Skip to content
Browse the whole research Library · Start page for AI agents ·

SMR, LLC; Palisades SMR, LLC; Pioneer Units 1 and 2; Exemption

.md · 1 sections · 2049 characters

Source, owner, and dates

vault: 02 - Research/Official Records/Official filings/2026-08-28-0000 - NRC Pioneer Units 1 and 2 pre-LWA excavation-wall exemption.md

Canonical source SHA-256: 8756a8e26054e33a63ee3c883703a3a6faf763ba3018b2b59ad731c9707bb5c5

Served copy SHA-256: 8756a8e26054e33a63ee3c883703a3a6faf763ba3018b2b59ad731c9707bb5c5

Owner evidence cutoffs: {"official-records-source-library": "2026-10-14"}

These are package-level cutoffs, not a claim that this source was rechecked on those dates. Use its own publication and capture dates.

Owners: official-records-source-library

complete text

Opening section

Section 1 of 1

# SMR, LLC; Palisades SMR, LLC; Pioneer Units 1 and 2; Exemption

## Quote / Content

The U.S. Nuclear Regulatory Commission (NRC) has issued an exemption in response to a request dated December 31, 2025, from SMR, LLC, on behalf of Palisades SMR, LLC, a wholly-owned subsidiary of Holtec International (collectively, Holtec) for approval to allow construction of permanent support of excavation walls prior to the issuance of a limited work authorization for Pioneer Units 1 and 2. The support of excavation walls will remain in place after construction is complete.

The exemption was issued on August 28, 2026.

Issuance of this exemption shall not be deemed to constitute a commitment to issue a construction permit or LWA.

## My notes

FR 2026-17626, 91 FR 55628, notice of issuance. Dockets 50-616 and 50-617; NRC-2026-0265. Exemption from 10 CFR 50.10(c) lets Holtec install and abandon in place specified support-of-excavation walls at Palisades Energy Center, Covert, Michigan, before an LWA. Holtec assumes the risk that the LWA or later CP may be denied. Staff dated the notice August 26; the exemption itself is dated August 28, 2026, and is effective upon issuance.

What it is not: LWA, construction permit, operating license, generation, or delivery. Energy Infrastructure research and the 2026-05-01 microreactors event do not own this Pioneer/Palisades SMR-300 exemption. No exact official Events object. Atomic. HTML page was CAPTCHA-blocked; full text taken from FR raw-text/API.

## Why this matters

The live object is a narrow pre-LWA construction-stage exemption for specified walls, with an express non-commitment on later licenses.