# Military Modernization — Source Watchboard

**Status:** `current saved source watchboard; no live watch or refresh implied`  
**Cutoff:** 2026-07-15; targeted FAST watch added 2026-09-25; targeted Project Meridian watch added 2026-09-30

## Watch rule

Watch the entity that can move the clock. A speech does not move a contract; a contract does not move operational acceptance; a test does not move appropriation.

| Track | Authoritative sources | Clock moved | Promotion trigger |
|---|---|---|---|
| Department strategy/organization | White House presidential actions; Defense/War releases and memoranda; DoD/DoW CIO; CDAO | direction, charter, reporting line | signed directive, strategy, charter, reorganization or cancellation |
| Budget/funding | DoD Comptroller; service budget justification; Congress.gov; enacted appropriations | request, authorization, appropriation | exact programme line and legal funding state |
| Contracts | Defense contract releases; SAM.gov; service contracting commands | solicitation, award, modification, obligation | named entity, vehicle, value type, scope and period |
| JADC2/joint requirements | Joint Staff; Secretary memoranda; DoD CIO/CDAO | requirement, implementation, reform | new validation rule, responsible entity or joint baseline |
| Army NGC2 | Army news; CPE C2IN/C3N; ASA(ALT); Army budget books | prototype, baseline, validation, delivery | unit implementation, PC-C6 result, production/delivery decision, interface/data-right document |
| Right to Integrate | Army CTO/ASA(ALT); participating programme offices | interface validation, hardening, fielding | capability moves from hackathon result to operational deployment |
| DAF Battle Network/ABMS | DAF PEO C3BM; AFLCMC; Air Force budget books | architecture, programme delivery, operational node | named fielded node, operational acceptance or portfolio reorganization |
| Navy Overmatch/PAE MS | NAVWAR; DON CIO; Navy budget books; PAE releases | fleet installation, software delivery, entity integration | class/ship/unit fielding, operational validation, formal transfer document |
| PWSA | SDA releases, awards and On Orbit page; Space Force budget | award, launch, on-orbit, operational handoff | tranche completion, operational acceptance or new common-ground/interface state |
| Golden Dome | White House; Golden Dome office; MDA; SDA; Space Force; Comptroller | architecture, award, fielding | objective architecture, production award, test, operational element |
| SATCOM/PNT | Space Systems Command; Space Force; budget books | contract, launch, test, operational transfer, cancellation | MUOS/ESS/PTES/PTS/PNT delivery or operational state |
| Cloud/edge | DISA; DoD CIO; JWCC task-order notices; budget books | vehicle, task order, deployment | follow-on vehicle, classified-edge capability, exit/portability or operational deployment evidence |
| Zero trust/identity | DoD CIO; DISA; component CIOs; DODIG/GAO | deployment, compliance, audit | component-level evidence against FY2027 target |
| Data/AI | CDAO; AI strategy reports; contract releases; GAO/DODIG | demo, transition, contract, fielding | named six-month PSP result, transition user, operational authorization or scale |
| Maven | Army contracts; CDAO; operational-unit releases; test/evaluation | licence, user, fielding, model/application scope | unit/system state or contract/data-right change |
| Autonomy/Replicator | DIU; DoD releases; service programme offices; GAO | production, delivery, unit training, operational use | verified quantity/state, successor initiative or completion report |
| Counter-UAS | JIATF 401; Army; DHS/FAA for domestic seams; DODIG | entity, authority, capability delivery | task-force implementation, fielded system, domestic-authority change |
| NC3/continuity | STRATCOM/NC3 Enterprise Center; DISA; Air Force/Navy/Space Force budgets and contracts | development, terminal/satellite/aircraft delivery, operational acceptance | E-4C, E-130J, ESS or secure-services milestone |
| Acquisition reform | White House; A&S; service acquisition executives; Federal Register/DFARS | legal/process, portfolio transfer, cancellation | implementing regulation, portfolio reorganization, programme cancellation/selection |
| FAST / resource governance | Deputy Secretary; USW(C)/CFO; Military Departments; Joint Staff; Defense Agencies and Field Activities | review, recommendation, disposition, implementation, measured result | named Director/charter; target and recommendation; authorized acceptance/rejection; budget, contract, organization or personnel action; measured savings/readiness result |
| Project Meridian / future-warfare study | Secretary; DoW CTO; named partner organization; Joint Staff and services; Federal Register and GSA FACA database where applicable | commission, constitution, study, report, disposition, implementation | partner instrument; roster/governance/conflict controls; January 28, 2027 report; named government disposition; later requirement, budget, award, test or fielding receipt |
| Subterranean capability | DARPA; Army Futures Command/DEVCOM; ERDC; DTRA; CPE CBRND; service labs and acquisition offices | research, prototype, transition, acquisition, field use | integrated system or program with named owner; unit evaluation; map/PNT/network/hazard performance; production or fielding receipt |
| Oversight/failure | GAO; DODIG; DOT&E; congressional hearings | risk, delay, test failure, recommendation | accepted programme risk, schedule breach, failed test or cancellation |

## Immediate watches

### Project Meridian

- Identity of the partner organization and the agreement, charter, task order or other instrument used to commission it.
- Full roster, compensation, selection, records, security, intellectual-property and conflict/recusal rules.
- Federal Advisory Committee Act determination or listing if the final structure is a covered advisory committee; absence of a same-day listing is not dispositive.
- Joint Staff and service inputs, requests for information, meetings and interim products.
- Findings and recommendations due January 28, 2027; separate public-report publication from classified-annex custody.
- Named official disposition of each recommendation and any later requirement, funding, solicitation, award, test or fielding action.
- Keep Project Agincourt and the announced Autonomous Warfare Command on their own execution clock.

### Subterranean domain

- Transition receipt for multi-robot autonomy, subterranean mapping, mesh communications or CBRN payloads into a named program and unit.
- Demonstrated GPS-free navigation accuracy and duration in a representative underground environment.
- A common interface for maps, confidence data, relay nodes and command systems across vendors.
- An operational evaluation that measures map accuracy, communications recovery, endurance, hazard detection and operator workload.
- Field-hardening and transition evidence for compact optical clocks, nonlinear inertial sensors, quantum sensors or deep-imaging systems.
- Rapid tactical-tunneling or robotic underground-logistics result beyond a completed research program.
- Evidence that the surface and underground force share one authoritative, versioned common operating picture.

### FAST

- Named Director, charter, staffing, review criteria and target list.
- First recommendation and the official with authority to accept, reject or modify it.
- Separate budget, reprogramming, contract, directive, organization or personnel instrument implementing any accepted recommendation.
- Measured cost, cycle-time, delivery or readiness result against a stated baseline.
- Formal interface with the Performance Improvement Officer, CAPE, A&S, CIO and Inspector General.
- Evidence that the team does not duplicate the review layers it was created to reduce.

### Army NGC2

- Project Convergence Capstone 6 result and whether the June baseline changes after validation.
- Delivery/fielding scope for 4th ID and 25th ID.
- Full interface, government-purpose-rights, data portability and cyber authorization terms.
- Whether Right to Integrate results become hardened operational releases.

### 2026 AI strategy

- Initial demonstrations due under the six-month clock.
- Named sponsors and transition users for Agent Network, Open Arsenal and Ender's Foundry.
- Whether “kill chain execution” remains decision support or crosses into new engagement governance.
- Evidence that component data catalogues were delivered and the seven-day denial/escalation mechanism is being used.
- Whether contracts actually require 30-day frontier-model refresh and prime-independent third-party integration.

### Navy PAE Mission Systems

- Formal organization/charter documents showing which authorities and personnel actually transferred.
- First delivery decision issued by the new PAE.
- Overmatch fleet-installation and operational-readiness detail.

### Space and Golden Dome

- Remaining PWSA Tranche 1 launches and initial warfighting capability declaration.
- AMDT3 delivery and launch readiness against the end-2028 statement.
- Golden Dome objective architecture, common ground system and battle-management integrator.
- PNT successor path after OCX cancellation.

### Continuity

- E-4C aircraft conversion/delivery and test milestones.
- Evolved Strategic SATCOM satellites, terminals and operational transition.
- E-130J TACAMO delivery and mission-system integration.
- Any public NC3 cybersecurity, AI or automation governance document.

### Commercial dependency

- JWCC follow-on acquisition and actual task-order distribution.
- Microsoft enterprise agreement ordering/obligation detail.
- Open DAGIR portability and government-data-right terms.
- multi-provider strategic SATCOM acquisition decisions.

## Evidence that does not move a state by itself

- conference remarks;
- vendor press releases without government confirmation;
- a budget request without enactment;
- a ceiling without an order/obligation;
- a launch without on-orbit checkout;
- an exercise without a result;
- a demonstration without a transition user;
- “AI-enabled,” “secure,” “resilient” or “open” without a testable definition.