# Source ledger — Federal Reserve Non-Core Initiative Governance

**Research ID:** `federal-reserve-noncore-initiative-governance-2026`
**Cutoff:** 2026-09-30 EDT

This ledger records what each source can prove. It does not promote an
announcement, recommendation or accounting aggregate into a later operating
state.

## Primary sources

### 1. Federal Reserve OIG Report 2026-FMIC-B-016

- **Source:** [*Evaluation of the Eccles-1951 Renovation Project Management and Construction Costs*, September 29, 2026](https://oig.federalreserve.gov/reports/board-eccles-1951-renovation-construction-costs-sep2026.pdf)
- **Controls:** project chronology; budget and package evidence; CMAR/GMP
  execution; governance and reporting findings; seven recommendations; Chairman
  Warsh's attached response; the Board-as-nonexpert-owner diagnosis; planned IT
  modernization as a future relevance point.
- **Does not prove:** final cost reasonableness; amount of avoidable loss; signed
  GMP; completed independent audit; recovered amount; issued agency policy;
  successful IT-modernization application; durable closure.

### 2. Board of Governors 2025 and 2024 financial statements

- **Source:** [OIG Report 2026-FMIC-B-003, March 12, 2026](https://oig.federalreserve.gov/reports/board-financial-statement-audit-mar2026.pdf)
- **Controls:** Board entity and U.S. GAAP boundary; year-end 2025 and 2024
  aggregate construction-in-process balances; capital expenditures; property
  accounting policy; financial-statement audit opinion and internal-control
  reporting.
- **Does not prove:** Eccles-1951-only cost; vendor, trade, package or cost-code
  detail; value for money; contract compliance; paid-but-unreceived services;
  exact placed-in-service classification.

### 3. Board of Governors 2023 and 2022 financial statements

- **Source:** [OIG Report 2024-FMIC-B-002, March 11, 2024](https://oig.federalreserve.gov/reports/board-financial-statement-audit-mar2024.pdf)
- **Controls:** earlier aggregate construction-in-process balances used to build
  the 2022–2025 accounting trend.
- **Does not prove:** project-level or vendor-level lineage.

### 4. Board Acquisition Policy

- **Source:** [Board of Governors Acquisition Policy](https://www.federalreserve.gov/aboutthefed/procurement/aquisition-policy.htm)
- **Controls:** the Board's published procurement posture and current public
  acquisition-policy surface.
- **Does not prove:** the specific Eccles-1951 contract, an operative post-OIG
  framework or application to IT modernization.

## Current evidence-state ledger

| Proposition | State | Controlling source |
|---|---|---|
| The Board failed to execute the Eccles-1951 CMAR contract effectively | observed finding | OIG Report 2026-FMIC-B-016 |
| The Board should treat itself as a nonexpert owner for certain non-core initiatives | observed OIG institutional diagnosis | OIG Report 2026-FMIC-B-016 |
| Seven corrective recommendations were issued | observed | OIG Report 2026-FMIC-B-016 |
| Warsh concurred and directed GSA, audit, GMP, metrics and remedies | directed | Management response attached to OIG Report 2026-FMIC-B-016 |
| GSA holds an operative delegated Project Executive mandate | not yet established separately | Return gate |
| An independent auditor has been selected and engaged | not established | Return gate |
| Awarded costs have been independently validated | not established | Return gate |
| A project-level GMP or enforceable substitute has been signed | not established | Return gate |
| The Board has recovered cash or obtained a project credit | not established | Return gate |
| The Board has issued the agency-wide framework | not established | Return gate |
| The framework governs planned IT modernization | not established | Return gate |
| The recommendations are closed and the capability is durable | not established | Return gate |

## Required source types for the next update

Prefer, in order:

1. OIG recommendation-follow-up or closure evidence;
2. signed Board/GSA authority, governance or interagency instrument;
3. procurement award or audit engagement record;
4. independent audit report and management response;
5. executed contract modification, GMP or fee cap;
6. Board policy, committee charter, RACI, KPI or dashboard;
7. contract demand, modification, credit, settlement or payment record;
8. audited financial statements and notes;
9. project-ledger, CIP or placed-in-service reconciliation; and
10. IT-modernization budget, charter, procurement or assurance record showing
    actual reuse of the framework.

## Source-handling rules

- Keep Board, GSA, contractor, auditor and OIG statements attributed to the
  issuing actor.
- Preserve original and current budget and schedule measures together.
- Keep award, invoice, accrual, cash payment, CIP, placed-in-service transfer and
  depreciation on separate clocks.
- Keep questioned, unsupported, disallowed, credited, reimbursed, settled and
  recovered amounts separate.
- Do not treat an OIG closure entry as durable capability without later-project
  operating evidence.
