--- title: "Wave 1 Project Ledger — Investment Claims to Funding Evidence" status: current artifact_role: source-bearing project ledger evidence_cutoff: 2026-07-31 --- # Wave 1 Project Ledger — Investment Claims to Funding Evidence ## How to read this ledger This is a deliberately **non-additive** first wave. It starts with source-rich projects that illustrate the different capital structures hidden inside public investment rhetoric. The absence of a disclosed facility, lender or draw means `not publicly stated`, not that the project is unfinanced. `Funding evidence` reports only what the linked source supports. Public awards are not cash receipts, and parent-level funds are not automatically allocated to the named asset. See [`CLAIM_RECONCILIATION_PROTOCOL.md`](CLAIM_RECONCILIATION_PROTOCOL.md) for non-addition rules and [`RESEARCH_DESIGN_AND_EVIDENCE_STANDARD.md`](RESEARCH_DESIGN_AND_EVIDENCE_STANDARD.md) for the evidence ladder. ## Semiconductors and advanced manufacturing | ID | Project / claim | Object and project state | Funding evidence located | Open proof / source | |---|---|---|---|---| | F-01 | TSMC Arizona — $165B planned U.S. investment | Multi-fab sponsor program; Fab 1 high-volume production end-2024, Fab 2 under construction, Fab 3 construction began 2025. | Up to $6.6B CHIPS direct funding; eligibility for up to $5B Commerce loans; $8B TSMC Arizona notes outstanding at 2025 year-end, parent-guaranteed. This does not evidence that the full $165B is closed or drawn. | Allocate sponsor equity, federal draws, customer support and notes to each fab. [20-F](https://www.sec.gov/Archives/edgar/data/1046179/000162828026025362/tsm-20251231.htm) | | F-02 | Micron — about $200B U.S. manufacturing and R&D plan | Twenty-year, multi-site parent program: Boise, Clay and Manassas. New York first concrete July 2026; Idaho first fab expected mid-2027. | Up to $6.1B CHIPS direct funding for two Boise and two Clay fabs plus $275M Manassas award; milestone based, not up-front cash. | Site-specific debt/equity and award disbursements not public. [Release](https://investors.micron.com/node/48921); [agreement disclosure](https://investors.micron.com/static-files/c77da8fc-f61f-4fd1-b064-0ca691a07445) | | F-03 | Samsung Central Texas — more than $37B | Multi-asset Taylor/Austin program; Taylor construction continued in 2025, target operational end-2026. | Up to $4.745B CHIPS direct funding, milestone payable; Taylor initial minimum investment reported as $17B. | Sponsor debt/equity, draws and allocation among assets not public. [Award](https://www.commerce.gov/news/press-releases/2024/12/biden-harris-administration-announces-chips-incentives-award-samsung); [update](https://semiconductor.samsung.com/sas/local-news/samsung-austin-semiconductors-two-campuses-inject-10-9b-into-central-texas-economy-in-2025/) | | F-04 | Amkor Peoria, Arizona — $7B two-phase campus | Specific advanced-packaging campus; groundbreaking 2025, first production expected 2028. | Up to $407M CHIPS direct funding, conditional on milestones; tax-credit and state/local incentives named but not fully quantified. | Sponsor debt/equity, actual award draws and customer contracts not public. [10-Q](https://ir.amkor.com/static-files/78e5c35d-9ea5-4399-8c4c-da9b0f96e828); [release](https://ir.amkor.com/news-releases/news-release-details/amkor-technology-breaks-ground-new-semiconductor-advanced) | | F-05 | Hyundai Motor Group — $21B, 2025–28 | Parent allocation: $9B auto, $6B parts/logistics/steel and $6B future industry/energy; no single borrower. | Sponsor release states categories and horizon; no project debt facility or full capital-stack record. | Start with each legal entity/site; distinguish group cash from local project debt. [Release](https://www.hyundai.com/worldwide/en/newsroom/detail/hyundai-motor-group-commits-to-us-growth-with-usd-21-billion-investment-0000000918) | | F-06 | BlueOval SK battery plants, Tennessee/Kentucky | Three Ford–SK On JV plants. | DOE closed a direct loan of up to $9.63B, including principal and capitalized interest, to **BlueOval SK LLC**—the JV borrower. | Draw schedule, JV equity, state incentives and actual spend remain open. [DOE close](https://www.energy.gov/edf/articles/doe-announces-963-billion-loan-blueoval-sk-further-expand-us-manufacturing-electric); [project page](https://www.energy.gov/edf/blueoval-sk) | | F-07 | Thacker Pass lithium, Nevada | Phase 1 targets 40,000 tonnes/year battery-grade lithium carbonate. | $2.23B amended DOE construction facility ($1.97B principal plus expected capitalized interest); draws of $435M on 2025-10-20 and $432M on 2026-02-24. JV: 62% Lithium Americas / 38% GM; GM $430M cash + $195M LC; Lithium Americas about $330M cash; GM offtake up to 100% of Phase 1. | Loan closed and drawn; continue draw/use and construction evidence. [2025 10-K](https://www.sec.gov/Archives/edgar/data/1966983/000119312526115081/lac-20251231.htm); [DOE page](https://www.energy.gov/edf/thacker-pass) | | F-08 | MP Materials 10X / Mountain Pass, California | Multibillion-dollar DoD partnership; project cost not audited in reviewed sources. | DoD bought $400M convertible preferred stock; executed $150M heavy-rare-earth-separation loan; 10-year price floor and 10X offtake. JPMorgan/Goldman $1B debt commitment letter; $650M assigned to 10X, but not proof of final facility/draw. | Separate public equity/loan from revenue support and commercial debt commitment. [MP 8-K](https://www.sec.gov/Archives/edgar/data/1801368/000119312525157310/d43796d8k.htm); [DoD loan](https://www.defense.gov/News/Releases/Release/Article/4270722/office-of-strategic-capital-announces-first-loan-through-dod-agreement-with-mp/) | ## Compute and data-center infrastructure | ID | Project / claim | Object and project state | Funding evidence located | Open proof / source | |---|---|---|---|---| | C-01 | Stargate — $500B over four years / 10GW | Parent-program target across variable sites and entities; not one financing close. | Launch names SoftBank, OpenAI, Oracle and MGX as initial equity funders and says $100B would begin deployment. No $500B credit agreement, equity-call schedule or collateral package disclosed. | Site SPV, binding commitments, calls/draws, debt provider, power and lease docs. [Launch](https://openai.com/index/announcing-the-stargate-project/) | | C-02 | Stargate I, Abilene — $15B JV | Flagship build-to-suit; Crusoe affiliates and Longhorn JV 3–8 lease additional buildings to Oracle America. First phase live on Oracle Cloud Infrastructure September 2025. | Blue Owl filings identify equity investments in Longhorn JVs with Crusoe affiliates; Crusoe described a $15B JV with Blue Owl and Primary Digital. | JV agreement, debt/equity split, lenders, lease economics and actual contributions. [Blue Owl filing](https://www.sec.gov/Archives/edgar/data/1944366/000194436625000100/osnl-20250630.htm); [Crusoe update](https://www.crusoe.ai/resources/newsroom/crusoe-announces-flagship-abilene-data-center-is-live) | | C-03 | Vantage Frontier, Texas — more than $25B / 1.4GW | 1,200-acre, ten-data-center campus; construction started, first building H2 2026, phases through 2028. | Prior platform funding: $9.2B equity and a $3B green loan across at least eight North American sites; neither allocated to Frontier. | Project loan/bond/equity, anchor tenants and power-cost allocation. [Frontier](https://vantage-dc.com/news/vantage-data-centers-unveils-plans-for-frontier-a-25b-mega-campus-in-texas-to-meet-unprecedented-ai-demand/); [platform funding](https://vantage-dc.com/news/vantage-data-centers-growth-continued-in-2024-driven-by-ai-and-cloud-adoption-secured-a-record-13-billion-in-incremental-funding/) | | C-04 | CoreWeave Lancaster, Pennsylvania — up to $6B | Proposed data-center equipment/capacity: initial 100MW, potential 300MW. | $2.6B delayed-draw term loan through CoreWeave Compute Acquisition Co. V and VII; filed materials identify it as financing Pennsylvania development. Corporate stack also includes DDTLs, bonds, converts, OEM/software finance, IPO proceeds and customer cash. | FID, loan draws, project allocation, land/lease, construction and offtake. [2025 10-K](https://www.sec.gov/Archives/edgar/data/1769628/000176962826000104/crwv-20251231.htm) | | C-05 | Google PJM region — more than $25B over two years | Regional corporate capex envelope; no individual campus schedule or SPV named. | Alphabet: 2025 capex $91.4B, operating cash flow $164.7B, $37.3B senior-note net proceeds for general corporate purposes. Separate $3B/20-year Brookfield hydro agreement is power support, not project debt. | Sites, equipment/building split, ownership/lease and project allocation. [Announcement](https://blog.google/company-news/outreach-and-initiatives/public-policy/pennsylvania-energy-innovation-summit/); [10-K](https://www.sec.gov/Archives/edgar/data/1652044/000165204426000018/goog-20251231.htm) | | C-06 | Blackstone/QTS Pennsylvania — more than $25B plus $60B "catalyzed" | Fund-managed digital and energy-infrastructure plan; construction expected by end-2028 subject to approvals. | Blackstone says its managed Infrastructure and Real Estate funds will invest and it formed a PPL JV. No public fund commitment, JV percentage, lender, customer contract or subsidy amount identified. | Separate fund equity, QTS/customer money, PPL generation funding and third-party debt; define $60B. [Announcement](https://www.blackstone.com/news/press/blackstone-to-invest-more-than-25-billion-in-pennsylvanias-digital-and-energy-infrastructure-plus-catalyze-an-additional-60-billion-investment/) | | C-07 | Meta Richland Parish / Entergy, Louisiana — over $50B | Campus expansion and associated 5GW capacity; construction and utility approval. | Meta's 2025 company-wide pool: $115.8B operating cash flow, $29.91B senior-note proceeds, $72.22B capex. LPSC approved Entergy generation/transmission facilities, but those figures do not allocate cash to the campus. | Energy-service agreement and Entergy project financing. [Meta update](https://about.fb.com/news/2026/07/teachers-local-businesses-win-as-meta-expands-louisiana-data-center/); [Meta 10-K](https://www.sec.gov/Archives/edgar/data/1326801/000162828026025534/meta-12312025x10kars.htm); [LPSC order](https://lpscpubvalence.lpsc.louisiana.gov/portal/PSC/ViewFile?fileId=nDWn%2Fjuc2%2BA%3D) | ## Energy, grid and defense reference rows | ID | Project / claim | Object and project state | Funding evidence located | Open proof / source | |---|---|---|---|---| | E-01 | Venture Global CP2 LNG, Louisiana | Phase I financing $15.1B; March 2026 Phase II close brought total CP2 financing to $20.7B. | CP2 LNG LLC: $11.25B senior-secured construction term loan + $850M working-capital/LC; CP2 Holdings: $2.8B equity bridge + $191M interest reserve. Phase II: $8.6B project financing with 26 named international banks. Long-term LNG contracts support revenue, not up-front customer funding. | FID and financial close; trace draws, holders after syndication, and construction spend. [Phase I 8-K](https://www.sec.gov/Archives/edgar/data/2007855/000200785525000036/vg-20250728.htm); [Phase II release](https://investors.ventureglobal.com/news/news-details/2026/Venture-Global-Announces-Final-Investment-Decision-and-Financial-Close-for-Phase-2-of-CP2-LNG/default.aspx) | | E-02 | NextDecade Rio Grande LNG Train 5, Texas — $6.7B expected project cost | FID, financial close and full notice to proceed. | SPV stack: $3.59B senior-secured non-recourse term loan + $500M senior-secured private-placement notes + $1.29B NextDecade equity + $1.29B GIP/BlackRock, GIC and Mubadala equity. NextDecade funded its $1.29B equity commitment with $233M cash and $1.33B term loans. | Strong example that sponsor "equity" can itself be debt financed; trace draws. [Financial-close release](https://investors.next-decade.com/news-releases/news-release-details/nextdecade-announces-positive-final-investment-decision-and-0); [financing 8-K](https://investors.next-decade.com/static-files/7f134a45-f08c-418b-8051-40b129ed9353) | | E-03 | AEP five-state transmission rebuild | Rebuild/reconductor nearly 5,000 miles of line. | $1.6B DOE loan guarantee at financial close, not an identified cash draw. AEP also reported $2.3B forward equity issuance and a Midwest transmission JV at corporate level, neither allocated dollar-for-dollar. | Lender, advance schedule and ratepayer recovery require FERC/state records. [DOE](https://www.energy.gov/articles/energy-department-closes-loan-guarantee-strengthen-us-grid-reliability); [AEP](https://pr.aep.com/news/releases/read/10501/AEP-Receives-US-Department-of-Energy-Loan-Guarantee-to-Upgrade-5000-Miles-of-Transmission-Lines) | | E-04 | Crane nuclear restart, Pennsylvania — 835MW | Restart positioned as firm power for data centers/other load. | DOE reports $1B loan closed to Constellation, backed by Constellation's balance sheet rather than a narrow-SPV borrower. | Project capex, equity allocation, advance record and site-specific customer contract not located. [DOE page](https://www.energy.gov/edf/crane-restart) | | E-05 | Lockheed munitions expansion / Troy, Alabama | Lockheed says more than $9B through 2030 across 20+ U.S. facilities; Troy center 87,000 sq. ft., with no project dollar value stated. | 2025 corporate pool: $8.557B operating cash flow, $1.985B net senior-note proceeds, $1.649B capex. $4.7B PAC-3 UCA is a demand/revenue instrument, not construction finance. | Construction underway; Troy-specific debt/grant unproven. [Troy release](https://investors.lockheedmartin.com/news-releases/news-release-details/new-lockheed-martin-facility-support-americas-arsenal-freedom); [10-K](https://www.sec.gov/Archives/edgar/data/936468/000162828026004195/lmt-20251231.htm) | | E-06 | Amentum / Savannah River Site AI and energy project — 1GW concept | NNSA selected Amentum to negotiate a phased lease with on-site generation. Selection is not lease execution, financing, construction or operation. | No financing facility or draw in selection notice. | Executed lease, SPV, approvals, equity/debt, customer and first construction spend. [NNSA selection](https://www.energy.gov/nnsa/articles/nnsa-selects-amentum-ai-data-center-and-energy-project-savannah-river-site) | ## First-wave pattern The ordinary capital channels become visible wherever disclosure resolves the asset, borrower and counterparty: parent/sponsor cash, public support, secured loans and notes, sponsor-managed funds, project JVs, international lenders and contracted customer relationships. The missing work is **allocation and draw evidence**, not a demonstrated funding gap that requires a crypto rail. Every row presently carries `digital-rail involvement: not evidenced in reviewed funding sources`.