.md · 1 sections · 6146 characters
workbench: Research Packages/AI-Enabled Turbine Asset Management and US Power Buildout 2025-2026/FORWARD_WATCHBOARD.md
Canonical source SHA-256: 63c1b387954715c17f77ecfe3b0f854ec0089d99d6c16dde747ba50c6c3701ee
Served copy SHA-256: 63c1b387954715c17f77ecfe3b0f854ec0089d99d6c16dde747ba50c6c3701ee
Owner evidence cutoffs: {"ai-turbine-asset-management-power-buildout": "2026-08-09"}
These are package-level cutoffs, not a claim that this source was rechecked on those dates. Use its own publication and capture dates.
Owners: ai-turbine-asset-management-power-buildout
Section 1 of 1
This board is a research radar, not a vault watch calendar. It keeps the next observable state changes and the evidence that would weaken the package's current thesis.
| Lane | Primary surface | Trigger to record | Falsifier / caution |
|---|---|---|---|
| National operating fleet | EIA-860M monthly releases | Unit status changes from planned/construction to operating; revised COD; cancellation or retirement | Never call gross “actual additions” all greenfield without checking uprates and corrections. |
| GE Vernova supply clock | Quarterly results, 10-Q/10-K, investor transcripts | Reservation-to-order conversions, backlog MW, shipments, factory throughput, service backlog | Reservations stall, cancellations rise, or deliveries move later. |
| Siemens Energy supply clock | Quarterly results and analyst presentation | Commitment MW, bookings, Charlotte/Tampa/Winston-Salem factory milestones, Gas Services backlog | Commitment measure changes definition or U.S. share is not disclosed. |
| MHI supply clock | Quarterly/fiscal results | Large-frame unit bookings, North American share, Takasago/Savannah capacity and delivery state | Global unit count cannot be allocated to U.S. projects. |
| NRG Texas Energy Fund | NRG results and PUCT records | Cedar Bayou 5 / Greens Bayou 6 construction milestones and COD; Wharton performance-grant test | “On time” changes; operating capacity differs from nameplate or schedule. |
| Georgia Power | Georgia PSC dockets and owner construction updates | Yates unit CODs; Wansley mechanical completion and COD | Equipment delivery is mistaken for operation. |
| Duke Cayuga | IURC records and Duke updates | Construction milestones; 2029/2030 unit CODs | Coal-unit disposition and gas-unit construction are collapsed. |
| Entergy Louisiana / Meta | LPSC dockets U-37882 and related construction filings | Each approval, notice to proceed, turbine delivery and individual COD | Contract funding claim is confused with cash already spent or every facility already approved. |
| Kilby | TCEQ permit docket, Chevron/Microsoft/GE filings | Final investment decision, final permits, notice to proceed, first turbine delivery, first power | PPA or air-permit draft is promoted to construction or 2.67 GW operation. |
Promote a technology state only when a primary record identifies the owner, asset or fleet, use case, operating state and authority boundary.
| Technology lane | Confirmation trigger | Falsifier / unresolved question |
|---|---|---|
| APM / remote monitoring | Named project contract or owner deployment; units and functions stated | OEM capability page is the only source; owner adoption remains unknown. |
| EAM / CMMS agent | Named operator says the feature is in production and identifies whether it drafts, recommends, approves or executes | Product release alone; no controlled-work or audit evidence. |
| Digital twin | Represented asset, purpose, configuration, validation period, error criteria and operational decision named | “Digital twin” used as an unbounded label. |
| Predictive maintenance | Prospective validation against as-found condition; false-positive/negative rates; changed work or outage state | Only retrospective success case or avoided-cost estimate. |
| Robotic inspection | Named site/fleet deployment; sensor modality; human review and work-order handoff stated | Demonstration or manufacturing QA generalized to field repair. |
| Closed-loop optimization | Exact manipulated variable, control period, safety envelope and fallback stated | Marketing says “autonomous” without control-authority detail. |
| Unattended plant operation | Regulator/inspection authority record, hazard analysis, abnormal-condition evidence and sustained operating history | One bounded test generalized to the fleet. |
| General agent in OT | Independent or government evaluation under dynamic fault and adversarial conditions; role-based authority and kill path | Lab benchmark or natural-language fluency treated as operating competence. |
## 3. Questions worth following
This package is ready for selective vault promotion only after human review. The strongest candidate landing is a concise factual spine linking:
Do not promote vendor benefit figures, speculative project capacity, a new watch date or a master narrative without a separate source check and explicit human choice.