EO 14318 Implementation Return Audit

.md · 2 sections · 14821 characters

Source, owner, and dates

workbench: Research Packages/Data Center Federal Legal Spine 2025-2026/EO_14318_IMPLEMENTATION_RETURN_AUDIT_2026-08-20.md

Canonical source SHA-256: 645dd2857950a9c21cfb60d6d21f6afd89f5a311ba19db6cb67011d92fe0b241

Served copy SHA-256: 645dd2857950a9c21cfb60d6d21f6afd89f5a311ba19db6cb67011d92fe0b241

Owner evidence cutoffs: {"data-center-federal-legal-spine": "2026-10-05"}

These are package-level cutoffs, not a claim that this source was rechecked on those dates. Use its own publication and capture dates.

Owners: data-center-federal-legal-spine

Opening section

Section 1 of 2

# EO 14318 implementation return audit — August 20, 2026

## Audit rule

An executive direction is recorded separately from the agency object it asks for. A press release is not upgraded into a lease, permit, award or final rule unless the official source establishes that exact state.

## Directive-to-return matrix

EO lane Directive / clock Public return located Legal or maturity state Firewall
§3 Commerce/OSTP finance Commerce, with OSTP, launch an initiative for financial support; agencies inventory existing support to OSTP. No express deadline. OSTP January 2026 retrospective says the order “launches” support. March 20 Commerce/DOE Portsmouth announcement links $33.3B of planned Japanese-backed generation investment to the U.S.–Japan agreement. Retrospective and project/investment announcement. No consolidated §3 initiative, inventory, federal award, loan/guarantee, grant, tax incentive or offtake located.
§5 categorical exclusions Agencies submit existing CE inventories to CEQ within 10 days: Aug. 2, 2025; identify possible new or adopted CEs. General agency NEPA procedure changes; CEQ April 9, 2026 CE guidance; project-specific DOE CX determinations. Procedures, nonbinding guidance and named project/action CXs. No public compiled EO inventory or newly titled cross-government data-center CE located. Publication was not expressly required.
§6 FAST-41 FPISC may post Qualifying Projects for transparency; 30-day clocks attach after specified agency notification. QTS Richmond DC5 and PORTS Technology Campus are FAST-41 covered projects. Statutory covered-project coordination, both in progress. No EO-specific transparency posting, transition record or project-specific Executive Director determination located. Coverage is not a permit.
§7 EPA regulations/guidance Develop/modify relevant CAA, CWA, CERCLA and TSCA instruments; Brownfield/Superfund guidance within 180 days: Jan. 19, 2026. January reuse guidance; TSCA §5 priority workflow; CAA resource hub and interpretive memo; proposed NSR construction rule; WRAP 2.0 work. Guidance, workflow, assistance, interpretation, proposal and future policy work. No omnibus EO-specific final deregulation package, cleanup waiver, blanket CAA exemption or data-center CWA effluent rule.
§7 ESA After federal sites are identified, action agencies initiate ten-year programmatic consultation on common construction activities. No posted EO-specific programmatic consultation or biological opinion located. Public-record gap. Does not prove consultation was not initiated. Project-level ESA duties remain.
§8 Army permits Review NWPs within 180 days: Jan. 19, 2026; determine whether activity-specific permit needed. Final reissued NWPs published Jan. 8, 2026, effective Mar. 15; NWP 39 expressly lists data centers. Final general-permit action. Not a blanket project permit; eligibility, ½-acre loss ceiling, notification, regional/general conditions, ESA and district review remain. Direct EO causation is not stated in the final notice.
§9 Interior land Identify suitable lands and authorize construction under applicable law. BLM Townsite right-of-way approval, Nevada, announced July 20, 2026. Agency decision; BLM register still showed decision/appeal period. Not final unappealable authorization, construction or operation. Public sources differ on acreage.
§9 DOE land Identify suitable DOE land and authorize construction under cited authority. Four-site selection; four solicitations; Portsmouth confirmed lease; Savannah River and Paducah selections; project-specific DOE CX determinations. Multiple site, solicitation, lease, selection and CX states. Each object retains its own clock. Most public pages do not publish the executed realty instrument or full terms.
§9 DOD land Identify suitable installations and use 10 U.S.C. 2667 leases where appropriate. Army conditional selections at Fort Bliss and Dugway; Air Force solicitations at eight installations. Exclusive negotiations and solicitations. Army deal expressly not final; no final Air Force award located; government purchase/use not guaranteed.

## Federal-land object ledger

### DOE

Site/object Date Current public state Exact boundary Official source
Four priority sites: INL, Oak Ridge, Paducah, Savannah River 2025-07-24 Sites selected for future solicitations. Not sponsor selection, lease, permit, finance, construction or operation. DOE
Idaho National Laboratory 2025-09-09 RFA for applicant-funded long-term leases on about 44,000 acres; rolling after initial Nov. 7 date. No official sponsor selection or executed lease located. DOE
Oak Ridge 2025-09-30 Competitive RFP for applicant-funded leases at two sites. No official sponsor selection or executed AI-data-center lease located. DOE
Savannah River 2025-09-30 / 2026-07-20 RFP followed by Amentum selection to negotiate a phased lease for proposed 1 GW data center and about 2 GW generation. DOE expressly says selection is not a final lease award; permits, security/safety review and approvals remain. RFP; selection
Paducah 2025-11-04 / 2026-07-29 RFO followed by Brookfield selection for 1.8 GW campus and NextEra selection for 2 GW gas plus up to 2.6 GW storage, about 785 acres. Partnership/selection announcement; power service agreement remains subject to Kentucky PSC approval; no operating proof. RFO; selection
Portsmouth / PORTS Technology Campus 2025-11-17 / 2026-03-20 DOE CX for a 189-acre lease; DOE later confirms an SB Energy affiliate is leasing federal land and reports groundbreaking. Public release is not full lease text; FAST-41 campus includes adjacent private land; full 10 GW announcement is not proved to lie on DOE land. CX-270875; DOE project return

### DOD and DOI

Site/object Date Current public state Exact boundary Official source
Fort Bliss / Carlyle; Dugway / CyrusOne 2026-03-26 Conditional selections and exclusive Army lease negotiations under 10 U.S.C. 2667. Expressly not final; no executed lease, construction or IOC established. Army
Air Force five-installation RFLP 2025-10-15 onward Competitive long-term lease solicitation at Arnold, Davis-Monthan, Edwards, JB McGuire-Dix-Lakehurst and Robins. Arnold reported no proposal; no final award located for the other sites. Air Force opportunities
Air Force Alaska RFLP 2026-04-10 Solicitation under 10 U.S.C. 2667 for JBER, Eielson and Clear SFS. No public final selection or lease located; government use/power purchase not guaranteed. SAM.gov
Townsite Data Center, Nevada 2026-06-26 decision / 2026-07-20 announcement BLM right-of-way approval; register remained in decision/appeal period. Not final unappealable authorization or operating proof; acreage discrepancy remains unresolved. BLM decision; NEPA register

## FAST-41 object ledger

Project Dashboard state at cutoff Authorizations shown Boundary
QTS Richmond Technology Park Data Center 5 Covered; in progress; estimated completion June 11, 2027; 2 of 4 processes complete. USACE-led federal process. Sponsor used ordinary statutory eligibility; posting does not establish EO notification/designation or final USACE action. Dashboard
PORTS Technology Campus Covered; in progress; estimated completion December 23, 2026; 0 of 4 processes complete on the reviewed page. USACE lead; FWS participating. Coverage does not establish approval, funding or completion. Dashboard

## Environmental return ledger

Object Date/state What changed What did not change Official source
CEQ government-wide NEPA regulation removal Interim final Feb. 25, 2025; final Jan. 8, 2026 Removed binding CEQ-wide regulations; agencies rely on NEPA, agency procedures and guidance. NEPA was not repealed; no data-center CE was created. Final rule PDF
CEQ CE guidance 2026-04-09 Explains creation, revision, adoption and application of CEs. No force/effect of law; not a data-center CE or approval. CEQ
EPA Superfund/Brownfield data-center guidance 2026-01 Screening, reuse compatibility, liability and control reminders. Informational only; no site designation, cleanup waiver, land-use approval or permit. EPA
EPA TSCA §5 priority workflow Submissions from 2025-09-29 Priority handling for documented qualifying-project chemical submissions. No changed substantive standard, PMN waiver, authorization or deadline. EPA
EPA CAA data-center resources Updated 2026-07-17 Consolidated existing CAA permit/program guidance; confirms state/local agencies issue most permits. No permit, exemption or independent law change. EPA
EPA islanded-generator Acid Rain memo Signed 2026-07-16 Fact-dependent interpretation that truly islanded units serving one private consumer generally fall outside ARP definitions. Not a rule/final action; later grid link may trigger ARP; expressly leaves every other CAA program untouched. EPA memo
EPA “Begin Actual Construction” NSR proposal 2026-05-13; comments closed 2026-06-29 Would distinguish specified non-emitting work from construction requiring a major NSR permit first. Proposal only; no final-rule reliance. 91 FR 26958
Army NWP 39 Published 2026-01-08; effective 2026-03-15 Final NWP expressly lists data centers as commercial/institutional development; general ½-acre loss ceiling and PCN. Not blanket coverage; regional/general conditions, district review and ESA remain. 91 FR 768
Project Skye individual-permit notice 2026-06-29; comments closed 2026-07-28 Shows five-center application with about 17.99 wetland acres and 8,115 stream feet remained on individual §404 path. Notice/application is not permit issuance or final environmental finding. USACE

Project-specific DOE categorical-exclusion returns

Section 2 of 2

## Project-specific DOE categorical-exclusion returns

These are decisions about named federal realty, assessment or transmission actions. They do not approve every element of a campus.

CX Date Action established Claim limit
CX-270875 2025-11-17 DOE proposes to lease 189 acres at Portsmouth. CX for lease action, not full campus permit.
CX-270900 2026-02-04 AEP easement for five 138-kV lines, 3.5 miles new ROW plus rebuild. Easement/environmental decision, not energized service.
CX-270956 2026-04-29 Environmental site assessment of the leased Portsmouth Batch 1 property. Assessment activity, not final design or construction approval.
CX-270955 2026-04-29 DOE plans to lease about 188 acres, Paducah Parcel C. Proposed lease action, not sponsor operation.
CX-270971 2026-05-04 DOE plans to lease about 785 acres, Paducah Parcel B. Proposed lease action; later sponsor selection remains a separate object.

Official index: DOE Portsmouth/Paducah CX determinations.

## Revocation chain

EO 14141, signed January 14, 2025, created an earlier federal-site architecture. It was not listed in the January 20 initial rescissions. EO 14318 expressly revoked it on July 23, 2025. Later DOE, Army and Air Force actions cite EO 14318, other current orders and/or independent statutes; they are not automatically classified as fulfillment of EO 14141's expired clocks.

Primary routes: EO 14141, EO 14318.