Source, owner, and dates

workbench: Research Packages/US Inbound Investment and Industrial Capex Funding Map 2025-2026/INITIAL_EVIDENCE_LEDGER.md

Canonical source SHA-256: e0c19fd29a5c5c295246e66eb5cb0ca33f4a955beaca0952cf6b455230cc8cb7

Served copy SHA-256: e0c19fd29a5c5c295246e66eb5cb0ca33f4a955beaca0952cf6b455230cc8cb7

Owner evidence cutoffs: {"us-inbound-investment-industrial-capex": "2026-07-31", "ai-infrastructure-capital-stack-risk-transfer": "2026-08-10", "industrial-project-finance-digital-rails": "2026-07-31"}

These are package-level cutoffs, not a claim that this source was rechecked on those dates. Use its own publication and capture dates.

Owners: us-inbound-investment-industrial-capex, ai-infrastructure-capital-stack-risk-transfer, industrial-project-finance-digital-rails

Opening section

Section 1 of 1

# Initial Evidence Ledger — Investment Claim to Funding Stack

## Macro controls

Object What the source supports What it does not support
BEA new FDI, 2025 $232.2B actual expenditures to acquire, establish or expand U.S. businesses; $218.4B acquisitions; $13.8B greenfield establishment/expansion; $284.5B planned future expenditure attached to those transactions. A claim that all announced investments are actual FDI or new physical construction.
BEA inward direct-investment position, end-2025 Foreign direct-investment position in the United States was $5.86T, up $266.0B in 2025; position is cumulative ownership/intercompany-finance stock, not annual project capex. Construction spend, a new-commitment ledger or a debt-funding total.
Fed Z.1, 2026 Q1 Nonfinancial-business debt outstanding was $22.6T; nonfinancial corporate debt $14.5T. Corporate bonds, depository loans, mortgages, commercial paper and other loans are distinct instruments. A project-level identification of lenders or the claim that banks alone fund industrial investment.
U.S. financial account, 2025 Net U.S. borrowing from foreign residents was $1.21T. That these flows funded the named investment projects or were FDI.

## Administration aggregate: object mismatch

The White House Investment Accelerator fact sheet said in March 2025 that more than $3T in private investment had been secured, without a project-by-project funding ledger or methodology. The White House investment list also includes a $1.2T Qatar “economic exchange,” a $1.4T UAE ten-year investment framework and corporate announcements. These are not interchangeable construction financings and must not be summed as a single debt pipeline.

## First project sample

Project / headline Physical or economic object Funding evidence located State and next proof
Apple — $500B / four years Apple says the figure includes suppliers, direct employment, data centers, facilities and Apple TV+ productions, not solely new construction. FY2025 10-K: $132.4B cash/cash equivalents/marketable securities; $12.7B PP&E purchases in FY2025; $91.3B term-debt principal. A rolling corporate-spend commitment. Need named-site capex and dedicated financing only if a particular asset is researched.
TSMC Arizona — $165B planned U.S. investment Multiple fabs and related facilities over years; disclosed operating/construction chronology. TSMC 2025 Form 20-F reports up to $6.6B CHIPS direct funding, up to $5B federal loans, and $8B TSMC Arizona notes outstanding at end-2025, parent-guaranteed. Concrete layered stack, but not all $165B is closed/drawn. Continue with award milestones, notes, parent contribution and each fab’s construction/COD.
Stargate — $500B / four years Future AI-infrastructure target. Announcement names SoftBank, OpenAI, Oracle and MGX as initial equity funders; says $100B would begin deployment. No signed $500B debt package is disclosed in the announcement. Announcement/equity-intent level. Split by site, SPV, power, customer contract and financing document.
CoreWeave Pennsylvania — $6B commitment AI data-center build; 100MW initial capacity with potential 300MW expansion. 2025 SEC materials describe a $2.6B delayed-draw term loan for the development. Company reported $10.3B investments, $9.3B net financing raised and $21.6B debt in 2025. A real debt/equity/customer-contract/OEM-finance mix. Trace first draw, collateral, power/interconnection and construction spend.
Venture Global Louisiana — $18B claim LNG infrastructure; project stack exists separately from any White House list. 2025 10-K reports $23.7B project-level debt and $34.8B total debt; Plaquemines issued $2.5B secured notes in April 2025. Classic asset-backed/project-finance reference case. Trace offtake contracts, lenders/noteholders, draw/use and operating cash flow.
Hyundai — $21B, 2025–28 $9B auto capacity, $6B parts/logistics/steel, $6B future industry/energy; includes but is not limited to a Louisiana EAF mill. Sponsor release does not identify a project debt facility or full capital stack. Aggregate group allocation, not evidence of $21B bank lending. Begin at individual legal entities/sites.

## Sources