No public fund commitment, JV percentage, lender, customer contract or subsidy amount identified. | Separate fund equity, QTS/customer money, PPL generation funding and third-party debt; define $60B. Announcement |
| C-07 | Meta Richland Parish / Entergy, Louisiana — over $50B | Campus expansion and associated 5GW capacity; construction and utility approval. | Meta's 2025 company-wide pool: $115.8B operating cash flow, $29.91B senior-note proceeds, $72.22B capex. LPSC approved Entergy generation/transmission facilities, but those figures do not allocate cash to the campus. | Energy-service agreement and Entergy project financing. Meta update; Meta 10-K; LPSC order |
Energy, grid and defense reference rows
| ID | Project / claim | Object and project state | Funding evidence located | Open proof / source |
|---|---|---|---|---|
| E-01 | Venture Global CP2 LNG, Louisiana | Phase I financing $15.1B; March 2026 Phase II close brought total CP2 financing to $20.7B. | CP2 LNG LLC: $11.25B senior-secured construction term loan + $850M working-capital/LC; CP2 Holdings: $2.8B equity bridge + $191M interest reserve. Phase II: $8.6B project financing with 26 named international banks. Long-term LNG contracts support revenue, not up-front customer funding. | FID and financial close; trace draws, holders after syndication, and construction spend. Phase I 8-K; Phase II release |
| E-02 | NextDecade Rio Grande LNG Train 5, Texas — $6.7B expected project cost | FID, financial close and full notice to proceed. | SPV stack: $3.59B senior-secured non-recourse term loan + $500M senior-secured private-placement notes + $1.29B NextDecade equity + $1.29B GIP/BlackRock, GIC and Mubadala equity. NextDecade funded its $1.29B equity commitment with $233M cash and $1.33B term loans. | Strong example that sponsor "equity" can itself be debt financed; trace draws. Financial-close release; financing 8-K |
| E-03 | AEP five-state transmission rebuild | Rebuild/reconductor nearly 5,000 miles of line. | $1.6B DOE loan guarantee at financial close, not an identified cash draw. AEP also reported $2.3B forward equity issuance and a Midwest transmission JV at corporate level, neither allocated dollar-for-dollar. | Lender, advance schedule and ratepayer recovery require FERC/state records. DOE; AEP |
| E-04 | Crane nuclear restart, Pennsylvania — 835MW | Restart positioned as firm power for data centers/other load. | DOE reports $1B loan closed to Constellation, backed by Constellation's balance sheet rather than a narrow-SPV borrower. | Project capex, equity allocation, advance record and site-specific customer contract not located. DOE page |
| E-05 | Lockheed munitions expansion / Troy, Alabama | Lockheed says more than $9B through 2030 across 20+ U.S. facilities; Troy center 87,000 sq. ft., with no project dollar value stated. | 2025 corporate pool: $8.557B operating cash flow, $1.985B net senior-note proceeds, $1.649B capex. $4.7B PAC-3 UCA is a demand/revenue instrument, not construction finance. | Construction underway; Troy-specific debt/grant unproven. Troy release; 10-K |
| E-06 | Amentum / Savannah River Site AI and energy project — 1GW concept | NNSA selected Amentum to negotiate a phased lease with on-site generation. Selection is not lease execution, financing, construction or operation. | No financing facility or draw in selection notice. | Executed lease, SPV, approvals, equity/debt, customer and first construction spend. NNSA selection |
First-wave pattern
The ordinary capital channels become visible wherever disclosure resolves the asset, borrower and counterparty: parent/sponsor cash, public support, secured loans and notes, sponsor-managed funds, project JVs, international lenders and contracted customer relationships. The missing work is allocation and draw evidence, not a demonstrated funding gap that requires a crypto rail.
Every row presently carries digital-rail involvement: not evidenced in reviewed funding sources.
Sources
Full saved reading
View cited sources (36)
These are the sources cited by this reading. Each source keeps its own date and scope.
- 20-F
- Release
- agreement disclosure
- Award
- update
- 10-Q
- release
- Release
- DOE close
- project page
- 2025 10-K
- DOE page
- MP 8-K
- DoD loan
- Launch
- Blue Owl filing
- Crusoe update
- Frontier
- platform funding
- 2025 10-K
- Announcement
- 10-K
- Announcement
- Meta update
- Meta 10-K
- LPSC order
- Phase I 8-K
- Phase II release
- Financial-close release
- financing 8-K
- DOE
- AEP
- DOE page
- Troy release
- 10-K
- NNSA selection
Document details and formats
Saved research reading. Its original dates and claim limits control; the export date does not refresh the evidence.
Saved source details
---
title: "Wave 1 Project Ledger — Investment Claims to Funding Evidence"
status: current
artifact_role: source-bearing project ledger
evidence_cutoff: 2026-07-31
---
Original title: Wave 1 Project Ledger — Investment Claims to Funding Evidence