Meta’s Richland Parish campus power and financing
Full saved reading
View cited sources (13)
These are the sources cited by this reading. Each source keeps its own date and scope.
- Commission order
- Commission meeting, p. 5
- Franklin Farms groundbreaking
- Construction power
- Entergy 2025 filing
- Application
- Procedural order
- Entergy filing, pp. 18–19 and 130–131
- Louisiana update
- Venture announcement
- Meta 2025 Form 10-K, Note 5
- Meta September 2026 Form 10-Q, Note 5
- Louisiana expansion announcement
Saved research reading. Its original dates and claim limits control; the export date does not refresh the evidence.
Saved source details
---
title: Meta’s Richland Parish campus power and financing
research_id: us-inbound-investment-industrial-capex
artifact_role: answer
status: current
evidence_cutoff: 2026-11-10
---
Meta’s Richland Parish campus power and financing
Approved utility capacity and work underway
The Louisiana Public Service Commission voted on August 20, 2025 and issued Order U-37425 on August 29. It certified Entergy Louisiana’s three proposed gas generation facilities totaling 2,262 MW and associated transmission resources for the utility system. Laidley LLC is the Meta subsidiary named for the original customer project. The resource approval and Laidley’s private service agreement have separate scopes. On December 1, Entergy reported breaking ground on the first two facilities, Franklin Farms Units 1 and 2, totaling approximately 1,500 MW and targeted for late 2028. The third facility, Waterford 5 in Killona, was targeted for 2029 in Entergy’s 2025 filing. The completed upgrade described by Entergy in April 2025 was designed to help provide 10 MW for construction. Metered campus load and commercial operation of the new generators remain unverified. Commission order · Commission meeting, p. 5 · Franklin Farms groundbreaking · Construction power · Entergy 2025 filing
Entergy signed a separate conditional service agreement with Evest LLC, another Meta subsidiary, in March 2026. The follow-on application in U-37882 proposes seven gas units totaling 5,278 MW, with four near the customer in Richland Parish and three in Pointe Coupee Parish. Entergy’s November 2 filing reports that the October hearing occurred and that Entergy reached a proposed settlement with commission staff and one intervenor. Commission certification was still pending in that filing and the procedural order scheduled December 16 consideration. Entergy estimates service for the units in 2030 and 2031. Louisiana’s November 9 update still described Hyperion as under construction. Application · Procedural order · Entergy filing, pp. 18–19 and 130–131 · Louisiana update
Campus financing and the announced expansion
Meta and funds managed by Blue Owl Capital entered their Hyperion joint venture on October 21, 2025. They disclosed an 80% Blue Owl funds and 20% Meta ownership split, pro rata commitments against approximately $27 billion in estimated development costs, and about $7 billion in Blue Owl funds’ cash contributed at formation. Meta’s 2025 filing reports a $4.30 billion net asset contribution and a $2.55 billion distribution to Meta. The distribution is the audited filing’s more precise figure for the same distribution that the announcement described as about $3 billion. Meta’s September 2026 filing still gives $27 billion estimated development costs and 2029 Louisiana lease commencement. The venture estimate, investor cash and cash distributed to Meta describe different things. Venture announcement · Meta 2025 Form 10-K, Note 5 · Meta September 2026 Form 10-Q, Note 5
The July 13, 2026 Louisiana release and Meta’s expansion announcement put the wider expansion at more than $50 billion and 5 GW of planned IT capacity. That IT capacity has a different measurement from the utility packages’ generation ratings. Entergy Louisiana disclosed two $500 million mortgage-bond issues in August 2026 with multiple uses, including potential funding for both groups of plants. The filing identifies spending across several projects and leaves the exact allocation to each project open. Neither the full expansion funding allocation nor commercial delivery of the proposed generation was established. Louisiana expansion announcement · Entergy filing, Note 4 and Entergy Louisiana cash flow discussion
Earlier source routes are the July investment ledger and the August turbine buildout ledger.