Permanent-magnet transition timeline

.md · 1 sections · 9527 characters

Source, owner, and dates

workbench: Research Packages/Permanent Magnets/PERMANENT_MAGNET_TRANSITION_TIMELINE.md

Canonical source SHA-256: e787803918353e971c7a578a36ca52f9786ce2a1dc43748e453ba47f80de42d3

Served copy SHA-256: e787803918353e971c7a578a36ca52f9786ce2a1dc43748e453ba47f80de42d3

Owner evidence cutoffs: {"permanent-magnets": "2026-07-22"}

These are package-level cutoffs, not a claim that this source was rechecked on those dates. Use its own publication and capture dates.

Owners: permanent-magnets

Permanent-magnet transition timeline

Section 1 of 1

# Permanent-magnet transition timeline

Cutoff: 2026-07-22
Clock rule: announcement, legal instrument, financing close, construction, commissioning, qualification, commercial shipment and sustained output are separate events.

## Factual spine

Date Clock Event Controlled status / limit Source
2023 operating Noveon reports commercial sales from San Marcos establishes pre-2025 U.S. production; does not establish 2,000-tpa output Noveon-hosted report
2024 operating MP Independence begins commercial rare-earth metal production metal, not yet finished-magnet commercial supply MP 10X release
2024 operating Energy Fuels begins commercial separated NdPr production at White Mesa midstream oxide output, not magnets Energy Fuels 10-K
2025-02-03 contract Nidec and Noveon announce five-year binding offtake with potential for more than 1,000 total tonnes, deliveries beginning 2025 contract ceiling is not delivered volume agreement
2025-03-20 legal/policy EO 14241 treats permanent magnets as derivative mineral products and activates DPA/financing/permitting posture policy authority; project execution remains separate Federal Register
2025-04-04 export-control legal China imposes licenses on seven medium/heavy rare-earth families and specified related materials active licensing; not a blanket ban MOFCOM No. 18
2025-04-15 investigation White House orders Section 232 investigation of processed critical minerals and derivative products investigation opened; no tariff automatically imposed order
2025-07 shipment Noveon begins GM magnet deliveries named commercial shipment GM/Noveon
2025-07 transaction MP and DoD execute public-private package equity/warrant, price floor, HREE finance and 10X outlet support have separate conditions MP/DoD
2025-07 contract Apple and MP announce $500m recycled-magnet partnership $200m prepayment and 2027 supply target; no 2025 Apple magnet deliveries implied Apple/MP
2025-08 shipment Noveon begins monthly ABB deliveries named commercial supply; end-2026 ramp remains future ABB/Noveon
2025-09-19 facility opening Neo opens Narva, Estonia magnet plant opening/sample state; 2026 mass-production output needs verification Neo Estonia
2025-10-09 export-control announcement China announces broader rare-earth and technology controls later suspended; keep separate from April rules SCIO explanation
2025-11-03 preliminary finance Commerce announces proposed $50m Vulcan support; OSC announces conditional $620m Vulcan and $80m ReElement loans later in November conditional/preliminary, not cash received NIST; OSC
2025-11-10 export-control suspension broader October controls suspended until 2026-11-10 April 2025 controls remain SCIO
2025-12-12 shipment eVAC ships first Sumter commercial magnets first shipment; not proof of Q1 2026 2,000-tpa run rate eVAC
2025-12 operating MP produces first NdFeB magnets on commercial equipment commercial-scale equipment milestone; 2026 GM ramp is separate MP results
2026-01-14 Section 232 remedy Proclamation 11001 finds PCMDP imports threaten national security and directs negotiations, including price-floor concepts 180-day negotiating milestone ran to mid-July; no later public remedy was located by cutoff proclamation
2026-01-19 private finance Noveon closes $215m Series C financing, not production Noveon
2026-02-02 reserve finance EXIM approves Project Vault loan authorization of up to $10bn, alongside approximately $2bn described private capital public loan + private capital; do not call the entire $12bn a federal reserve appropriation EXIM
2026-02-26 site/capacity MP selects Northlake for 10X planned; commissioning targeted 2028 MP
2026-03-26 commissioning USAR commissions Stillwater Phase 1a commissioning; customer shipment and year-end run rate remain open USAR
2026-04-19 merger agreement USAR signs agreement to acquire Serra Verde proposed/signed; expected Q3 close subject to conditions SEC 8-K
2026-05 diplomacy U.S.–China fact sheet says China will address shortages/restrictions in several critical-mineral lanes commitment, not proof that every license or shipment issue cleared White House
2026-06-03 final finance agreement Commerce finalizes up to $277m incentives and up to $1.3bn loan for USAR final agreement; milestone disbursement and build remain separate NIST
2026-06-18 conditional finance OSC signs $725m conditional Energy Fuels loan commitment no final disbursement implied OSC
2026-07-20 sourcing/qualification legal White House orders defense critical-material supply-chain mapping, qualification acceleration and waiver restriction active order; Jan. 1, 2027 and rulemaking clocks ahead White House

## Forward clocks

Target Observable What it would prove What it would not prove
2026 Q3 USAR–Serra Verde transaction close legal consolidation projected 2027 output or successful integration
2026 Q4 USAR 600-tpa Stillwater run-rate claim ramp progress if supported by tonnes and shipments 10,000-tpa future platform
2026-11-10 scheduled end of China October-control suspension whether broader controls reactivate, extend or change status of April controls, which already operate separately
2027-01-01 defense waiver restriction begins change in contractor sourcing/mitigation practice instant availability of qualified domestic parts
2027 Q1 USAR Phase 1b 1,200-tpa target expanded Stillwater line if verified feedstock security or customer acceptance
2027 Apple–MP supply start; Iluka commissioning; Noveon/Kangwon target individual contract/project progress aggregate Western independence
2028 MP 10X commissioning; Round Top commercial target physical transition into new capacity stable yield/nameplate/customer-qualified output
2029–2030 multiple 10,000-tpa projects whether announced Western nameplate becomes real profitable operation without state support