Source ledger — Federal Reserve Non-Core Initiative Governance

Full saved reading

View cited sources (4)

These are the sources cited by this reading. Each source keeps its own date and scope.

Optional file downloads
For AI readers: complete text and record details

Saved research reading. Its original dates and claim limits control; the export date does not refresh the evidence.

Source ledger — Federal Reserve Non-Core Initiative Governance

> Later check — November 23, 2026: Dated return. GSA publicly confirmed its announced project role on October 1. The November 9 OIG management-challenges report continues the renovation warning and identifies forecasting/modeling modernization as a concrete next-project risk. No completed independent cost audit, signed ceiling, quantified recovery, issued agency-wide framework, demonstrated first reuse or closure was located; Oversight.gov lists all seven recommendations open. The September baseline and proof-gate states below retain their original clocks.

Research ID: federal-reserve-noncore-initiative-governance-2026

Cutoff: 2026-09-30 EDT

This ledger records what each source can prove. It does not promote an

announcement, recommendation or accounting aggregate into a later operating

state.

Primary sources

1. Federal Reserve OIG Report 2026-FMIC-B-016

- Source: *Evaluation of the Eccles-1951 Renovation Project Management and Construction Costs*, September 29, 2026

- Controls: project chronology; budget and package evidence; CMAR/GMP

execution; governance and reporting findings; seven recommendations; Chairman

Warsh's attached response; the Board-as-nonexpert-owner diagnosis; planned IT

modernization as a future relevance point.

- Does not prove: final cost reasonableness; amount of avoidable loss; signed

GMP; completed independent audit; recovered amount; issued agency policy;

successful IT-modernization application; durable closure.

2. Board of Governors 2025 and 2024 financial statements

- Source: OIG Report 2026-FMIC-B-003, March 12, 2026

- Controls: Board entity and U.S. GAAP boundary; year-end 2025 and 2024

aggregate construction-in-process balances; capital expenditures; property

accounting policy; financial-statement audit opinion and internal-control

reporting.

- Does not prove: Eccles-1951-only cost; vendor, trade, package or cost-code

detail; value for money; contract compliance; paid-but-unreceived services;

exact placed-in-service classification.

3. Board of Governors 2023 and 2022 financial statements

- Source: OIG Report 2024-FMIC-B-002, March 11, 2024

- Controls: earlier aggregate construction-in-process balances used to build

the 2022–2025 accounting trend.

- Does not prove: project-level or vendor-level lineage.

4. Board Acquisition Policy

- Source: Board of Governors Acquisition Policy

- Controls: the Board's published procurement posture and current public

acquisition-policy surface.

- Does not prove: the specific Eccles-1951 contract, an operative post-OIG

framework or application to IT modernization.

Current evidence-state ledger

PropositionStateControlling source
The Board failed to execute the Eccles-1951 CMAR contract effectivelyobserved findingOIG Report 2026-FMIC-B-016
The Board should treat itself as a nonexpert owner for certain non-core initiativesobserved OIG institutional diagnosisOIG Report 2026-FMIC-B-016
Seven corrective recommendations were issuedobservedOIG Report 2026-FMIC-B-016
Warsh concurred and directed GSA, audit, GMP, metrics and remediesdirectedManagement response attached to OIG Report 2026-FMIC-B-016
GSA holds an operative delegated Project Executive mandatenot yet established separatelyReturn gate
An independent auditor has been selected and engagednot establishedReturn gate
Awarded costs have been independently validatednot establishedReturn gate
A project-level GMP or enforceable substitute has been signednot establishedReturn gate
The Board has recovered cash or obtained a project creditnot establishedReturn gate
The Board has issued the agency-wide frameworknot establishedReturn gate
The framework governs planned IT modernizationnot establishedReturn gate
The recommendations are closed and the capability is durablenot establishedReturn gate

Required source types for the next update

Prefer, in order:

1. OIG recommendation-follow-up or closure evidence;

2. signed Board/GSA authority, governance or interagency instrument;

3. procurement award or audit engagement record;

4. independent audit report and management response;

5. executed contract modification, GMP or fee cap;

6. Board policy, committee charter, RACI, KPI or dashboard;

7. contract demand, modification, credit, settlement or payment record;

8. audited financial statements and notes;

9. project-ledger, CIP or placed-in-service reconciliation; and

10. IT-modernization budget, charter, procurement or assurance record showing

actual reuse of the framework.

Source-handling rules

- Keep Board, GSA, contractor, auditor and OIG statements attributed to the

issuing actor.

- Preserve original and current budget and schedule measures together.

- Keep award, invoice, accrual, cash payment, CIP, placed-in-service transfer and

depreciation on separate clocks.

- Keep questioned, unsupported, disallowed, credited, reimbursed, settled and

recovered amounts separate.

- Do not treat an OIG closure entry as durable capability without later-project

operating evidence.