Thacker Pass Phase 1 construction costs, funding and progress
Full saved reading
Read source: June 30 Form 10-Q, capex table
View cited sources (2)
These are the sources cited by this reading. Each source keeps its own date and scope.
Saved research reading. Its original dates and claim limits control; the export date does not refresh the evidence.
Saved source details
---
title: "Thacker Pass Phase 1 construction costs, DOE loan draws and physical progress"
research_id: us-inbound-investment-industrial-capex
evidence_cutoff: 2026-11-11
---
Thacker Pass Phase 1 construction costs, funding and progress
How much construction cost has Lithium Americas actually capitalized?
Lithium Americas’ November 11, 2026 preliminary release reports $2,447.6 million in cumulative capitalized construction and other project costs through September 30, 2026. That includes $2,261.3 million of Phase 1 construction within the project estimate, $114.2 million of other capitalized development and $72.1 million of capitalized interest. Its August 13, 2026 Form 10-Q reported $1,785.1 million in total through June 30, 2026, of which $1,621.7 million was Phase 1 construction. The comparable published totals imply a $662.5 million Q3 increase, including $639.6 million in the construction category. The held construction-use audit covers the earlier March 31, 2026 cumulative reading of about $1.277 billion. November 11 cost table · June 30 Form 10-Q, capex table
Capitalization records costs recognized as assets and includes interest. The construction line excludes prepaid costs and long-lead equipment deposits until goods or services are received. It includes incurred tariffs and excludes $19.5 million in cumulative community contributions expensed under U.S. GAAP, which the project estimate includes. The filed June 30 cash flow statement gives $631.564 million in six-month consolidated cash additions to mineral properties, plant and equipment. The company attributes the year-over-year increase primarily to higher construction activity and expenditures at Thacker Pass. A project-specific supplier-payment total remains unverified. The issuer raised its Phase 1 capital-cost estimate from $2.93 billion to $3.83 billion including contingency and its fiscal 2026 guidance from $1.3–$1.6 billion to $1.7–$2.0 billion. The issuer attributed about $245 million of the increase to revised installation labor rates and about $100 million to tariffs and logistics. The latter includes estimated tariff exposure of about $60 million. These estimate components carry separate scopes from the cumulative costs. The November 11 figures remain preliminary and unaudited. The company scheduled full Q3 results for November 12, 2026. Issuer estimate, accounting footnotes and reporting status
What was drawn on the DOE loan, and how does the proposed funding bridge work?
Lithium Nevada LLC is the DOE borrower within the Lithium Americas–GM joint venture. The first two advances totaled $867 million. The filed Q2 report records a third advance of $342 million on June 3, 2026, bringing receipts to $1.209 billion. The November update reports a fourth advance of $239 million on August 21, 2026, bringing receipts to $1.448 billion. It also reports that Lithium Americas contributed $120 million in required reserve funding on October 7, 2026 under the earlier amendment. Advances, reserve balances and costs capitalized describe separate cash and accounting stages. Q2 DOE loan note · November liquidity update
The company says the November 10, 2026 DOE loan amendment and related arrangements address an estimated $995 million incremental funding need. The stated components are $895 million of added capex, $58 million in net additional sustaining-reserve needs through March 2028, and $42 million net across other items. The expected funding bridge uses $650 million in planned Lithium Americas contributions to the JV, $315 million already credited to DOE-loan reserve accounts and available as required, and a roughly $30 million reduction in sustaining-reserve requirements during and after ramp-up. The issuer reported a 62% Lithium Americas and 38% GM ownership split at June 30. As of the November release, the company expected its stake to increase and the resulting ownership shares were still being finalized. Actual contributions, reserve deployment and the final ownership split remain open. Issuer financing update · Held finance-close evidence
What has been built and when is production expected?
The Q2 filing reports completed local high-voltage-line upgrades and placement of the first electrical room, 115 kV transformer and control enclosures. All major structural steel had reached the site by the end of August 2026, with installation continuing. By September 30, 2026, the company reported detailed engineering complete, procurement over 90%, over 80% of third-party contract value committed and over 50% incurred. By the end of October 2026, 80% of the required fabricated piping was in transit or delivered. These percentages have different denominators. At the separate Winnemucca transload terminal, the reported 95% in Q3 applied to rail stabilization and sub-ballast installation. Q2 construction report · November construction update
The company’s November update targets late 2027 mechanical completion and a commercial production ramp through 2028. It describes early utility commissioning and grid energization as future 2026 milestones. The 40,000 tonnes per year figure is nominal lithium carbonate output at full Phase 1 capacity. The reviewed sources establish construction progress and leave operating output, timing of sales and full-rate performance open. Issuer timeline and production scope