Where does each FORTRESS America base project stand on the proof ladder? — saved evidence, page 1

Saved evidence through 2026-09-30. This table projects the linked graphic data; it does not refresh the underlying research.

Return to the graphic · Complete saved JSON

Rows 1–20 of 29. Page 1 of 2.

Section context and qualifications
Uncertainty
  • A stated 14- or 21-day design capability is not an observed test; the package says an independence claim is only as strong as its load boundary, duration and operating-test record.
  • The projects have different boundaries (full base, critical load, a gate, a tenant facility), so they are not counted toward one readiness score.
  • The full saved FORTRESS source ledger is available. It lists controlling, framework and project sources with their authority, access state and limits; the signed memorandum remains under the September 30 access hold.
  • Source gap (package README): The official release links the signed memorandum, but the publisher PDF was not retrievable through the available browser, HTTP or PDF-reader paths on September 30. Search indexing exposed the memorandum text and a secondary mirror reproduced it, but this package keeps the memorandum in official_link_access_hold state. The accessible official release controls the confirmed public announcement; memorandum-only wording must be rechecked against the signed PDF before quotation.
  • Candidate primary source, not yet checked: 10 U.S.C. §2920 (https://www.govinfo.gov/link/uscode/10/2920)
SectionRecordSaved detailsSources and dates
How far each project has been provedProgram direction
Value
1
Display
1
For this row’s sourcing, see the saved details, section context and linked research.
How far each project has been provedSelection / negotiation
Value
4
Display
4
For this row’s sourcing, see the saved details, section context and linked research.
How far each project has been provedPrototype lane
Value
1
Display
1
For this row’s sourcing, see the saved details, section context and linked research.
How far each project has been provedOperational description
Value
4
Display
4
For this row’s sourcing, see the saved details, section context and linked research.
How far each project has been provedIsland test observed
Value
1
Display
1
For this row’s sourcing, see the saved details, section context and linked research.
The proof ladder6
Step
Text
P0 · Direction
Minimum record
Text
Official direction or program announcement.
Where fortress sits
Text
FORTRESS America is here: a real program exists, but implementation is not yet fixed.
For this row’s sourcing, see the saved details, section context and linked research.
The proof ladder7
Step
Text
P1 · Scope fixed
Minimum record
Text
Named installation, electrical boundary, mission loads, duration and performance standard.
Where fortress sits
Text
This is the first missing FORTRESS-wide receipt.
For this row’s sourcing, see the saved details, section context and linked research.
The proof ladder8
Step
Text
P2 · Authority and money fixed
Minimum record
Text
Appropriation, obligation or executed agreement naming the accountable owner and operator.
Where fortress sits
Text
Conditional selection and FYDP alignment do not reach this state.
For this row’s sourcing, see the saved details, section context and linked research.
The proof ladder9
Step
Text
P3 · Design and permission fixed
Minimum record
Text
Accepted architecture, interconnection, cyber controls and required license or authorization.
Where fortress sits
Text
A vendor pairing or notice to negotiate remains earlier than this state.
For this row’s sourcing, see the saved details, section context and linked research.
The proof ladder10
Step
Text
P4 · Built
Minimum record
Text
Physical completion with material deficiencies identified or closed.
Where fortress sits
Text
Construction completion still does not prove integrated operation.
For this row’s sourcing, see the saved details, section context and linked research.
The proof ladder11
Step
Text
P5 · Commissioned
Minimum record
Text
Accepted integrated system delivering power to its defined loads.
Where fortress sits
Text
Yuma, New London, McCoy and Sigonella have public operating descriptions with different boundaries.
For this row’s sourcing, see the saved details, section context and linked research.
The proof ladder12
Step
Text
P6 · Island tested
Minimum record
Text
Observed no-grid start, transfer and carriage of a defined load.
Where fortress sits
Text
Miramar has public mission-critical islanding evidence; that is not automatically a full-load endurance test.
For this row’s sourcing, see the saved details, section context and linked research.
The proof ladder13
Step
Text
P7 · Endurance and recovery tested
Minimum record
Text
Required load carried for the required duration, followed by safe recovery or resynchronization.
Where fortress sits
Text
Stated 14- or 21-day design capability is not the same as an observed test.
For this row’s sourcing, see the saved details, section context and linked research.
The proof ladder14
Step
Text
P8 · Recurring readiness
Minimum record
Text
Repeated exercise, maintenance, fuel, staffing and exception evidence.
Where fortress sits
Text
This is the durable portfolio outcome FORTRESS ultimately needs.
For this row’s sourcing, see the saved details, section context and linked research.
Project by project · Program directionFORTRESS America
Sub
central Department program; office directed under USW(A&S)
Badge
Text
Program direction
Where the public record stops
Site list, definition and funding unresolved
Public state
established
Load and duration
every major installation; “independent power” undefined
Next decisive record
office, charter, site list, technical standard and budget
For this row’s sourcing, see the saved details, section context and linked research.
Project by project · Selection / negotiationArmy SCI energy
Sub
private developer on Army land; emergency priority by agreement
Badge
Text
Selection or negotiation
Where the public record stops
Six conditional pairings
Public state
six conditional selections
Load and duration
solicitation says island within qualifying outage and support installation ≥14 days
Next decisive record
executed EUL/PPA, financing close, interconnection and test
For this row’s sourcing, see the saved details, section context and linked research.
Project by project · Selection / negotiationArmy Janus
Sub
contractor-owned/operated reactors
Badge
Text
Selection or negotiation
Where the public record stops
Pairings and planned 2028 deployment
Public state
five vendor site pairings selected
Load and duration
site requirements not equal to full-base load by announcement alone
Next decisive record
design/authorization, construction, criticality and power delivery
For this row’s sourcing, see the saved details, section context and linked research.
Project by project · Selection / negotiationNWS Crane MMR
Sub
planned commercial owner/operator; Navy host with Army Janus and department partners
Badge
Text
Selection or negotiation
Where the public record stops
Pairings and planned 2028 deployment
Public state
deployment announced for 2028
Load and duration
critical operations; announcement does not establish full-installation load
Next decisive record
executed agreement, authorization, design, construction, criticality and accepted delivery
For this row’s sourcing, see the saved details, section context and linked research.
Project by project · Selection / negotiationEielson microreactor
Sub
proposed private vendor under long-term service arrangement
Badge
Text
Selection or negotiation
Where the public record stops
Notice of intent; up to 5 MW critical load
Public state
notice of intent negotiation
Load and duration
up to 5 MW to critical infrastructure
Next decisive record
final award, NRC licence, construction and operation
For this row’s sourcing, see the saved details, section context and linked research.
Project by project · Prototype laneProject Pele
Sub
government prototype/test at INL
Badge
Text
Prototype lane
Where the public record stops
INL demonstration, not base service
Public state
prototype demonstration path
Load and duration
technology demonstration, not base service
Next decisive record
fueled criticality, output and published test result
For this row’s sourcing, see the saved details, section context and linked research.