Public Military Compute and Data Center Overlap Map

.md · 2 sections · 15591 characters

Source, owner, and dates

workbench: Research Packages/Data Center Federal Legal Spine 2025-2026/PUBLIC_MILITARY_COMPUTE_AND_DATA_CENTER_OVERLAP_MAP_2026-08-20.md

Canonical source SHA-256: 440fae1fe8347011b8bf1b1aa00e1a24e68128f9d7d30b928d858d29d792b3b9

Served copy SHA-256: 440fae1fe8347011b8bf1b1aa00e1a24e68128f9d7d30b928d858d29d792b3b9

Owner evidence cutoffs: {"data-center-federal-legal-spine": "2026-10-05"}

These are package-level cutoffs, not a claim that this source was rechecked on those dates. Use its own publication and capture dates.

Owners: data-center-federal-legal-spine

Opening section

Section 1 of 2

# Public military compute and data-center overlap map — August 20, 2026

## Controlling ruling

The public overlap is real, but it is not one program and it is not one project clock. It has three distinct layers:

  1. commercial data centers proposed on military land under enhanced-use leasing;
  2. military data-center, cloud and frontier-AI procurements that create or modernize compute demand; and
  3. DOE/NNSA and Navy nuclear-security projects that connect high-density compute to mission-resilient power.

The strongest public physical objects are the Army's conditional selections at Fort Bliss and Dugway and the Air Force's multi-installation lease solicitations. None of the reviewed Army or Air Force records establishes a completed, operating hyperscale campus. The most mature public military compute objects are procurement vehicles and modernization awards, but those do not identify the commercial campus that carries a workload.

This crosswalk uses public official sources only. It does not infer classified facilities, unnamed tenants, private capacity reservations, or a military workload from a developer's general defense business.

## Inclusion rule

An object enters the core map only when an official public source establishes at least one of these joins:

General AI strategy, vendor marketing, classified-program speculation and military energy projects with no public data-center or compute join remain outside the core ledger.

## The three-layer public project map

Layer Public object Current public state What the military join actually is What it does not prove
Military land Fort Bliss, Texas / Carlyle Army conditional selection; exclusive negotiations under 10 U.S.C. §2667; about 1,384 acres; projected IOC FY2027. Commercial developer would finance, build, operate, maintain and decommission on non-excess Army land. Army expressly says the deal is not final. No executed lease, dedicated Army workload, permits, construction or IOC is established. Army
Military land Dugway Proving Ground, Utah / CyrusOne Army conditional selection; exclusive negotiations under 10 U.S.C. §2667; about 1,201 acres; projected IOC FY2029. Same enhanced-use-lease model on Army land. Selection and an IOC target are not an executed lease or operating campus. Army
Military land Arnold, Davis-Monthan, Edwards, JB McGuire-Dix-Lakehurst and Robins Closed Air Force request for lease proposals for EO 14318 “Qualifying Projects”: greater than 100 MW new load and at least $500 million. Air Force offered installation parcels for commercial AI data centers and sought fair-market lease consideration; it reserved first refusal on proposed on-site generation. The multi-site solicitation is not a selection or lease. Arnold received no proposal; no final public award was located for the other four sites. Air Force opportunities; Arnold bounded return
Military land JBER, Eielson AFB and Clear SFS, Alaska Air Force solicitation AFCEC-26-R-0006; offers were due May 29, 2026; later public history showed solicitation updates through July 14. Private commercial use of one or more parcels on active installations through 10 U.S.C. §2667. The government stated that its purchase of data-center services or power was neither required nor guaranteed and would need separate contracts. No public final selection or lease was located. SAM.gov
Military compute DISA Cloud Instance data-center modernization / Hewlett Packard Enterprise $931 million other transaction agreement announced November 20, 2025. Modernizes DISA data centers and adds global hybrid/multi-cloud capacity for mission partners; DISA says it complements JWCC. The public announcement does not identify every site, a new hyperscale campus, construction quantities, accepted capacity or a commercial tenant. DOD CIO
Military cloud Joint Warfighting Cloud Capability / AWS, Google, Microsoft and Oracle Four multiple-award IDIQ contracts announced December 12, 2022; public vehicle ceiling described as $9 billion. Lets military users order commercial cloud services across unclassified, secret and top-secret levels, from the continental United States to the tactical edge. A shared ceiling is not an obligation or vendor revenue; the awards do not prove a new named physical data center, a task order, migration, acceptance or operation. DOD CIO
Military AI workload CDAO frontier-AI prototype OTAs / OpenAI, Google, Anthropic and AIQ Phase Four public prototype agreements, each stated at a value of $200 million, for warfighting and enterprise use cases; the award notices reported about $2 million obligated at award for each. Public demand signal for frontier-model development and evaluation in national-security workflows. Agreement value is not total spend; the notices do not name a training data center, power source, capacity reservation, deployment or accepted operational capability. OpenAI award; Google, Anthropic and AIQ Phase awards
National-security federal land Savannah River Site, South Carolina / Amentum NNSA selected Amentum on July 20, 2026 to negotiate a phased lease for a proposed 1 GW data center and about 2 GW of on-site generation, initially gas and later nuclear. The site supports NNSA national-security missions; the public project expressly invokes national security and EO 14299. SRS is a DOE/NNSA site, not a DOD installation. NNSA says the selection is not a final lease award; permitting, safety, security and federal approvals remain. NNSA
Enacted military energy/compute bridge FY2026 NDAA, P.L. 119-60 §321 Enacted December 18, 2025; requires Navy initiation of a ten-year nuclear-energy pilot at one or more naval installations by December 18, 2026. Installation selection may consider data-center co-location; the first report is due within 30 days after pilot initiation. The statute does not itself select a base, reactor, developer or data center, and does not supply a lease, license, permit or operating authority. Public Law 119-60
Enacted military planning FY2026 NDAA, P.L. 119-60 §1531 Enacted roadmap duty; first update due March 1, 2027, followed by triennial updates through 2033. Requires installation-specific estimates for footprint, electricity, water, community effects, mitigation and resilience for military-installation data centers built or expanded. Reporting is not project authorization, a PUC/FERC cost-allocation decision, an environmental permit or proof that construction occurred. Public Law 119-60
Executive national-security bridge EO 14299 Operative direction signed May 23, 2025. Directs an Army nuclear-energy program of record and a reactor operating at a domestic military installation by September 30, 2028; directs DOE to initiate critical-defense-facility designation for qualifying AI data centers at or coordinated with DOE facilities. The order is not a named data-center designation, base selection, reactor authorization or construction record. White House

## What is genuinely overlapping

### 1. Federal real estate is becoming a commercial capacity lane

The Army and Air Force objects are not ordinary military construction. They use 10 U.S.C. §2667 to expose underused, non-excess installation land to privately financed commercial development. That makes the installation the land host, not automatically the customer, tenant, utility or permitting authority for the whole project.

The Alaska solicitation is the cleanest firewall: even on active military land, government purchase of data-center services or power is optional and would require a separate contract. A ground lease and a workload award therefore cannot be joined without the missing service or power instrument.

### 2. Military demand is visible before its physical footprint is

JWCC, the CDAO frontier-AI agreements and DISA's Cloud Instance initiative show real public demand for classified cloud, hybrid hosting and model capability. Their public records usually identify the vehicle, vendor, ceiling or agreement value, initial obligation and broad performance geography—not the commercial facility, megawatts, water source or transmission path serving the work.

This makes the demand-side military clock more mature than the public siting clock, but it does not permit a one-to-one facility attribution.

### 3. Power resilience is the legal bridge

EO 14299 and FY2026 NDAA §321 connect advanced nuclear power, military installations and possible data-center co-location. Savannah River shows the same architecture at the DOE/NNSA edge: a very large commercial data center, dedicated generation and a national-security campus. The correct classification is national-security federal land, not “military base data center.”

No reviewed public object establishes that the Savannah River project, the Army enhanced-use-lease projects, the Air Force solicitations and the Navy pilot are one coordinated build program.

### 4. The ordinary outside gates remain

A 10 U.S.C. §2667 lease path does not by itself resolve:

The data-center “war” can therefore reach a military-hosted commercial project at the grid edge, environmental-permit edge and public-cost edge even when local zoning authority is altered by federal land status.

## Clocks that must never be collapsed

MILITARY-LAND PROJECT
site offered -> proposal -> conditional selection -> executed lease
-> environmental and utility approvals -> construction -> IOC / operation

MILITARY COMPUTE PROCUREMENT
vehicle or prototype agreement -> task order / obligation -> deployment
-> acceptance -> migrated or operating workload

NUCLEAR / MISSION-POWER PROJECT
directive or pilot -> named site and technology -> authorization and fuel
-> construction -> criticality -> power delivery -> data-center service

An object on one line cannot promote an object on another line. In particular:

Public watch objects

Section 2 of 2

## Public watch objects

Object Next document that would change the state Primary public surface
Fort Bliss / Dugway Executed enhanced-use lease; project NEPA/realty decision; interconnection/service agreement; construction notice. Army; installation pages; SAM.gov; federal NEPA notices.
Air Force five-installation solicitation Named selection or no-selection notice for Davis-Monthan, Edwards, JBMDL and Robins; executed lease. AFCEC opportunities; SAM.gov; installation releases.
Air Force Alaska solicitation Named potential lessee or cancellation; executed ground lease; any separate government data-center-service or power contract. SAM.gov AFCEC-26-R-0006; AFCEC.
DISA Cloud Instance Delivery/task milestones, named modernization sites, accepted capacity and obligated amount. DOD CIO; DISA; USAspending/FPDS where public.
JWCC Vendor-specific task order, obligation, deployment and acceptance record. DOD contracts; DISA; USAspending/FPDS where public.
Frontier-AI OTAs Prototype completion, acceptance, production follow-on and actual obligation. DOD contract announcements; CDAO/DIU.
Navy §321 pilot Public initiation notice, named installation/reactor, first report or contract. Navy; congressional reports; SAM.gov; federal environmental notices.
Savannah River / Amentum Executed phased lease, safety/security approvals, environmental permits and power/interconnection instruments. NNSA/DOE; federal permitting pages; South Carolina utility/environmental agencies.
EO 14299 designation lane Public critical-defense-facility designation naming a data center or DOE-coordinated site. DOE/NNSA; White House; Federal Register.

## Explicit exclusions

## Research posture

This is a bounded public-project crosswalk, not a census of military IT, base energy or classified infrastructure. It preserves the existing federal legal registry's object states and joins them to the prior Military Modernization package only at public, named interfaces. It is pending workbench research and not live-vault authority.

Prior public architecture context: Military Command and Data Control Stack and Military Modernization Research Package.