Source ledger — Federal Reserve Non-Core Initiative Governance
Full saved reading
View cited sources (4)
These are the sources cited by this reading. Each source keeps its own date and scope.
Saved research reading. Its original dates and claim limits control; the export date does not refresh the evidence.
Source ledger — Federal Reserve Non-Core Initiative Governance
> Later check — November 23, 2026: Dated return. GSA publicly confirmed its announced project role on October 1. The November 9 OIG management-challenges report continues the renovation warning and identifies forecasting/modeling modernization as a concrete next-project risk. No completed independent cost audit, signed ceiling, quantified recovery, issued agency-wide framework, demonstrated first reuse or closure was located; Oversight.gov lists all seven recommendations open. The September baseline and proof-gate states below retain their original clocks.
Research ID: federal-reserve-noncore-initiative-governance-2026
Cutoff: 2026-09-30 EDT
This ledger records what each source can prove. It does not promote an
announcement, recommendation or accounting aggregate into a later operating
state.
Primary sources
1. Federal Reserve OIG Report 2026-FMIC-B-016
- Controls: project chronology; budget and package evidence; CMAR/GMP
execution; governance and reporting findings; seven recommendations; Chairman
Warsh's attached response; the Board-as-nonexpert-owner diagnosis; planned IT
modernization as a future relevance point.
- Does not prove: final cost reasonableness; amount of avoidable loss; signed
GMP; completed independent audit; recovered amount; issued agency policy;
successful IT-modernization application; durable closure.
2. Board of Governors 2025 and 2024 financial statements
- Source: OIG Report 2026-FMIC-B-003, March 12, 2026
- Controls: Board entity and U.S. GAAP boundary; year-end 2025 and 2024
aggregate construction-in-process balances; capital expenditures; property
accounting policy; financial-statement audit opinion and internal-control
reporting.
- Does not prove: Eccles-1951-only cost; vendor, trade, package or cost-code
detail; value for money; contract compliance; paid-but-unreceived services;
exact placed-in-service classification.
3. Board of Governors 2023 and 2022 financial statements
- Source: OIG Report 2024-FMIC-B-002, March 11, 2024
- Controls: earlier aggregate construction-in-process balances used to build
the 2022–2025 accounting trend.
- Does not prove: project-level or vendor-level lineage.
4. Board Acquisition Policy
- Source: Board of Governors Acquisition Policy
- Controls: the Board's published procurement posture and current public
acquisition-policy surface.
- Does not prove: the specific Eccles-1951 contract, an operative post-OIG
framework or application to IT modernization.
Current evidence-state ledger
| Proposition | State | Controlling source |
|---|---|---|
| The Board failed to execute the Eccles-1951 CMAR contract effectively | observed finding | OIG Report 2026-FMIC-B-016 |
| The Board should treat itself as a nonexpert owner for certain non-core initiatives | observed OIG institutional diagnosis | OIG Report 2026-FMIC-B-016 |
| Seven corrective recommendations were issued | observed | OIG Report 2026-FMIC-B-016 |
| Warsh concurred and directed GSA, audit, GMP, metrics and remedies | directed | Management response attached to OIG Report 2026-FMIC-B-016 |
| GSA holds an operative delegated Project Executive mandate | not yet established separately | Return gate |
| An independent auditor has been selected and engaged | not established | Return gate |
| Awarded costs have been independently validated | not established | Return gate |
| A project-level GMP or enforceable substitute has been signed | not established | Return gate |
| The Board has recovered cash or obtained a project credit | not established | Return gate |
| The Board has issued the agency-wide framework | not established | Return gate |
| The framework governs planned IT modernization | not established | Return gate |
| The recommendations are closed and the capability is durable | not established | Return gate |
Required source types for the next update
Prefer, in order:
1. OIG recommendation-follow-up or closure evidence;
2. signed Board/GSA authority, governance or interagency instrument;
3. procurement award or audit engagement record;
4. independent audit report and management response;
5. executed contract modification, GMP or fee cap;
6. Board policy, committee charter, RACI, KPI or dashboard;
7. contract demand, modification, credit, settlement or payment record;
8. audited financial statements and notes;
9. project-ledger, CIP or placed-in-service reconciliation; and
10. IT-modernization budget, charter, procurement or assurance record showing
actual reuse of the framework.
Source-handling rules
- Keep Board, GSA, contractor, auditor and OIG statements attributed to the
issuing actor.
- Preserve original and current budget and schedule measures together.
- Keep award, invoice, accrual, cash payment, CIP, placed-in-service transfer and
depreciation on separate clocks.
- Keep questioned, unsupported, disallowed, credited, reimbursed, settled and
recovered amounts separate.
- Do not treat an OIG closure entry as durable capability without later-project
operating evidence.