Actual Construction-Use Evidence Audit — Six Deep Dives

Rule

A lender or DOE advance proves borrower receipt, not necessarily contractor payment or capitalized construction. A capitalized-cost/CIP figure is strong deployment evidence, but still does not identify which financing source paid each dollar. Do not derive a residual by subtracting draws from CIP.

ProjectActual receiptActual construction-use evidenceWhat cannot be claimedEvidence grade
CP2 LNGJuly 2025 equity bridge of $2.809B fully drawn to make indirect equity contributions; Phase-1 construction facilities not fully drawn at 2025 year-end.$9.9B of CP2 Phases 1 and 2 total project cost paid at 2025-12-31.That $9.9B is not Phase-1-only, not a use-of-proceeds match to the $15.1B close, and not operating revenue.Partial combined-project spend
Rio Grande LNG Train 5$150M first installment of $500M notes issued December 2025; $3.6B Train-5 bank facility had zero drawn at 2026-03-31.Q1 2026 $1.176674B PP&E cash acquisition and $11.659040B facility-under-construction asset are consolidated across Phase 1, Trains 4 and 5.No Train-5-only CIP, paid-to-date cost, restricted cash, EPC payable or equity cash received.Project receipt; no project-specific spend
Thacker Pass Phase 1$867M DOE ATVM advances through 2026-02-24, retained in restricted borrower accounts.$1.277B cumulative capitalized construction/project cost at 2026-03-31; $1.138B within $2.93B Phase-1 construction-capex estimate.CIP is not a source-by-source reconciliation: do not describe the difference from DOE advances as an unfunded gap.Strong project-specific actual-use evidence
BlueOval SK$7.835540B DOE/FFB advances to BOSK before May 2026 restructuring.KY Facility 1 certificate of occupancy; KY Facility 2 building constructed.No audited BOSK CIP, contractor-payments, restricted-cash or plant-by-plant advance schedule located; advance is not spend.Strong borrower receipt; physical progress, no cost figure
TSMC Arizona$8.0B Arizona notes outstanding at 2025 year-end; no published CHIPS/loan draw or paid-in amount under $20B capital authorization.Fab 1 volume production at end-2024; Fab 2 and Fab 3 construction state public.No Arizona CIP/PP&E-at-cost, construction cash paid, project restricted cash, CHIPS cash received, loan draw, or fab revenue figure.Operational/build evidence, no dollar deployment
Abilene DC1Gross equity contributions of $926.846823M at 2025-12-31; construction-facility draw unavailable.Two buildings delivered in 2025; $146.738356M interest/loan-acquisition cost capitalized; $35M one-time land/power reservation payment; rent began March and July 2025.Gross equity is not net cost because $303.608587M distributions occurred. ASC 946 fair-value accounting does not supply historical construction-cost/CIP roll-forward or loan utilization.Partial financial/use markers; no total cost

Ranking for an eventual deployed-capital numerator

  1. Thacker Pass — usable project-specific capitalized cost and advance clocks.
  2. CP2 — real paid-cost evidence, only for the combined Phases 1–2 project family.
  3. Abilene DC1 — partial capitalized-finance and physical-delivery evidence, no historical-cost total.
  4. Rio Grande Train 5 — actual note issuance, but spend is broader-facility and the bank loan was undrawn.
  5. BlueOval SK — large actual advances and physical milestones, no cost/spend disclosure.
  6. TSMC Arizona — actual operating/build status, no public dollar deployment record in reviewed sources.

The ranking is an evidence-quality ranking, not a ranking of project importance, likely cost, or commercial viability.

Sources

Sources

Full saved reading

View cited sources (8)

These are the sources cited by this reading. Each source keeps its own date and scope.

Document details and formats
Optional file downloads
For AI readers: complete text and record details

Saved research reading. Its original dates and claim limits control; the export date does not refresh the evidence.

Saved source details

---

title: "Actual Construction-Use Evidence Audit — Six Deep Dives"

status: current

artifact_role: deployment-clock audit

evidence_cutoff: 2026-07-31

---