.md · 1 sections · 1505 characters
workbench: _Working/federal-budget-2026-2027/goal/terra_institutions/agriculture/batch6/REPORT.md
Canonical source SHA-256: f023daa0ad757fb6fddbf150b6e86d9eaf028b2639632d5c9567bfed570b019c
Served copy SHA-256: f023daa0ad757fb6fddbf150b6e86d9eaf028b2639632d5c9567bfed570b019c
Owner evidence cutoffs: {"federal-budget-fy2026-fy2027": "2026-09-11T19:55:13-04:00"}
These are package-level cutoffs, not a claim that this source was rechecked on those dates. Use its own publication and capture dates.
Owners: federal-budget-fy2026-fy2027
Section 1 of 1
# USDA FY2027 ARS Chapter 20 — Buildings & Facilities completion
This batch continues the human-owned ARS read without duplicating it. The human receipt covers physical pages 1–40 (printed 20-1–20-40); this receipt sequentially reads physical pages 41–52 (printed 20-41–20-52), completing the 52-page official Chapter 20 document across two clearly separated scopes.
The Buildings & Facilities request is zero new FY2027 appropriation, a $60.650 million decrease from FY2026. That does not mean the account has zero FY2027 activity: the CJ estimates $62.592 million in FY2027 obligations, drawing on balances and prior/supplemental resources. Tables ARS-17 and ARS-19 keep appropriation, total available, and obligation measures distinct.
The construction table is explicitly a December 2025 status snapshot. It mixes completed work, contracts already awarded, project holds pending proposed closure, and future award/completion expectations. It defines a Program of Requirement as a planning document for program, space/equipment, and design criteria, but names no published POR, cost estimate, alternatives analysis, or model that explains the FY2027 zero-appropriation request. Those items remain an exact-source queue rather than an absence claim.
Source: official USDA ARS Chapter 20 PDF. This batch read the official browser-rendered source; a direct local download was not retained as source text.