title: October 3–12 Defense and Intelligence
status: complete
artifact_role: factual_spine
research_id: federal-government-weekly-delta-2026-10-12
---

# Wave 3 — defense and intelligence

## CVN-81 plan gate

The August 13 memorandum required a plan by October 12 for replacing EMALS and
Advanced Weapons Elevators on CVN-81 with steam and hydraulic systems,
including timeline and resources. Direct White House, Navy and Department of
War searches found the controlling directive and existing records on the
electromagnetic systems, but no public plan, delivery confirmation, accepted
design, contract change, obligation or construction receipt.

The recipient is the President through OMB and the National Security Advisor,
so the plan could be delivered without public release. The watch stays open.

Primary source: [August 13 memorandum](https://www.whitehouse.gov/presidential-actions/2026/08/rebuilding-the-united-states-navy-and-americas-shipbuilding-industrial-base/)

## High-risk property at Savannah River

DOE OIG found that Centerra-Savannah River Site did not properly classify or
account for thousands of high-risk items and did not perform required
assessments before disposition. It also found DOE oversight insufficient and
issued four recommendations. The affected property includes protective gear,
weapons, ammunition, optics and explosives.

This is a contractor and federal-oversight finding. It does not establish that
items were stolen, diverted or used, or that the recommendations are closed.

Primary source: [DOE OIG report page](https://www.energy.gov/ig/articles/action-needed-ensure-centerra-savannah-river-site-appropriately-manages-high-risk)

## Access limits

The Department of War release and daily-contract interfaces and the Navy's
search surfaces did not yield a reliable October 3–12 inventory. Existing
September content was visible. No silence or no-contract conclusion is drawn;
the direct routes remain held.