title: SEC EDGAR procurement and new-vendor entry map
status: current
artifact_role: factual_spine
research_ids:
  - federal-strategic-plans
  - sec-investor-advisory-committee
evidence_cutoff: 2026-09-18
---

# SEC EDGAR procurement and new-vendor entry map

## Question

Is there a public bidding process for the next phase of EDGAR, and what would a
new technology company have to submit or already hold in order to compete?

## Bottom line

No open, public EDGAR redesign or successor solicitation was located as of the
evidence cutoff. Direct SAM.gov searches of active notices for `OneIT`, the
current EDGAR order number `50310221F0112`, and the exact description `SEC
Enterprise EDGAR System Support Services` returned no match. The SEC's current
FY 2026 procurement forecast also does not list the enterprise EDGAR support
order, although it does list smaller EBO software renewals and a separate OIT
EDGAR tape-storage contract. These are bounded negative findings, not proof
that the SEC has made no internal acquisition decision or issued nothing to
holders of a closed contract vehicle.

The current enterprise EDGAR support award is not a stand-alone contract open
to the whole market. It is delivery order `50310221F0112` under the SEC's
multiple-award **OneIT unrestricted-pool IDIQ**, parent award
`50310218D0027`. Official award data describe the order as subject to multiple-
award fair opportunity. Under FAR 16.505, that type of order competition is
conducted among eligible holders of the multiple-award contract. A company
that does not already hold OneIT therefore cannot simply send the SEC a bid for
a new task order under that vehicle.

That does not make outside technology impossible. It creates several distinct
entry doors:

1. join a listed OneIT prime as a subcontractor or teaming partner;
2. compete in a future OneIT on-ramp if the SEC advertises one;
3. compete for a separately advertised successor contract, GSA vehicle order,
   or other open procurement if eligible for the chosen vehicle;
4. respond to an RFI, sources-sought notice, draft RFP or industry engagement
   before a solicitation; or
5. submit a narrow unsolicited proposal only if the idea is genuinely unique
   and innovative and is **not** an attempt to get ahead of a known or already
   published EDGAR requirement.

The SEC may instead exercise an option, modify the current order, issue a
bridge, or place new work through an existing vehicle. In those lanes a new
vendor may have no direct prime-contract submission opportunity at all.

## What the current award structure tells us

| Object | Confirmed public record | Entry consequence |
|---|---|---|
| Current EDGAR support delivery order | `50310221F0112`; Maximus Federal Technology Solutions; start September 27, 2021; current end December 15, 2026; potential end December 15, 2031; about $156.986 million obligated and about $269.785 million base plus all options as checked September 18 | The December date is an option/continuity decision gate, not an automatic public recompete. |
| Parent vehicle | `50310218D0027`; OneIT unrestricted pool; multiple-award IDIQ; current ordering end May 31, 2028 | A new order may be competed only among current vehicle holders unless the SEC uses another route. |
| Order competition field | Subject to multiple-award fair opportunity; commercial products/services; one offer received in the recorded order action | “Full and open” in the order record does not mean every company in the economy could bid; eligibility was bounded by the parent vehicle. |
| SEC OneIT program | Restricted small-business and unrestricted pools covering application development, business systems, infrastructure, security, data, governance and technology business management | The service channels are broad enough to carry EDGAR operations or modernization work. |
| Vehicle on-ramp | SEC's OneIT handout says on-ramps are periodic, based on agency need, have no predetermined schedule and will be advertised on SAM.gov | No company can self-enroll between advertised on-ramp events. |

Sources: [official USAspending EDGAR award record](https://www.usaspending.gov/award/CONT_AWD_50310221F0112_5000_50310218D0027_5000/),
[SEC Enterprise Vehicle List](https://www.sec.gov/files/enterprise-vehicle-list.pdf),
[SEC OneIT program handout](https://www.sec.gov/files/2021_OneIT_Program_Handout.pdf),
and [FAR 16.505](https://www.acquisition.gov/far/16.505).

## Who is in the published OneIT unrestricted pool?

The SEC's published Enterprise Vehicle List identifies the following ten
contract holders in the OneIT unrestricted pool. The contract identifier is
the stable procurement identity; a listed business name may later change
through acquisition, novation or corporate renaming.

| Contract | SEC-listed holder | SEC-listed teaming contact |
|---|---|---|
| `50310219D0001` | 3A JV | `SECOneOIT@3a-llc.com` |
| `50310218D0026` | Accenture Federal Services | `SEC.ONE.IT@afs.com` |
| `50310218D0025` | Booz Allen Hamilton | `Booz_Allen_SEC_OneIT@bah.com` |
| `50310219D0005` | Incentive Technology Group | `oneoit@itgfirm.com` |
| `50310219D0007` | Invictus JV | `SECONEOIT@c2sginc.com` |
| `50310219D0008` | KCI-Acuity JV | `BD@KCIAcuityllc.com` |
| `50310218D0027` | Maximus Federal Consulting | `SecOneIT@maximus.com` |
| `50310219D0011` | Procentrix | `OneIT@procentrix.com` |
| `50310219D0012` | Pyramid Systems | `SECONEITContracts@psi-it.com` |
| `50310219D0014` | Team GreenZone | `contracts@dminc.com` |

This is the relevant pool for a new unrestricted OneIT task-order competition.
For the current EDGAR order, Maximus is already the prime, so a new supplier's
most direct present-day approach is to Maximus. The other holders become more
important if the SEC competes a new EDGAR or modular modernization task order
across the pool. The SEC's 2021 handout expressly tells prospective
subcontractors to contact the primes on this list.

Source: [SEC Enterprise Vehicle List](https://www.sec.gov/files/enterprise-vehicle-list.pdf).

## What a OneIT on-ramp actually looks like

An on-ramp is a competition for admission to the **underlying IDIQ vehicle**.
It is not a proposal for a specific EDGAR task and it does not guarantee later
EDGAR work. A winning firm receives the right to compete for later orders,
subject to the vehicle minimum and fair-opportunity rules.

The 2019 OneIT on-ramp, solicitation `50310219R0016`, is the concrete model:

- it was a negotiated public RFP intended to add approximately ten companies;
- it applied only to the restricted small-business pool, not the unrestricted
  pool;
- an offeror had to qualify as a small business under NAICS `541512`, maintain
  accurate SAM and responsibility records, and address all seven OneIT service
  channels;
- the source-selection method was highest technically rated with a fair and
  reasonable price, rather than lowest-price technically acceptable;
- the resulting IDIQ carried a $1,000 minimum guarantee per contractor, not a
  task-order award or promise of material revenue; and
- a prime could use a joint venture or subcontractors, subject to teaming,
  commitment-letter and limitations-on-subcontracting rules.

The historical proposal contained six electronic volumes:

1. general and eligibility documents, including the signed offer, self-scoring
   sheet, representations, certifications and applicable teaming documents;
2. relevant experience across the seven service channels;
3. past-performance evidence for those projects;
4. optional scored certifications, including CMMI level 2 or higher, ISO 9001,
   ISO 20000 and the ISO/IEC 27000 information-security series;
5. risk evidence, including breadth across channels, multiple-award-contract
   experience and small-business participation; and
6. price.

The governing OneIT language identifies possible on-ramp triggers: too little
competition, too few task-order bids, inadequate solution quality, loss of
small-business coverage, or an incumbent pool unable to satisfy new and
emerging technologies. It called for advance public notice and a formal
solicitation open to all firms eligible for the selected pool. A future event
could change every proposal detail, so the 2019 RFP is an anatomy and readiness
guide, not a current solicitation.

Sources: [2019 OneIT on-ramp RFP](https://imlive.s3.amazonaws.com/Federal%20Government/ID24130062768063537304615137590649469025/50310219R0016.pdf)
and [SEC OneIT program handout](https://www.sec.gov/files/2021_OneIT_Program_Handout.pdf).

## Can software, licenses or services be donated?

### Short answer

Possibly through a properly authorized and documented lane, but the SEC cannot
simply accept a vendor's free production software or labor as an informal gift.
No current public evidence of donated software or donated services operating
the enterprise EDGAR system was located. That is a bounded public-record
finding, not proof that the SEC has never evaluated free software, used open
source, or entered a nonpublic trial.

The word **donated** can describe several legally different arrangements:

| Proposed arrangement | Likely legal/acquisition character | Practical boundary |
|---|---|---|
| Proprietary software, equipment, license or cloud credits given to the SEC | Gift or in-kind contribution | Ordinarily requires specific statutory gift-acceptance authority; an informal acceptance risks improperly augmenting the SEC's appropriation. The principal SEC statute located authorizes narrow travel and foreign-authority reimbursements, not a general technology-gift program. |
| Company personnel perform implementation or support for free | Voluntary/gratuitous services or a no-cost contract | Informal voluntary services are prohibited. An advance written gratuitous-service waiver may address future-pay claims for eligible individuals, while ongoing company performance is better routed through a formal no-cost contract or other authorized agreement. Inherently governmental functions remain federal. |
| Time-limited proof of concept, sandbox or evaluation license | Trial/evaluation acquisition | Possible if Acquisitions, counsel, ethics, security and the system owner approve written terms defining duration, data, access, IP, return/removal, support, liability and no follow-on entitlement. A successful trial is not authorization for production or a sole-source follow-on. |
| Open-source or public-domain software generally available to everyone | License/use rather than a vendor-specific gift | The no-price download does not eliminate license, security, supply-chain, accessibility, records, operations, authority-to-operate or maintenance review. Public availability also does not authorize installation in EDGAR. |
| A OneIT prime includes a third-party tool at no separately stated charge | Contractor solution and contract pricing, not necessarily a direct gift to the SEC | This may be the most practical no-additional-cost route if it is within the order, the prime remains accountable, and the contracting officer accepts the license, data rights, security, support and exit terms. It cannot be used to enlarge the order's scope or create an undisclosed follow-on commitment. |
| Formal zero-dollar/no-cost contract | Procurement instrument with no government payment obligation | It can avoid the voluntary-services problem when it is binding and expressly gives the contractor no expectation or claim for government payment. Because the SEC is obtaining services for government use, competition, conflicts, security and data-rights questions can still apply. |

### The SEC already encountered this exact boundary

The SEC OIG's 2010 review of Form 13F found that a third party had prepared and
delivered the official quarterly Section 13(f) securities list without current
payment and without any formal contract. The OIG concluded that the informal
arrangement appeared to violate the Antideficiency Act's voluntary-services
prohibition and exposed the SEC to abrupt termination with no recourse. It
recommended a formal contract or agreement documenting the supplier's duties
and expressly stating both that the SEC had no financial obligation and that
the firm had no expectation of payment. SEC management concurred.

That is strong SEC-specific precedent for the present question: a vendor may
provide something at zero price, but the operational relationship still needs
an authority, an owner, written duties, acceptance conditions, continuity and
an enforceable exit. “Free” does not mean outside procurement governance.

A separate SEC OIG technology investigation recorded that staff contemplated a
30- or 60-day no-cost equipment evaluation with vendor terms revised to comply
with federal acquisition rules. The agency ultimately purchased equipment
instead. This is evidence that a controlled no-cost proof of concept can be
considered; it is not evidence of a donated production system.

General GAO guidance supplies the outer rule: absent specific statutory
authority, agencies ordinarily may not accept donated goods or services for
their own use; voluntary services are restricted by 31 U.S.C. 1342; and a
valid, binding no-cost contract can be permissible when the government has no
financial liability and the contractor expects no government payment.
Commercial-software agreements must also state the government's rights to use,
disclose, modify, distribute and reproduce the software, with government terms
controlling over inconsistent vendor boilerplate.

Sources: [SEC OIG Review of Section 13(f) Reporting Requirements, Report 480](https://www.sec.gov/files/480.pdf),
[SEC OIG technology-contract investigation, Report 523](https://www.sec.gov/files/OIG-523%28redacted%29.pdf),
[GAO, Gifts of Goods and Services to the Government](https://www.gao.gov/products/b-289903-0),
[GAO, Treasury Acceptance of Voluntary Services](https://www.gao.gov/products/b-324214),
[GAO, GSA no-cost contracts](https://www.gao.gov/products/b-302811),
[15 U.S.C. 78d](https://www.law.cornell.edu/uscode/text/15/78d),
and [FAR 27.405-3](https://www.acquisition.gov/far/27.405-3).

## The five practical entry lanes

### Lane 1 — option, modification or bridge on the current order

If the SEC exercises an existing option, modifies the order within scope, or
uses an authorized logical-follow-on or bridge path, there may be no public
proposal for a new prime contractor. Maximus would remain the prime unless the
legal instrument says otherwise. A new technology supplier's practical route
would be a commercial license, subcontract or teaming arrangement accepted by
the prime and permitted under the order, subject to government approval where
required.

**What the new firm submits:** nothing directly to the SEC as a competing prime
unless the SEC separately requests it. It would ordinarily present the prime
with a capability statement, proof of concept, technical integration plan,
security posture, pricing, IP/data-rights terms, past performance and a clear
statement of what contract work it can perform.

### Lane 2 — a new task order under OneIT

FAR 16.505 requires the contracting officer to give the multiple-award
contract's eligible awardees a fair opportunity, subject to limited exceptions.
For a large order the task-order notice must identify the requirement,
response time, evaluation factors and the role of price. The exact proposal can
therefore be shorter and more tailored than a new stand-alone RFP, but only a
current OneIT holder receives the right to compete.

**What an eligible prime submits:** whatever the task-order request specifies—
typically a technical and management approach, staffing and key personnel,
relevant experience or past performance, transition and continuity plan,
risk/security response, and price or cost. These are readiness categories, not
confirmed EDGAR solicitation volumes; the task-order request would control.

**What a non-holder can do:** team or subcontract with one or more listed
OneIT primes. The SEC's own subcontracting guide recommends approaching likely
bidders early and seeking inclusion in the prime's subcontracting plan.

### Lane 3 — a future OneIT on-ramp

An on-ramp adds companies to the underlying vehicle rather than awarding the
EDGAR work itself. The SEC's 2021 program handout says future on-ramps depend on
agency need and have no predetermined schedule. The prior 2019 on-ramp was for
the restricted small-business pool and required a proposal under its own RFP.
That historical event shows that on-ramping is legally possible; it does not
show that another event is now planned.

**What the firm submits:** the future on-ramp RFP controls. At minimum, a
prospective prime should be ready to prove vehicle-level capability across the
required service channels, relevant experience and past performance,
responsible-contractor status, key personnel or organizational capacity, and
fair and reasonable pricing. It must also satisfy any size or socioeconomic
eligibility attached to the pool.

### Lane 4 — a new open solicitation or another vehicle

The SEC says it uses SAM.gov, GSA eBuy, GSA Multiple Award Schedules,
government-wide acquisition contracts, SEC enterprise vehicles and
interagency agreements. A successor could therefore be publicly open, limited
to a small-business category, competed among GSA or GWAC holders, or divided
into several procurements. “Publicly visible” and “open to this particular
vendor” are separate questions.

**Baseline prime prerequisites:** active SAM.gov registration and UEI, correct
NAICS and size representations, required representations and certifications,
and eligibility for any named schedule, SIN, GWAC or set-aside. The company
then submits exactly the technical, management, past-performance, price and
administrative volumes in the solicitation. A UEI without an active SAM
registration does not permit direct bidding.

### Lane 5 — an unsolicited proposal

The SEC expressly accepts electronic unsolicited proposals at
`UnsolicitedProposals@sec.gov`, but this is a narrow innovation channel. Under
the current FAR-overhaul text, the proposal must be innovative and unique,
independently originated, sufficiently detailed and mission-relevant. It
cannot be an advance proposal for a known competitively acquirable need or
address a previously published requirement. The SEC specifically warns that a
superior product, ordinary commercial offer, advertising package, or proposal
to replace an existing contracted requirement is often rejected.

A compliant unsolicited proposal must include:

- company identity, organization type and technical/business contacts;
- identification of proprietary data and other parties receiving or funding
  the proposal;
- submission date and an authorized signature;
- concise title and abstract;
- objectives, approach, level of effort, anticipated results and mission
  contribution;
- key personnel and any requested government support;
- proposed price or estimated cost, validity period, preferred contract type
  and duration;
- organizational description, relevant experience, past performance and
  facilities; and
- applicable organizational-conflict, clearance and environmental statements,
  plus prior SEC technical contacts.

If the company wants evaluation-only restrictions on its data, it must use the
SEC/FAR prescribed legend on the title page and corresponding legend on each
restricted sheet. A favorable evaluation still does not itself authorize a
sole-source award; the technical office must sponsor and fund the work and the
contracting officer must obtain the required competition justification.

Sources: [SEC unsolicited-proposal instructions](https://www.sec.gov/about/divisions-offices/office-acquisitions/unsolicited-contract-proposals)
and [current FAR-overhaul Part 15, Subpart 15.5](https://www.acquisition.gov/far-overhaul/far-part-deviation-guide/far-overhaul-part-15).

## What “new tech” should have ready before any door opens

This is a readiness file, not a submission to the SEC:

1. **Federal identity and eligibility:** active SAM registration, UEI, NAICS
   codes, size status and applicable SBA certifications.
2. **One-page mission fit:** the exact EDGAR problem solved, the affected
   control layer, and why the idea reduces risk, burden, latency, cost or
   duplication.
3. **Inspectable proof:** a proof of concept or demonstrator with measurable
   results, not only a product deck. The SEC's own vendor sheet calls out
   proofs of concept and technologies.
4. **Integration and transition:** how the capability works alongside a live,
   mission-critical EDGAR environment; rollback, backward compatibility,
   historical records, APIs and continuity.
5. **Security and information-state design:** identity, least privilege,
   logging, provenance, public/nonpublic classification, secure development,
   software supply chain and incident response. Exact controls and clauses
   would be established by the solicitation and system authorization process.
6. **Data and accessibility:** structured-data/taxonomy handling, data rights,
   records retention, privacy and Section 508 accessibility where applicable.
7. **Delivery evidence:** named key personnel, relevant past performance,
   staffing and surge capacity, quality controls and realistic schedule.
8. **Commercial file:** pricing/cost model, license and IP terms, proposed
   contract or subcontract model, organizational conflicts and any government
   support needed.
9. **Prime strategy:** identify whether the company is seeking direct prime
   status, a future on-ramp, a GSA/GWAC path or a place on a OneIT prime's team.

The most persuasive package would map the technology to the known EDGAR
control problems—information-state separation, data quality, provenance,
review workflow, resilience and transition—without claiming that the SEC has
selected that architecture.

## Can a genuinely new company bid today?

| Route | Direct prime bid today? | Current assessment |
|---|---:|---|
| Current Maximus option/modification | No | No public competition is created merely by the option gate. |
| New order under current OneIT vehicle | No, unless already a holder | A non-holder's live path is teaming/subcontracting. |
| OneIT on-ramp | No active event located | Possible only if the SEC advertises one. |
| Separate EDGAR successor RFP/RFQ | No active notice located | Possible if and when the SEC publishes or routes one through an eligible vehicle. |
| GSA eBuy/GWAC competition | Only if the firm holds the named vehicle or teams with one that does | This route may not be visible as a general SAM solicitation. |
| Unsolicited proposal | Yes, but only in the narrow FAR sense | Poor fit for an ordinary EDGAR replacement pitch; possible for a genuinely unique, independently developed capability outside a known requirement. |
| Subcontract/teaming approach | Yes | Most immediate practical entry route; it does not confer prime or system-control rights. |

## Watch gates

Treat each as a separate acquisition state:

1. SEC forecast adds EDGAR enterprise support, redesign or review work;
2. SAM.gov posts an EDGAR/OneIT RFI, sources-sought notice, presolicitation,
   solicitation, on-ramp, award notice or exception-to-fair-opportunity
   justification;
3. SEC issues a draft RFP, industry day or vendor-engagement notice;
4. USAspending changes the current order's end date, options, obligations,
   recipient, description or parent vehicle;
5. SEC updates the Enterprise Vehicle List or announces a OneIT successor;
6. a GSA eBuy/GWAC holder discloses a request or teaming solicitation;
7. Maximus or another listed prime publicly seeks a specialized EDGAR partner;
8. an award, not merely a notice, identifies a new modernization module; or
9. the SEC publishes a proof-of-concept, challenge, cooperative agreement,
   no-cost contract, gift-acceptance determination or zero-dollar award related
   to EDGAR technology; or
10. a contract statement of work reveals the actual target architecture,
   transition obligations and acceptance measures.

## Evidence and authorization boundary

Evidence checked September 18, 2026 EDT. The SAM negative result is bounded to
the exact active-notice searches stated above; vehicle-holder-only requests,
GSA eBuy notices, unpublished acquisition planning and differently titled
requirements may not appear in that search. The FY 2026 procurement forecast
is an estimate, not a solicitation or commitment. The 2021 OneIT handout and
2019 on-ramp are historical evidence of vehicle design, not evidence of a
current on-ramp. No Chronicle landing, watch creation, installed-app change or
publication is authorized by this Workbench save.