Federal Reserve Eccles-1951 OIG evaluation

Report date: 2026-09-29

Evidence cutoff: 2026-09-30 EDT

Later bounded return: November 23, 2026 EDT; see the dated check below. The September findings and accounting vintages above retain their original clocks.

Status: current Workbench research

Owner: fed-clearing-treasury

Scope: The Federal Reserve OIG's evaluation of management, governance,

contract execution, cost growth, design-feature claims and corrective actions

for the Marriner S. Eccles and 1951 Constitution Avenue renovation project.

This is not a value-for-money opinion, a criminal investigation or an

independent verification of every awarded cost.

Bottom line

The report closes one allegation and opens a much more concrete institutional

case.

- The OIG found **no reasonable grounds to believe a federal criminal-law

violation occurred that required referral to the Attorney General** and no

Board-policy violation warranting an administrative-misconduct finding.

- The OIG nevertheless found that the Board **did not effectively manage and

execute** the construction-manager-at-risk contract. The Board failed to use

the contract's principal cost controls, did not establish an effective cost

ceiling and governed a multibillion-dollar project through an insufficient

oversight structure.

- The construction budget rose from **$921,000,000 in February 2020 to

$2,018,000,000 in December 2024, an increase of $1,097,000,000**, or about

119 percent. The broader renovation-project budget rose from

$1,317,000,000 to $2,381,000,000. A January 2026 contractor proposal put

construction at $2,135,000,000, but the Board still had not agreed to a

guaranteed maximum price as of July 2026.

- The report does not conclude that the final project cost is reasonable or

unreasonable and does not quantify how much of the increase was caused by

mismanagement. It identifies contributing causes and missed controls.

- Inflation, site conditions, limited competition and design changes all

mattered. But the OIG rejected inflation as a sufficient explanation for the

scale of the largest increases.

- Marble, fountains, the garden terrace, skylights, glass atria, private dining

language and the chairman's elevator were **not material drivers of the cost

increase**. The OIG found that these features were already in the design that

supported the initial budget; beehives were never part of this project.

The decisive plotline is therefore not criminal luxury spending. It is that a

self-funded federal agency chose a contract meant to transfer cost risk and then

administered it in a way the OIG says resembled **uncapped cost-plus,

pay-as-you-go construction**.

The four separate clocks

ClockCurrent stateWhat it does not establish
CriminalThe April 2026 Justice Department probe was closed; the OIG found no reasonable grounds for a criminal referralNo acquittal after a merits trial; no approval of project management
Administrative misconductOIG found no Board-policy violation warranting an administrative-misconduct findingNo finding that management was effective
Audit and managementOIG found repeated contract-execution, cost-control, governance and reporting deficiencies and issued seven recommendationsOIG did not price the avoidable loss or rule on overall cost reasonableness
Corrective operationChairman Kevin Warsh concurred and directed GSA project leadership, an independent cost audit, GMP negotiations, fixed metrics, contract reconciliation and possible remediesA direction is not completed implementation, a recovered dollar or a final cost ceiling

What the budget figures mean

The OIG distinguishes the renovation budget from the broader multicycle capital

budget. These figures should not be collapsed.

ObjectFebruary 2020Latest approved figure in the reportLater proposal or state
Construction portion$921,000,000$2,018,000,000, approved December 2024$2,135,000,000 contractor GMP proposal in January 2026; not agreed as of July 2026
Eccles-1951 renovation project$1,317,000,000$2,381,000,000, approved December 2024OIG describes this as the most recently revised renovation budget
Multicycle capital budget that contains the project$1,378,000,000$2,455,000,000, approved in 2024Includes acquisition and other project-related capital objects beyond the OIG's narrower renovation-budget line

The OIG also reports that construction was expected to finish in the second

quarter of 2024 under the 2020 plan. By August 2026, the expected construction

completion date was December 2027.

The balance-sheet bridge

The Board's own audited financial statements already show the accounting trail

that the awarded-cost audit can penetrate. This is the **Board of Governors'

balance sheet**, not a Reserve Bank balance sheet. The Board prepares it under

U.S. GAAP on an accrual basis.

Year-endBoard construction in processAnnual increase
2022$132,535,471—
2023$357,260,135$224,724,664
2024$721,702,038$364,441,903
2025$1,239,980,443$518,278,405

The balance increased $1,107,444,972 from year-end 2022 through year-end

2025. The 2025 statements define construction in process as costs incurred for

long-term building enhancements for assets that have not entered productive

Board service. They separately report $527,426,113 of 2025 capital

expenditures and $343,298,787 in 2024.

These public figures are aggregate Board accounts, not an Eccles-1951

subsidiary ledger. They should not be treated as exact project spend: other

long-term building enhancements, accruals, retainage and timing differences may

also be present. The proximity is nevertheless important. The Board reported

$721,702,038 of total construction in process at year-end 2024, while its

2025 capital budget reported $701,600,000 of cumulative Eccles-1951 spending

through that same date. The $20,102,038 difference is a reconciliation

question, not permission to equate the two measures.

The audit can expose the missing chain beneath the aggregate line:

> contract and subcontractor → price package → invoice or pay application →

> cost code and project ledger → accrued or retained amount → construction in

> process → placed-in-service component → fixed-asset subsidiary record →

> useful life and depreciation

That chain can identify which entity supplied plumbing, HVAC, electrical,

earthwork, masonry and other components; what the Board capitalized; what it

expensed; whether paid or accrued services were actually received; and how the

completed project is divided among buildings, improvements, equipment and

other depreciable components. The published financial statements reveal only

the aggregate construction-in-process line. The independent audit, contract

audit files, project cost ledger, pay applications, retainage schedules and

eventual placed-in-service entries are the potential route to the actual fixed

asset listing.

The Board's 2025 financial-statement auditor issued an unmodified opinion and

reported effective internal control over financial reporting. That opinion

addresses whether the statements are materially fairly presented; it is not a

vendor-level value-for-money opinion and does not answer whether individual

awards were well competed or contract services were received.

The contract failure

Intended model

The Board chose construction manager at risk (CMAR). In a normally managed

CMAR project:

1. the construction manager joins during design;

2. the manager supplies evolving whole-project estimates;

3. owner, designer and manager use those estimates to keep design within a

stated cost limit;

4. the parties establish a guaranteed maximum price (GMP) near the start of

construction or substantial design completion; and

5. the manager then bears material cost and schedule risk above that ceiling,

subject to defined exceptions.

Actual execution

The Board did not obtain the expected risk transfer.

- The CMc was hired in March 2022, after two design phases were complete.

- The solicitation required prices for only $1,491,543 of preconstruction

services and general conditions, not an estimate for the full construction

scope. Modifications later increased the contract above $2,000,000,000.

- The project team set an $857,000,000 stated cost limitation in April 2020

but did not keep it current, require the architect to design within it or tell

the CMc and owner representative about it.

- Contract provisions called for three detailed CMc estimates as design

evolved. The Board did not formally request a whole-project estimate until

December 2025, after more than $2,000,000,000 of work had been awarded.

- The Board determined design was substantially complete in January 2025 but

still had no agreed GMP in July 2026.

- Instead of several large phases or one project ceiling, the Board divided

virtually all work into 84 limited-scope price packages.

- The CMc received a fee equal to 2.95 percent of construction cost without

a project-level cap. That reduced the incentive to restrain total cost.

The OIG's core judgment is functional: accumulating scores of awards without an

overall ceiling made the arrangement resemble a higher-risk cost-plus

reimbursement contract even though the contract form was CMAR.

The package and competition evidence

By December 31, 2025, the Board had awarded 69 price packages with an initial

award value of $1,978,398,480. The contractor's January 2026 proposal showed

those packages finishing $26,600,000 below the award total: the Board would

receive $21,600,000 and the CMc the contractually capped $5,000,000 share

of savings. Fifteen remaining packages were then valued at $62,891,943.

That package-level underrun does not answer whether the total project was well

priced. The ceiling was never set before the packages established the price.

Including change orders, the OIG compared $2,078,000,000 of awarded

construction work through December 2025 with the architect's March 2022 estimate

of $1,117,000,000 for the same packages: a $960,000,000 increase.

The sharpest example is mechanical, electrical and plumbing (MEP):

MEP objectEarlier estimateAwardIncrease
Core and shell MEP$178,000,000 in March 2022$539,000,000 in July and October 2023$361,000,000 / 203%
Interior fit-out MEP$28,000,000 in March 2022$155,000,000 in June 2025$127,000,000 / 454%
All four MEP packages$206,000,000$694,000,000$488,000,000 / 237%

Three of the four MEP packages did not receive the contract's preferred minimum

of three bids. Those three packages totaled $624,000,000. The construction

manager documented limited availability, but the Board did not ask its separate

owner representative to produce an independent estimate or validate the large

variance. Staff told the OIG they prioritized keeping the schedule moving.

What drove the increase

Seven construction categories explain $799,000,000, or 83 percent, of the

OIG's $960,000,000 estimate-to-award increase.

CategoryMarch 2022 estimateAwarded costIncreaseIncrease %
Plumbing and HVAC$107,000,000$346,000,000$239,000,000223%
Electrical$91,000,000$252,000,000$161,000,000177%
Earthwork$49,000,000$158,000,000$109,000,000222%
Wood, plastics and composites$16,000,000$110,000,000$94,000,000588%
Metals$32,000,000$104,000,000$72,000,000225%
Masonry$41,000,000$108,000,000$67,000,000163%
Concrete$65,000,000$122,000,000$57,000,00088%
Total$401,000,000$1,200,000,000$799,000,000199%

The nationwide PPI for new office construction rose about 24 percent from March

2022 to January 2026. The OIG cautions that a national index cannot price a

unique historic Washington project. It uses the comparison only to show that

inflation alone cannot explain increases ranging from 88 to 588 percent.

The report identifies several interacting causes:

- post-pandemic labor, material and supply-chain inflation;

- limited subcontractor competition and segmentation that may have discouraged

bidders, lost bulk-purchasing economies and produced modification premiums;

- excavation beside a high water table, unstable soil and contamination;

- more hazardous-material abatement than expected;

- historic-preservation and security constraints;

- delayed and changing design; and

- contract and governance decisions that left the Board exposed to these

risks.

The major owner-directed change occurred in January 2023, after construction

began: the Board shifted the interior fit-out from predominantly open workspace

to predominantly closed offices. That delayed interior-design completion by

21 months, until October 2024, and overall substantial design completion until

January 2025. The delay postponed the planned fall 2023 GMP and extended the

project's exposure to inflation and redesign costs.

Why the “luxury” case is not the OIG case

The OIG checked eight criticized features against the November 2019 initial

plan and the May 2021 final plan. All were already part of those plans and did

not materially explain later increases.

FeatureOIG finding or available cost
Chairman/private elevatorExisting pre-renovation feature; serves multiple floors, with controlled access at the governors' floor
Private dining spacesDesign language also describes conference rooms; Board says they are multiuse, not governor-only
Water featuresFour historic Eccles fountains remain; four new 1951 fountains were removed in June 2025 because of expected criticism; GMP proposal showed $3,400,000 for water features
MarbleMostly restoration: project team said 87% restored and 13% new; $107,900,000 masonry category includes much more than marble
Garden terraceDescription includes original planter boxes and the south lawn over the new garage
Vegetated roofsEstimated at $615,000 and intended for energy, stormwater and roof-life benefits
Glass atriaTwo scaffolding components cost $6,000,000 in the proposal
SkylightsProposal showed $27,600,000, including restoration of the historic Eccles skylight
BeehivesNot part of the Eccles-1951 project

This does not mean every feature was wise or cheap. It means the OIG found the

headline features were not material causes of the billion-dollar construction

increase.

The governance failure

The Board of Governors approved the annual operating and capital budgets but,

under delegated administrative authority, did not manage daily execution. The

Committee on Board Affairs advised the Board and presented budgets but had no

project-level decision role. Facility Services held primary execution

responsibility, with procurement, financial-management and executive groups

supporting or receiving updates.

The OIG found that this structure did not match the project's risk:

- no fixed project-level cost or schedule success measure;

- unclear oversight roles and accountability;

- a narrow RACI matrix that escalated specified change events but generally did

not require senior review of in-scope awards, even when those awards exceeded

estimates by more than $100,000,000;

- a trust-based posture in which senior officials avoided second-guessing the

project team; and

- quarterly dashboards that repeatedly called the project on track because

the reference budget and schedule were reset to the latest approved numbers.

The dashboards did label the budget at risk for four consecutive quarters

before the 2025 budget increase. But a moving baseline obscured performance

against the original promise.

This closely repeats the prior Martin Building pattern. Earlier OIG work had

already identified weak preplanning, unreliable estimates, unused cost controls,

incomplete status reporting and unclear governance. All 11 earlier

recommendations were formally closed, yet several control failures recurred.

Closure of a recommendation therefore did not prove that the underlying

management capability had become durable.

The seven OIG recommendations

The OIG recommends that the chairman or a designee:

1. negotiate a GMP or determine another way to secure best value for project

completion;

2. set fixed project-cost and schedule-success metrics;

3. cap the CMc fee as the contract provides;

4. strengthen governance with a responsible oversight body, clear reporting

lines and defined Board/Committee on Board Affairs reporting;

5. exercise the contract audit clause and validate awarded costs, allowances,

contingencies, fees and savings;

6. reconcile CMAR and CMOR requirements against services received and consider

reimbursement for paid-but-unreceived services; and

7. create an agency-wide framework for future significant initiatives,

including full-scope budgets, stated cost limits, metrics, accountability,

escalation rules and independent senior oversight.

The OIG will follow up quarterly. Recommendation issuance is not closure.

Warsh's response and the operating-control shift

Chairman Kevin Warsh concurred with the findings and all recommendations in a

September 29 response attached to the report. His letter directs:

- GSA to serve immediately as Project Executive, reporting to the Board of

Governors and the chair;

- an independent audit of the accuracy and compliance of all awarded costs;

- prompt GMP negotiations;

- fixed budget and schedule metrics;

- a GSA-assisted review of project contracts and the value of services not

received;

- reimbursement or project credits where warranted; and

- permanent internal standards for future major initiatives.

This is a substantive state change in the control plane. It brings GSA—the

executive branch's ordinary federal-property specialist—into project execution

even though the Board's special statutory property authority and ownership do

not disappear. It is not yet evidence of a signed GMP, completed audit,

validated final cost, recovered funds or on-time completion.

Plotline significance

The report sharpens the earlier self-funding and real-estate map in four ways.

1. Insulation reached administration, not only monetary policy. The Board's

special purse and property authority permitted a large ordinary construction

project to sit outside the normal appropriations/FAR/GSA chain.

2. Retrospective oversight worked, but late. OIG reconstructed the failure

after most work had been priced and more than $2,000,000,000 awarded.

3. The control response partially imports the missing outside discipline.

Warsh's GSA Project Executive, independent audit and fixed metrics insert

external construction competence without Congress first rewriting the

Federal Reserve Act.

4. Legal vindication and management accountability diverge. Powell and

staff were not found criminally or administratively culpable; the institution

was still found to have governed the project badly.

The live question is no longer whether the OIG will rule. It is whether the

Board and GSA turn the recommendations into enforceable ceilings, verified

costs, contract remedies and a durable governance framework.

Return gates

TriggerRequired proofBoundary
GMP finalized or formally rejectedSigned agreement or Board/GSA decision identifying the final cost-control substituteA January 2026 proposal is not an agreed ceiling
Independent audit completedAudit report, tested population, exceptions and quantified questioned costsEngagement announcement is not validation
Contract remedies pursuedDemand, credit, reimbursement, settlement or adjudicated recovery“Will seek” is not a recovered dollar
Fixed metrics adoptedNamed budget baseline, schedule baseline, change protocol and reporting ownerAnother rebased dashboard is not original-baseline accountability
OIG recommendation closureRecommendation-by-recommendation evidence accepted by OIGManagement concurrence is not closure
Construction completionSubstantial-completion and acceptance recordsDecember 2027 remains a forecast
Final project costFinal contract reconciliation, all packages, changes, fees, credits and closeoutApproved budget, awarded amount, invoice, cash payment and final cost remain separate
Durable governance reformIssued agency policy and application to another significant initiativeA renovation-only workaround is not institutional learning

Primary source

- Federal Reserve OIG, *Federal Reserve: Evaluation of the Eccles-1951 Renovation Project Management and Construction Costs*, Report 2026-FMIC-B-016, September 29, 2026

- Federal Reserve OIG, *Board of Governors Financial Statements as of and for the Years Ended December 31, 2025 and 2024*, Report 2026-FMIC-B-003, March 12, 2026

- Federal Reserve OIG, *Board of Governors Financial Statements as of and for the Years Ended December 31, 2023 and 2022*, Report 2024-FMIC-B-002, March 11, 2024

- Federal Reserve Non-Core Initiative Governance 2026/README.md

- FEDERAL_RESERVE_SELF_FUNDING_AND_REAL_ESTATE_CONTROL_MAP.md

- FEDERAL_RESERVE_PURSE_AUDIT_AND_STOPPING_POWER_MAP_2026-09-20.md

- FED_NAMED_CAPITAL_AND_TECHNOLOGY_COUNTERPARTY_LEDGER.md

- FEDERAL_RESERVE_USES_OF_MONEY_LEDGER_2025.md

November 23, 2026 return — has the cost audit appeared?

Disposition: dated extension; no completed corrective-action proof gate crossed in the public sources reviewed. The September 29 OIG evaluation exists, but the separate independent audit of awarded costs promised in the chairman's response was not located. Neither an auditor engagement nor a public delivery deadline was established. This does not establish that internal work has not begun.

What appeared after our September check

- October 1 — GSA confirmed its announced project role. Its official release says it will serve as Project Executive and supplies Administrator Forst's support. This corroborates the participating agency's commitment; it does not disclose a signed interagency instrument, detailed decision rights, audit engagement or completed cost validation. The October 20 page-update stamp is not a new project milestone.

- November 9 — the OIG issued a later management-challenges report. *2026–2027 Major Management Challenges*, printed pages 9–10, keeps the renovation among the Board's major infrastructure challenges and repeats the contract-execution and cost-management failures. It is a later warning and institutional-risk assessment, not the independent cost audit or a recommendation-closure report. Its December 2027 construction forecast is expressly an August 2026 schedule state; its rounded $2.4 billion budget is not a newly validated final cost.

- The next-project connection is more concrete. The November report identifies the economic forecasting and modeling modernization effort, approved at $500 million in 2024. It says the initiative is no longer reflected in the multicycle budget because the Board is in the process of contracting with a third party for a comprehensive cost estimate. That is an estimating/procurement step, not a completed estimate, canceled program, issued Recommendation 7 framework or proof that the framework has been used. The OIG expressly warns that the initiative could create similar cost and schedule risks. This continues our existing institutional-learning watch; it does not establish a second failed project.

Where our return points stand

Return pointPublic evidence checked November 23
Independent awarded-cost auditNo engagement record or completed result located in the reviewed sources
Signed guaranteed maximum price, enforceable substitute or fee capNo later executed instrument located
Fixed cost/schedule metrics and oversight charterNo later operative record located
Contract reconciliation, reimbursement or project creditsNo quantified result located
Project/vendor ledger, CIP reconciliation or placed-in-service accountingNo later project-level reconciliation located; historical Board financial statements remain aggregate
Agency-wide framework and first reuseNo issued framework or demonstrated reuse located; November report adds a concrete modernization risk/estimating context
OIG closureOversight.gov's report record, retrieved November 23, lists all seven recommendations open; no separately dated closure evidence located

The public OIG issued-report list still contains the September 29 renovation evaluation and no later renovation-specific report. The ongoing-work list describes its contract-invoice audit as nonconstruction work; it is not the promised renovation cost audit.

The open-recommendations release is dated October 27, but its underlying PDF is a September 30 snapshot. Its detailed table covers recommendations issued through March 31 and open over six months. The absence of Eccles from that table therefore proves no closure. Oversight.gov's listing is the retrieved public status, not proof of real-time internal progress. Its $0 questioned-cost field does not validate all costs or establish zero avoidable loss.

The Board's building FAQ, last updated September 30, still quotes a $2.46 billion approved budget; that is neither a new November cost measurement nor final spend. The public Acquisition Policy retains its October 7, 2020 update date and does not supply the promised new significant-initiative framework.

Timing: November 23 is 55 days after the report. The OIG promised quarterly follow-up, not a quarterly public-report deadline or an audit completion date. Our existing December 31, 2026 project return remains useful; the March 31, 2027 institutional-learning return also remains open, with earlier return on an actual publication. Neither date is an official audit deadline.

Integration: existing owners fed-clearing-treasury and federal-reserve-noncore-initiative-governance-2026; existing threads eccles-renovation and fed-noncore-project-framework. The live register and crosswalk have no current story-file pointer for either thread. Retain this extension in the existing owners; create no story merely for filing. September visual and financial baselines remain unchanged. Return checks and Catalog component note updated; no app installation, public release, schedule change or Git write performed.