workbench: Research Packages/Permanent Magnets/PERMANENT_MAGNET_TRANSITION_TIMELINE.md
Canonical source SHA-256: e787803918353e971c7a578a36ca52f9786ce2a1dc43748e453ba47f80de42d3
Served copy SHA-256: e787803918353e971c7a578a36ca52f9786ce2a1dc43748e453ba47f80de42d3
Owner evidence cutoffs: {"permanent-magnets": "2026-07-22"}
These are package-level cutoffs, not a claim that this source was rechecked on those dates. Use its own publication and capture dates.
Owners: permanent-magnets
Section 1 of 1
# Permanent-magnet transition timeline
Cutoff: 2026-07-22
Clock rule: announcement, legal instrument, financing close, construction, commissioning, qualification, commercial shipment and sustained output are separate events.
| Date | Clock | Event | Controlled status / limit | Source |
|---|---|---|---|---|
| 2023 | operating | Noveon reports commercial sales from San Marcos | establishes pre-2025 U.S. production; does not establish 2,000-tpa output | Noveon-hosted report |
| 2024 | operating | MP Independence begins commercial rare-earth metal production | metal, not yet finished-magnet commercial supply | MP 10X release |
| 2024 | operating | Energy Fuels begins commercial separated NdPr production at White Mesa | midstream oxide output, not magnets | Energy Fuels 10-K |
| 2025-02-03 | contract | Nidec and Noveon announce five-year binding offtake with potential for more than 1,000 total tonnes, deliveries beginning 2025 | contract ceiling is not delivered volume | agreement |
| 2025-03-20 | legal/policy | EO 14241 treats permanent magnets as derivative mineral products and activates DPA/financing/permitting posture | policy authority; project execution remains separate | Federal Register |
| 2025-04-04 | export-control legal | China imposes licenses on seven medium/heavy rare-earth families and specified related materials | active licensing; not a blanket ban | MOFCOM No. 18 |
| 2025-04-15 | investigation | White House orders Section 232 investigation of processed critical minerals and derivative products | investigation opened; no tariff automatically imposed | order |
| 2025-07 | shipment | Noveon begins GM magnet deliveries | named commercial shipment | GM/Noveon |
| 2025-07 | transaction | MP and DoD execute public-private package | equity/warrant, price floor, HREE finance and 10X outlet support have separate conditions | MP/DoD |
| 2025-07 | contract | Apple and MP announce $500m recycled-magnet partnership | $200m prepayment and 2027 supply target; no 2025 Apple magnet deliveries implied | Apple/MP |
| 2025-08 | shipment | Noveon begins monthly ABB deliveries | named commercial supply; end-2026 ramp remains future | ABB/Noveon |
| 2025-09-19 | facility opening | Neo opens Narva, Estonia magnet plant | opening/sample state; 2026 mass-production output needs verification | Neo Estonia |
| 2025-10-09 | export-control announcement | China announces broader rare-earth and technology controls | later suspended; keep separate from April rules | SCIO explanation |
| 2025-11-03 | preliminary finance | Commerce announces proposed $50m Vulcan support; OSC announces conditional $620m Vulcan and $80m ReElement loans later in November | conditional/preliminary, not cash received | NIST; OSC |
| 2025-11-10 | export-control suspension | broader October controls suspended until 2026-11-10 | April 2025 controls remain | SCIO |
| 2025-12-12 | shipment | eVAC ships first Sumter commercial magnets | first shipment; not proof of Q1 2026 2,000-tpa run rate | eVAC |
| 2025-12 | operating | MP produces first NdFeB magnets on commercial equipment | commercial-scale equipment milestone; 2026 GM ramp is separate | MP results |
| 2026-01-14 | Section 232 remedy | Proclamation 11001 finds PCMDP imports threaten national security and directs negotiations, including price-floor concepts | 180-day negotiating milestone ran to mid-July; no later public remedy was located by cutoff | proclamation |
| 2026-01-19 | private finance | Noveon closes $215m Series C | financing, not production | Noveon |
| 2026-02-02 | reserve finance | EXIM approves Project Vault loan authorization of up to $10bn, alongside approximately $2bn described private capital | public loan + private capital; do not call the entire $12bn a federal reserve appropriation | EXIM |
| 2026-02-26 | site/capacity | MP selects Northlake for 10X | planned; commissioning targeted 2028 | MP |
| 2026-03-26 | commissioning | USAR commissions Stillwater Phase 1a | commissioning; customer shipment and year-end run rate remain open | USAR |
| 2026-04-19 | merger agreement | USAR signs agreement to acquire Serra Verde | proposed/signed; expected Q3 close subject to conditions | SEC 8-K |
| 2026-05 | diplomacy | U.S.–China fact sheet says China will address shortages/restrictions in several critical-mineral lanes | commitment, not proof that every license or shipment issue cleared | White House |
| 2026-06-03 | final finance agreement | Commerce finalizes up to $277m incentives and up to $1.3bn loan for USAR | final agreement; milestone disbursement and build remain separate | NIST |
| 2026-06-18 | conditional finance | OSC signs $725m conditional Energy Fuels loan commitment | no final disbursement implied | OSC |
| 2026-07-20 | sourcing/qualification legal | White House orders defense critical-material supply-chain mapping, qualification acceleration and waiver restriction | active order; Jan. 1, 2027 and rulemaking clocks ahead | White House |
| Target | Observable | What it would prove | What it would not prove |
|---|---|---|---|
| 2026 Q3 | USAR–Serra Verde transaction close | legal consolidation | projected 2027 output or successful integration |
| 2026 Q4 | USAR 600-tpa Stillwater run-rate claim | ramp progress if supported by tonnes and shipments | 10,000-tpa future platform |
| 2026-11-10 | scheduled end of China October-control suspension | whether broader controls reactivate, extend or change | status of April controls, which already operate separately |
| 2027-01-01 | defense waiver restriction begins | change in contractor sourcing/mitigation practice | instant availability of qualified domestic parts |
| 2027 Q1 | USAR Phase 1b 1,200-tpa target | expanded Stillwater line if verified | feedstock security or customer acceptance |
| 2027 | Apple–MP supply start; Iluka commissioning; Noveon/Kangwon target | individual contract/project progress | aggregate Western independence |
| 2028 | MP 10X commissioning; Round Top commercial target | physical transition into new capacity | stable yield/nameplate/customer-qualified output |
| 2029–2030 | multiple 10,000-tpa projects | whether announced Western nameplate becomes real | profitable operation without state support |