--- title: Data Center Federal Legal Spine 2025-2026 status: active cutoff: 2026-08-20 artifact_role: research-package-router --- # Data Center Federal Legal Spine 2025-2026 This is Wave 1 of a source-first project on the U.S. conflict over data-center buildout. It follows legal objects rather than advocacy: enacted provisions, introduced bills, executive directives, agency rules and guidance, federal-land instruments, permits, and the exact return object that would change each state. It is **active retained Workbench evidence**, not live-vault authority. No vault files, counts, watches, or project queues were changed. Evidence cutoff: **August 20, 2026 ET**. ## Read order 1. [`FEDERAL_DATA_CENTER_RETURN_REFRESH_2026-10-05.md`](FEDERAL_DATA_CENTER_RETURN_REFRESH_2026-10-05.md) — current return on the named DOE lane, Savannah River and Paducah site-control gates, and the federal/state large-load rule bridge. 2. [`FEDERAL_DATA_CENTER_LEGAL_SPINE_2025-2026.md`](FEDERAL_DATA_CENTER_LEGAL_SPINE_2025-2026.md) — integrated factual answer and legal-state map through the original wave. 3. [`DATA_CENTER_WAR_LANDSCAPE_FRESH_ORIENTATION_2026-08-20.md`](DATA_CENTER_WAR_LANDSCAPE_FRESH_ORIENTATION_2026-08-20.md) — representative cross-jurisdiction map of the federal, grid, state, local, environmental, incentive, judicial and Tribal fronts. 3. [`PUBLIC_MILITARY_COMPUTE_AND_DATA_CENTER_OVERLAP_MAP_2026-08-20.md`](PUBLIC_MILITARY_COMPUTE_AND_DATA_CENTER_OVERLAP_MAP_2026-08-20.md) — public-project-only crosswalk among military-land leases, defense compute procurements and national-security power/data-center objects. 4. [`EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md`](EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md) — directive-to-return audit across finance, federal land, FAST-41 and environmental permitting. 5. [`FEDERAL_DATA_CENTER_LEGISLATION_REGISTRY_119TH_CONGRESS_2026-08-20.md`](FEDERAL_DATA_CENTER_LEGISLATION_REGISTRY_119TH_CONGRESS_2026-08-20.md) — direct bills, narrow enacted provisions and broader permitting bills. 6. [`FEDERAL_DATA_CENTER_CLAIM_FIREWALL_AND_WATCHBOARD_2026-08-20.md`](FEDERAL_DATA_CENTER_CLAIM_FIREWALL_AND_WATCHBOARD_2026-08-20.md) — prohibited compressions, public gaps and exact promotion tests. 7. [`DATA_CENTER_FEDERAL_LEGAL_OBJECT_REGISTRY_2026-08-20.json`](DATA_CENTER_FEDERAL_LEGAL_OBJECT_REGISTRY_2026-08-20.json) — canonical machine-readable object inventory for the federal wave. 8. [`validate_data_center_federal_legal_spine.py`](validate_data_center_federal_legal_spine.py) — scoped structural and claim-state validator. ## Controlling ruling There is no enacted general federal commercial data-center moratorium, federal large-load queue, rate-allocation mandate, water-reporting regime, emissions fee, or federal-land prohibition in the official record reviewed for this wave. The direct commercial bills located remain proposals in committee. Executive implementation is real but decentralized. EO 14318 has returned federal-land solicitations, conditional selections, a publicly confirmed DOE lease, a BLM right-of-way decision, FAST-41 covered-project postings, EPA reuse guidance and TSCA review priority, and final reissued Army nationwide permits, including NWP 39's express data-center coverage. Those objects do **not** collapse into a completed project, a blanket environmental exemption, or a financing award. Congress has enacted two narrow FY2026 NDAA provisions: a Navy nuclear-energy pilot that may consider data-center co-location, and recurring DOD planning estimates for military-installation data centers. Neither is a general commercial siting or rate regime. ## Evidence constitution Each material row keeps five clocks separate: `directive or proposal -> issued legal instrument -> project authorization -> construction -> operation` The package also separates: - **law** from a bill or resolution; - **rule** from guidance or an interpretive memorandum; - **permit coverage** from permit issuance; - **solicitation** from selection, lease and construction; - **selection for negotiations** from a final lease award; - **categorical-exclusion determination** from every other required approval; - **public-record gap** from proof of agency noncompliance; and - **official project description** from audited cost, financing close or operating performance. ## Wave boundary Wave 1 covers the federal executive, federal permitting/environmental, federal land and congressional layers. FERC, RTO/ISO large-load tariffs, state PUC rate cases, state statutes, and local land-use dockets belong to later object books. The fresh-orientation layer now identifies representative examples and the correct research architecture; it is not a comprehensive state or docket census. ## Promotion boundary Nothing in this package is approved for vault promotion. If Katie later selects material for the Chronicle, the vault copy becomes controlling and the detailed workbench registry remains an evidence layer.