workbench: Research Packages/FORTRESS America and Military Installation Energy Independence 2026-09-30/PROGRAM_AND_PROJECT_REGISTRY.md
Canonical source SHA-256: c4c6055e095f5e36612cf044079b338b0a373d463836658aeab9b8022194cd74
Served copy SHA-256: c4c6055e095f5e36612cf044079b338b0a373d463836658aeab9b8022194cd74
Owner evidence cutoffs: {"fortress-america-installation-energy-independence": "2026-09-30T23:59:59-04:00"}
These are package-level cutoffs, not a claim that this source was rechecked on those dates. Use its own publication and capture dates.
Owners: fortress-america-installation-energy-independence
Section 1 of 1
# Program and Project Registry
Status: current bounded registry; not an exhaustive site census
Cutoff: 2026-09-30 ET
| Program/project | Owner/operator model | Public state | Load/duration boundary | Next decisive receipt |
|---|---|---|---|---|
| FORTRESS America | central Department program; office directed under USW(A&S) | established |
every major installation; “independent power” undefined | office, charter, site list, technical standard and budget |
| 10 U.S.C. §2920 implementation | Department/services/agencies | statutory_requirement |
each installation's critical-mission energy; 99.9% minimum availability by FY2030 | issued standards, site baselines and compliance evidence |
| Installation Energy Plans | services/installations | planning_system |
installation-specific mission/load/risk | current plan tied to financed projects and tests |
| ERCIP | OSD/services; appropriated Defense-wide MILCON | operating_funding_program |
project-specific mission assurance | project list, award, completion and test |
| Army SCI energy | private developer on Army land; emergency priority by agreement | six_conditional_selections |
solicitation says island within qualifying outage and support installation ≥14 days | executed EUL/PPA, financing close, interconnection and test |
| Army Janus | contractor-owned/operated reactors | five_vendor_site_pairings_selected |
site requirements not equal to full-base load by announcement alone | design/authorization, construction, criticality and power delivery |
| NWS Crane MMR | planned commercial owner/operator; Navy host with Army Janus and department partners | deployment_announced_for_2028 |
critical operations; announcement does not establish full-installation load | executed agreement, authorization, design, construction, criticality and accepted delivery |
| Eielson microreactor | proposed private vendor under long-term service arrangement | notice_of_intent_negotiation |
up to 5 MW to critical infrastructure | final award, NRC licence, construction and operation |
| Project Pele | government prototype/test at INL | prototype_demonstration_path |
technology demonstration, not base service | fueled criticality, output and published test result |
| MCAS Yuma microgrid | utility partnership | operational_publicly_described |
backup capacity for 100% current/projected base requirements | current exercise and readiness result |
| MCAS Miramar microgrid | mixed sources and third-party/system partners | operational_and_exercised |
design description up to 21 days; observed exercise covered mission-critical operations | current endurance/recovery exercise report |
| SUBASE New London microgrid | Navy plant plus first-right access to utility/private fuel-cell park | operational |
essential functions; 10.75 MW CHP plus 7.4 MW fuel cells | current black-start/endurance result |
| Fort McCoy Main Gate microgrid | Army/Xcel partnership | operational_scope_limited |
gate and nearby mission-essential facilities; stated ≥14 days | observed 14-day or recurring exercise result |
| DLA Distribution Sigonella | DLA/NAVFAC tenant-facility system | activated_scope_limited |
DLA facilities; stated up to 14 days on one fuel load | observed endurance and recovery result |
| Next Great American Base | future model-base initiative | announced_design_objective |
completely off commercial grid by announcement | site, authority, plan, budget, construction and operation |
The current estate already contains full-load, critical-load, campus, gate and tenant-facility microgrids plus emerging nuclear and private-generation models. FORTRESS cannot use a single project count as its readiness denominator. The portfolio needs common load, duration and test fields before unlike projects can be compared.