Tribal data centers — source watchboard

.md · 2 sections · 16095 characters

Source, owner, and dates

workbench: Research Packages/Sovereign Compute/TRIBAL_DATA_CENTER_SOURCE_WATCHBOARD.md

Canonical source SHA-256: 7d1d2ddf1571a482090e5c7e9a93fad3f717eb566b70f274267e15000ddb1528

Served copy SHA-256: 7d1d2ddf1571a482090e5c7e9a93fad3f717eb566b70f274267e15000ddb1528

Owner evidence cutoffs: {"sovereign-compute": "2026-10-05"}

These are package-level cutoffs, not a claim that this source was rechecked on those dates. Use its own publication and capture dates.

Owners: sovereign-compute

Tribal data centers — source watchboard

Section 1 of 2

# Tribal data centers — source watchboard

Updated: 2026-08-27 Status: manual watch map; dated returns reconciled; successor returns ledger-governed Purpose: locate primary actions early without turning rumors or repeated press coverage into duplicate events.

[!caution] Freshness boundary The four dated return questions below were checked on 2026-08-27. The check produced negative or limited evidence, not proof that an unlocated action did not occur. Each successor source/state trigger is governed by the Research Return Ledger. The undated DOE convening and approximately September 2027 Colusa target remain standing package watches.

## Watch rule

Watch the entity that can actually change the relevant state. A developer's press release can announce a partnership; it cannot prove a tribal lease. A tribal council can authorize a deal; it cannot prove grid capacity. A utility filing can establish an interconnection request; it cannot prove final construction. Each source is assigned to the clock it can move.

## Federal sources

Source Clock Trigger to capture
BIA approved HEARTH regulations Land / leasing authority New or amended business, energy, or general leasing regulations for a watched Tribe
BIA leasing services Land / lease approval Business lease, right-of-way, handbook, or approval-process change
BIA TERAs and TEDOs Energy authority New TERA or TEDO certification; scope and effective date
DOE Office of Indian Energy Federal partnership / funding Tribal Data Center Convening; site assistance; awards; webinars; legal or engineering guidance
DOE Indian Energy events Convening Agenda, speakers, participating Tribes, developers, matchmaking, or follow-up materials
FERC news and dockets Grid / rates Large-load tariffs, co-location, cost allocation, flexible load, generator tie, or tribal-energy filings
FAST-41 project dashboard Federal permitting Named data-center project, sponsor, site, lead agency, or tribal consultation
EPA data-center resources Air / environmental Turbine rules, exemptions, enforcement, permitting guidance, or tribal air-program action
Federal Register General federal action Data center + Tribe/Indian/Native/HEARTH/TERA/trust land; categorical exclusion; land solicitation; funding
New York Public Service Commission Case 26-E-0045 New York grid / rates Large-load interconnection rules, separate rate classes, cost allocation, technical conference, white paper, and Indigenous Nation comments
NYISO interconnection queue New York power New, modified, withdrawn, or completed large-load request near a New York Indigenous territory; owner, MW, point of interconnection, and in-service target
NYSDEC Indian Nation Affairs Consultation / environmental CP-42 consultation, environmental permit, cultural-resource review, or Nation-specific outreach for a data-center project
New York data-center legislation State regulation Governor action, effective date, implementing study, hearing rules, permit pause, rate classifications, and scope questions involving tribal parcels

## Tribal-government and enterprise sources

Entity Primary pages or records Trigger to capture
Cachil Dehe / Colusa Indian Community Tribal council records; Colusa Indian Energy news; approved HEARTH text Parcel, lease, Center of Excellence activation, generation permit/contract, financing, construction, tenant, or additional partner
Quechan Indian Tribe Tribal announcements; Council and special-meeting records; Economic Development Administration; environmental-review notices Due-diligence authorization, parcel/site map, developer identity, 200-MW power configuration, environmental scope, community vote, lease, or termination
Caddo Nation Council agendas/minutes/resolutions; economic-development authority; tribal newspaper; BIA HEARTH text Developer contact, RFP, resolution, referendum, parcel, lease, power or water agreement
Cherokee Nation Executive orders; task-force pages; Council records Data-center task-force report or extension; citizen input; policy; project or moratorium
Seminole Nation of Oklahoma General Council/Tribal Council resolutions and minutes; official communications Original March 7 moratorium; duration; amendments; developer identity; enforcement
Muscogee (Creek) Nation National Council legislation and minutes; executive branch; Looped Square Ranch/food-sovereignty records Substitute or reintroduced technology-park legislation, developer identity, parcel change, or new environmental safeguards following NCA 25-077's 4-11 defeat
Forest County Potawatomi / Potawatomi Ventures Data Holdings; Potawatomi Ventures Expansion, added power, new tribal-government customers, data-sovereignty service, ownership or campus change
Southern Ute Tribal Council; Department of Energy; Growth Fund; TERA implementation First project approved through TERA; large-load, generation, or digital-infrastructure application
Shoshone-Bannock Official press releases; Pocatello administrative record July 16 appeal, written decision, new project materials, treaty or consultation action
Yakama Nation Tribal Council; cultural-resource and treaty-fisheries entities; Goldendale dockets Historic-properties plan, consultation record, storage approval, land transaction, confirmed data-center offtaker
Oneida Indian Nation of New York Oneida ordinances and regulations; Turning Stone Enterprises; Oneida Innovations Group; federal contract notices; utility and NYISO records Location or expansion of four stated Tier III data centers; third-party hosting; sovereign-cloud offering; large-load request; new lease or equipment procurement
Tonawanda Seneca Nation Nation correspondence; GCEDC STAMP library; Town of Alabama records; DEC and Army Corps records Stream hearing, SEQRA determination, site-plan revision, 500-MW power instrument, tenant, generator air permit, water/wastewater decision, Nation response or litigation
Saint Regis Mohawk Tribe / Akwesasne governments SRMT Council and Environment Division; Mohawk Council of Akwesasne; Mohawk Nation Council of Chiefs; Mohawk Networks; Massena planning records Separate government positions; Massena site-plan and SEQR actions; power allocation; Alcoa sale; additional developers; 140-acre parcel status; tribal telecom or compute partnership
Seneca Nation of Indians Council records; Seneca Holdings and Seneca Nation Group; Seneca Energy; broadband records Physical cloud/data-center footprint; PPA or large-load study; site screening; developer approach; equipment or hosting contract
Shinnecock Indian Nation Council records; Shinnecock Power; NTIA and ConnectALL records; LIPA dockets Fiber completion, carrier/NOC agreement, energy project, edge/sovereign-cloud node, site or land-status action
Tuscarora Nation Council/environmental records; Haudenosaunee Environmental Task Force; NTIA; NYPA Niagara records Fiber completion, network operator, power or telecom enterprise, large-load or developer approach, consultation on nearby Niagara projects

## Developer and capital sources

Entity Source Trigger to capture
UnityCloud Company website; corporate registrations; financing announcements First named Tribe, parcel, signed agreement, financing, power partner, construction, or operating capacity
Strata Expanse Company releases; SEC/REIT and financing records; local permits Colusa site control, gray-space subscription, tenant, financing, equipment, second tribal partner
Colusa Indian Energy News Tribal power projects serving data centers; project-company creation; government funding; construction
STACK Infrastructure Company releases; planning and utility dockets Confirmed Indigenous-land, sacred-site, treaty, or tribal-power connection rather than geographic proximity alone
Hyperscalers and operators SEC filings; company releases; state incentive contracts; utility dockets Named tribal counterparty, land status, power seller, sovereign-cloud claim, or national-security workload
Brokers, project LLCs, and land companies Secretary of State records; county land records; UCC filings; planning packets Common officers, repeat law firms, options, assignments, financing, or migration from a blocked site

## Utility and resource sources

For each confirmed site, identify the balancing authority, retail utility, water supplier, air regulator, and gas pipeline before searching their dockets.

Capture:

## Revenue-source watch

The economic-need hypothesis must be built nation by nation. For every watched Tribe, collect dated primary records for:

National gaming totals are a context series, not a substitute for tribal accounts. The current national baseline is record FY2024 gross gaming revenue, while particular Tribes may still face closure, market loss, debt, or extreme concentration. NIGC — FY2024 Gross Gaming Revenue

## Search vocabulary

Use combinations rather than only “data center”:

Immediate dated watches

Section 2 of 2

## Immediate dated watches

Date Watch Expected source
2026-07-16 Pocatello appeal hearing for former Hoku-site project City Council packet, recording, written decision; Shoshone-Bannock response
2026-07-24, 5:00 p.m. EDT DOE tribal-energy funding deadline DOE award announcements and application summaries later in 2026
Through 2026-08-14 Cherokee data-center task-force report or extension Cherokee Nation executive/task-force pages
2026-08-13 DOE webinar on tribal pathways in nuclear energy Participant list and any explicit data-center/microreactor pairing
Date not announced DOE Tribal Data Center Convening DOE event page, agenda, attendees, presentations, resulting agreements
Approximately 2027-09 Colusa target to exceed 100 MW onsite generation Permits, equipment, financing, construction, commissioning

## 2026-08-27 dated-return receipt

Original return anchor Bounded result through 2026-08-27 Boundary and route
2026-07-16 — Pocatello appeal hearing for former Hoku-site project Pocatello's official Agenda Center exposed the July 16 meeting/appeal surface, but the bounded check did not recover a controlling written disposition. Access/locator hold; ledger-governed. Do not infer approval or denial. Return on a written decision, complete administrative record or attributable Shoshone-Bannock response.
2026-07-24, 5:00 p.m. EDT — DOE tribal-energy funding deadline The application clock passed. DOE's program page places award announcements later in 2026; no award/result follows from deadline passage alone. Resolved at the filing clock; ledger-governed successor. Return on a DOE award announcement or application/result summary.
2026-08-13 — DOE webinar on tribal pathways in nuclear energy DOE now provides a recording and slides. The materials are general civilian-nuclear and microreactor support; they do not establish a named tribal data-center pairing. Resolved negative for the pairing test; ledger-governed successor. Return on a named Tribe, site, developer, data-center project or executed support object.
Through 2026-08-14 — Cherokee data-center task-force report or extension Cherokee Nation's current task-force page still lists the Data Center Task Force, but the bounded check did not locate a report or extension. Negative public-source check; ledger-governed. Non-detection is not proof of nonproduction. Return on the report, written extension or official disposition.
Date not announced — DOE Tribal Data Center Convening No dated gate was adjudicated by this receipt. Standing watch / package-context-only. Keep the event, agenda, attendee, presentation and resulting-agreement triggers above.
Approximately 2027-09 — Colusa target to exceed 100 MW onsite generation The target is future-dated and was not adjudicated by this receipt. Standing watch / package-context-only. Keep permit, equipment, financing, construction and commissioning triggers above.

## Event capture template

<a id="yyyy-mm-dd-action-title"></a>### YYYY-MM-DD — action title

**Status:** Occurred / Announced / Proposed / Approved / Operating / Scheduled
**Entity acting:**
**Other entities named:**
**Project ID / aliases:**
**Clock:** Tribal government / land / developer / power / water-environment / capital / compute / revenue / resistance / national security
**Project stage before:**
**Project stage after:**
**Land status:** Verified / claimed / unknown
**Location:**
**Time:** Publicly stated / not publicly stated

One neutral paragraph stating what the source establishes and what remains unestablished.

**Primary source:** [Label](URL)
**Secondary corroboration:** [Label](URL), if needed
**Open document request:**

## Promotion rule

A lead becomes a confirmed project only when the record contains, at minimum:

  1. a named Tribal Nation or tribal entity;
  2. a named project, developer, operator, or official tribal action;
  3. a location or land relationship specific enough to test;
  4. a dated source establishing the action;
  5. a project stage that does not depend on inference.

No number of repeated articles can substitute for those fields.