Federal fusion date, time and place ledger, 2020–2035

.md · 3 sections · 33873 characters

Source, owner, and dates

workbench: Research Packages/Federal Science Operating System/FEDERAL_FUSION_DATE_TIME_PLACE_LEDGER_2020-2035.md

Canonical source SHA-256: b4845153a6a27f43e7c2a6e527d4fc1ea5e3bb0c20ca828f8655bd6e02833f68

Served copy SHA-256: b4845153a6a27f43e7c2a6e527d4fc1ea5e3bb0c20ca828f8655bd6e02833f68

Owner evidence cutoffs: {"federal-science-operating-system": "2026-10-12", "federal-fusion-commercialization": "2026-08-15", "genesis-mission": "2026-10-13"}

These are package-level cutoffs, not a claim that this source was rechecked on those dates. Use its own publication and capture dates.

Owners: federal-science-operating-system, federal-fusion-commercialization, genesis-mission

Federal fusion date, time and place ledger, 2020–2035

Section 1 of 3

# Federal fusion date, time and place ledger, 2020–2035

Evidence cutoff: 2026-08-15 17:34:07.266 UTC
Status: current Workbench research; factual clock register
Scope: material U.S. fusion-policy, scientific, regulatory, licensing, publication and forward-target clocks in the Federal Science / fusion bridge
Astrology boundary: this Research file contains factual clocks only. Chart conventions and readiness selections are maintained separately in Chronicle Astrology Files and have no evidence vote.

## Short answer

Only a few fusion objects presently support a genuinely timed chart. The strongest physical clock is NIF's first ignition shot at 1:03:50 a.m. local facility time on December 5, 2022. The strongest federal administrative clock is the fusion proposed rule's 8:45 a.m. Eastern public-inspection filing on February 25, 2026. DOE's August 15 campaign supplies an exact digital publication instant—1:34:04.501 p.m. EDT for the root post—but no source-attested physical posting place.

The June 9 roadmap release is date-only. Exact timestamps found in its webpage and PDF metadata describe page creation, later modification or file production; none is proven to be the public-release instant.

The project-registry extension adds a date-only physical clock for Realta's June 19, 2026 WHAM direct-energy-conversion experiment and exact publication clocks at 7:00 a.m. ET on June 30 for that result and 8:00 a.m. ET on July 15 for its Forge/Hammir site announcement. It also preserves exact Type One publication clocks while keeping their underlying contract, LOI and filing times unresolved. Tennessee's March 11 rule receipt is stamped 10:37 a.m., but the source omits the timezone and therefore does not support an exact-instant chart.

## Governing clock rules

  1. Preserve the object's real clock role. Experiment, announcement, filing, publication, signature, enactment, effectiveness and deadline are separate events even when they concern the same instrument.
  2. Preserve only the precision stated or deterministically recoverable from a primary object. Never manufacture midnight, noon, a timezone or a place as historical fact.
  3. Source place or locus is factual metadata. An institutional headquarters, press-release dateline, project site and online publication origin are not interchangeable.

The D.C.-cast chart convention and chart-readiness overlay are maintained separately in Chronicle Astrology Files at 03 - Astrology/Astrology Files/Mundane Story Overlaps/Federal Fusion Chart Readiness 2020-2035.md. They do not contribute factual evidence to this ledger.

### Durable vocabulary

## Factual clock register

All unknowns below are affirmative research findings: the source was checked and did not establish the missing field. Derived means a transparent calendar or civil-time conversion, not a source-printed value.

Clock ID Object and clock role Source date and time Precision / timezone Source place or locus Status and fact established Boundary / open retrieval Primary source
FUS-LAW-20201227 Energy Act of 2020 milestone-program authorization enacted within P.L. 116-260 2020-12-27; time not publicly stated date; date_only_no_clock Signature place not established in the enrolled law occurred; authorization created Not an appropriation, award or operating program milestone; exact signature time/site unresolved P.L. 116-260
FUS-POL-20220317 White House fusion summit scheduled opening and event window 2022-03-17, 10:00 a.m.–1:00 p.m. ET datetime; opening exact_minute, event bounded_source_window; EDT / America/New_York Physical venue not stated in the official agenda occurred as a scheduled federal policy event; 10:00 a.m. is the advertised opening Actual opening instant and venue require a recording or event record OSTP/DOE agenda
FUS-NIF-20221205 NIF first fusion-ignition shot; physical experiment 2022-12-05, 1:03:50 a.m. local facility time datetime; exact_second; timezone not printed, derived as PST / America/Los_Angeles; derived UTC 09:03:50Z National Ignition Facility, Lawrence Livermore National Laboratory, Livermore, California occurred; physical ignition shot Preserve the derived-zone caveat; do not substitute the December 13 public announcement or treat target gain as facility/grid gain LLNL exact clock
FUS-MILESTONE-SELECT-20230531 DOE selects eight Milestone Program recipients 2023-05-31; time not publicly stated date; date_only_no_clock DOE selection/publication locus not established occurred; funding cohort selected Selection is not an executed agreement, obligation, verification, payment or plant DOE award list
FUS-STRAT-20240606 DOE Fusion Energy Strategy 2024 published; strategy clock 2024-06-06; time not publicly stated date; date_only_no_clock DOE release has Washington, D.C. dateline and identifies a White House event; exact release/event locus and time unresolved occurred; strategy and related funding opportunity announced Strategy publication, event, funding opportunity and later award are distinct clocks DOE strategy release
FUS-MILESTONE-TIA-PUB-20240606 DOE announces all eight Milestone TIAs signed June 3–5 2024-06-06; individual agreements dated within 2024-06-03–05; times not stated announcement date; agreement window; date_only_no_clock / bounded_source_window DOE online publication; signature places unresolved occurred; eight executed program agreements publicly established Announcement is not a milestone review or payment; signature window is not a single event instant DOE strategy and agreement announcement
FUS-LAW-20240709 ADVANCE Act section 205 enacted 2024-07-09; time not publicly stated date; date_only_no_clock Exact signature site not established in the enacted record occurred; fusion definitions amended and NRC rulemaking deadline created Not a completed rule or project license P.L. 118-67
FUS-REALTA-WHAM-20240715 WHAM first plasma; physical experiment 2024-07-15; time not publicly stated date; date_only_no_clock Physical Sciences Laboratory, Stoughton, Wisconsin occurred; first plasma in the 17 T mirror machine Not scientific/engineering gain, electricity or a private power plant UW–Madison
FUS-CFS-LIC-20241024 CFS reports Massachusetts grant of SPARC broad-scope radioactive-materials license 2024-10-24; issuance time not publicly stated in checked release date; date_only_no_clock Massachusetts Agreement-State regulatory object; SPARC site Devens occurred as company-reported license grant Exact agency issuance clock, operative terms, amendments, inspections and first-plasma authorization remain separate CFS license announcement
FUS-NIF-20250407 NIF record-yield shot; physical experiment 2025-04-07, “shortly after 4 a.m.” local facility time datetime; approximate_source; timezone not printed, derived as PDT / America/Los_Angeles NIF, LLNL, Livermore, California occurred; 8.6 MJ yield and target gain 4.13 later reported No exact minute/second; do not normalize “shortly after” to 4:00 a.m.; target gain is not facility/grid gain LLNL shot account
FUS-ASSET-20250527 Secretary Wright visit used as later DOE card-photo provenance 2025-05-27; time not publicly stated date; date_only_no_clock Matter in Extreme Conditions instrument, SLAC National Accelerator Laboratory, Menlo Park, California occurred; identifies the earlier source image Not an August 15 facility event or a fusion-state change SLAC photo record
FUS-CFS-GOOGLE-20250630 CFS/Google 200 MW PPA publicly announced 2025-06-30; signature and publication times not publicly stated date; date_only_no_clock ARC project is proposed in Chesterfield County, Virginia; agreement-signature locus unresolved occurred; company-reported commercial offtake object Not construction, generation, interconnection or delivery CFS announcement
FUS-TYPEONE-PSS-PUB-20250722 Type One/TVA Power Service Shops contracts release; publication clock 2025-07-22, 4:13:40 p.m. EDT; UTC 20:13:40Z datetime; exact_second; America/New_York Online publication; Knoxville dateline is not proof of publication origin occurred; limited fabrication/welding contracts publicly announced Underlying execution times unresolved; not Infinity Two construction Type One release
FUS-TYPEONE-LOI-PUB-20250919 Type One/TVA letter-of-intent release; publication clock 2025-09-19, 8:36:27 p.m. EDT; UTC 2025-09-20T00:36:27Z datetime; exact_second; America/New_York Online publication; Oak Ridge dateline is not proof of publication origin occurred; conditional deployment interest publicly announced LOI signature/issuance time unresolved; not a PPA, TVA Board authorization or plant approval Type One release
FUS-CFS-MAGNET-20250930 CFS reports DOE validation of full-scale SPARC TF magnet milestone and $8M payment 2025-09-30; validation and payment times not stated date; date_only_no_clock CFS/DOE administrative and technical loci unresolved; SPARC at Devens occurred as company-reported DOE verification/payment Not SPARC first plasma, gain or ARC plant performance CFS announcement

Factual clock register (continued)

Section 2 of 3

| FUS-RMAP1-20251016 | Fusion S&T Roadmap Part I public unveiling | 2025-10-16; time not publicly stated | date; date_only_no_clock | DOE release associates the week's Fusion Enterprise events with Washington, D.C.; exact release/event locus unresolved | occurred; first roadmap part published | Not Roadmap Part II, an award or construction authorization | DOE Part I release | | GEN-EO-20251124 | EO 14363 signed/dated; Genesis establishment clock | 2025-11-24; signature time not publicly stated | date; date_only_no_clock | Official text carries “THE WHITE HOUSE”; physical signing location not independently established | occurred; Genesis Mission chartered | Signature, OFR filing and Federal Register publication are separate | Official EO text | | GEN-OFR-20251126 | EO 14363 filed for public inspection | 2025-11-26, 11:15 a.m. ET | datetime; exact_minute; EST / America/New_York; UTC 16:15Z | Office of the Federal Register, Washington, D.C. administrative locus | occurred; public-inspection filing clock | Not the President's signature or the November 28 publication | Official EO notice | | GEN-FR-20251128 | EO 14363 Federal Register publication | 2025-11-28; publication day, no distinct release instant stated | date; date_only_no_clock | Federal Register publication / Washington, D.C. legal locus | occurred; official publication | Not the November 24 establishment/signature clock | Federal Register | | FUS-THEA-DESIGN-20260113 | Thea reports DOE certification/approval of Helios preconceptual design | 2026-01-13; DOE decision and publication times not publicly stated | date; date_only_no_clock | Company online publication; underlying DOE review locus unresolved | occurred as company-reported DOE design milestone | Not an operating Eos/Helios machine, license, site, electricity or standalone DOE action record | Thea release | | FUS-APPROP-20260123 | FY2026 Fusion Energy Sciences appropriation enacted within P.L. 119-74 | 2026-01-23; time not publicly stated | date; date_only_no_clock | Exact signature site not established in the enacted record | occurred; FES account funding enacted | House passage Jan. 8, Senate passage Jan. 15, presentation Jan. 22 and enactment Jan. 23 are separate; FY label is not enactment | P.L. 119-74 | | FUS-LIC-20260129 | Type One / Bull Run initial byproduct-material application reported submitted | 2026-01-29; filing time not public | date; date_only_no_clock | Filing locus unresolved; Nashville is the release dateline; Bull Run near Clinton, Tennessee is the project site | occurred as company-reported initial submission | No TDEC receipt timestamp, completeness finding, disposition, license or operation | Type One release | | FUS-TYPEONE-APP-PUB-20260129 | Type One initial-application announcement; publication clock | 2026-01-29, 9:36 a.m. EST; UTC 14:36Z | datetime; exact_minute; America/New_York | Online publication; Nashville dateline is not proof of publication origin | occurred; exact communications clock for the company-reported submission | Not the filing/receipt instant, completeness, disposition or license | Type One release | | GEN-CHALLENGES-20260212 | DOE publicly announces 26 Genesis challenges | 2026-02-12; publication time not publicly stated | date; date_only_no_clock | Online DOE publication; physical publication origin not established | occurred; challenge set publicly announced | Does not reveal internal submission/review timestamps or prove IOC | DOE announcement | | FUS-NRC-DOC-20260223 | NRC proposed-rule document dated | 2026-02-23; time not applicable/not stated | date; date_only_no_clock | NRC document locus; no physical act established by the document date alone | occurred as the agency document date | Not public inspection, publication, finalization or effectiveness | Official notice text | | FUS-NRC-OFR-20260225 | NRC proposal filed for public inspection | 2026-02-25, 8:45 a.m. ET | datetime; exact_minute; EST / America/New_York; UTC 13:45Z | Office of the Federal Register, Washington, D.C. administrative locus | occurred; exact public-inspection filing | Not NRC adoption, February 26 publication, a final rule or effective rule | GovInfo notice · NARA filing procedure | | FUS-NRC-PUB-20260226 | NRC fusion-machine proposed rule published | 2026-02-26; no distinct publication time stated | date; date_only_no_clock | Federal Register / Washington, D.C. legal-publication locus | occurred; proposed framework opened for comment | Proposal is not final or effective and does not issue a project license | GovInfo notice | | FUS-TN-RULE-FILE-20260311 | Tennessee fusion-rule filing received by Secretary of State | 2026-03-11, 10:37 a.m.; source timezone not stated | datetime; exact_minute text with unresolved zone | Filing form names Division of Publications, Nashville; physical/electronic receipt mode unresolved | occurred; Sequence 03-11-26, Rule IDs 10543–10549 received | No defensible UTC conversion; not the June 9 effective clock or a project license | Tennessee filing | | FUS-CFS-PJM-20260428 | CFS announces ARC/Fall Line PJM interconnection application | 2026-04-28; application/announcement time not publicly stated | date; date_only_no_clock | Proposed plant Chesterfield County, Virginia; PJM receipt locus/time unresolved | occurred; company application publicly established and PJM confirmed fusion among Cycle 1 applicants next day | Not queue validation, study, interconnection agreement, synchronization or export | CFS announcement · PJM confirmation | | FUS-ZAP-DESIGN-20260519 | Zap reports DOE approval of about-50-MWe-net-per-module preconceptual design | 2026-05-19; DOE decision and publication times not publicly stated | date; date_only_no_clock | Company online publication; DOE review locus unresolved | occurred as company-reported DOE design milestone | Not a built module, selected site, license, gain or generated electricity | Zap release | | FUS-NRC-CLOSE-20260527 | NRC proposal comment period closes | 2026-05-27; no universal deadline hour stated | date; date_only_no_clock | Distributed submission routes; 4:15 p.m. Rockville cutoff applies only to hand delivery | occurred; comment-period calendar date reached | Never infer 11:59 p.m.; submission-mode-specific cutoffs must remain separate | GovInfo notice | | FUS-TN-ANN-20260601 | Tennessee announces its June 9 fusion regulations | 2026-06-01, page displays 9:00 a.m.; timezone not stated | datetime; exact_minute text with unresolved zone | TDEC online publication; physical origin not established | occurred; announcement published | Do not assume Central Time or turn Nashville into the online-publication locus | TDEC release | | FUS-XCIMER-PHOENIX-20260603 | Xcimer announces start of Phoenix laser-prototype operations | 2026-06-03; operating-start and publication times not publicly stated | date; date_only_no_clock | Phoenix laser bay, Denver, Colorado | occurred; integrated excimer amplification/compression platform operating above 1 kJ | Not a fusion shot, ignition, gain, heat or electricity | Xcimer release | | GEN-JP-20260604 | U.S.–Japan Genesis partnership publicly announced | 2026-06-04; time not publicly stated | date; date_only_no_clock | DOE online publication; physical release/signing locus not established | occurred; planned five-year partnership announced, subject to appropriations | Not an appropriation, executed project award or operating capability | DOE announcement | | FUS-THEA-TWIN-20260608 | Thea announces Helios digital-twin and AI-surrogate collaboration | 2026-06-08; publication time not publicly stated | date; date_only_no_clock | Distributed company, NVIDIA, Synopsys, Argonne and PPPL design/model work | occurred; named fusion AI/model collaboration established | Not Genesis IOC, DCP operating proof or plant performance | Thea release | | FUS-RMAP2-20260609 | Finalized Fusion S&T Roadmap / Part II publicly released | 2026-06-09; release time not publicly stated | date; date_only_no_clock | DOE body dateline WASHINGTON—; Washington, D.C. is an institutional/dateline anchor, not a proven CMS-device location | occurred; finalized strategy published | No exact public-release time; webpage and PDF metadata clocks below are different objects | DOE release · Roadmap | | FUS-TN-EFF-20260609 | Tennessee Chapter 0400-20-14 becomes effective | 2026-06-09; exact effective time not stated | date; date_only_no_clock | Statewide Tennessee legal effect; no single physical event location | occurred; Agreement State fusion-machine framework effective | Never infer midnight as historical effect; not an issued Bull Run license | TDEC release | | FUS-XCIMER-DESIGN-20260610 | Xcimer reports DOE approval of Athena preconceptual design and roadmap | 2026-06-10; DOE decision and publication times not publicly stated | date; date_only_no_clock | Company online publication; DOE review locus unresolved | occurred as company-reported DOE design milestone | Not Phoenix fusion operation, Vulcan engineering breakeven, a site/license or 400 MWe generation | Xcimer release | | FUS-REALTA-DEC-20260619 | WHAM direct-energy-conversion experiment; physical event | 2026-06-19; experiment time not publicly stated | date; date_only_no_clock | WHAM, Physical Sciences Laboratory, Stoughton, Wisconsin | occurred; multiple amps at about 100 volts converted from plasma kinetic energy | Mostly recovered supplied input power; expressly not net electricity or large-scale conversion of fusion-born power | Realta technical account | | FUS-NIF-20260620 | NIF eleventh ignition; physical experiment | 2026-06-20; shot time not publicly stated | date; date_only_no_clock | NIF, LLNL, Livermore, California | occurred; 7.9 ± 0.4 MJ and target gain about 3.8 reported | Shot ID, time and zone unresolved; target gain is not facility/grid gain | NIF ignition record | | FUS-REALTA-DEC-PUB-20260630 | Realta DEC press-release publication | 2026-06-30, 7:00 a.m. ET; UTC 11:00Z | datetime; exact_minute; EDT / America/New_York | Online publication; physical publication origin not stated | occurred; exact communications clock for the June 19 result | Not the physical experiment time | PRNewswire release | | FUS-REALTA-FORGE-PUB-20260715 | Realta Forge/Hammir site and incentives announcement | 2026-07-15, 8:00 a.m. ET; UTC 12:00Z | datetime; exact_minute; EDT / America/New_York | Project site OM Station, Madison, Wisconsin; online publication origin not stated | occurred; site/incentive plan publicly announced | Not groundbreaking, construction, commissioning or a power-plant site | PRNewswire release · WEDC | | GEN-FUSION-SELECT-20260722 | Genesis project selections include named fusion/DCP work | 2026-07-22; publication time not publicly stated | date; date_only_no_clock | Distributed project portfolio; no single operating locus | occurred; selection for award negotiations | Not an executed OTA/FWP, obligation, platform access, workflow or physical result | DOE release · project list | | FUS-X-20260815 | DOE Energy Without Limits root post; online publication | 2026-08-15, 1:34:04.501 p.m. EDT; UTC 17:34:04.501Z | datetime; exact_second plus milliseconds deterministically derived from X Snowflake ID; America/New_York is display conversion | Online publication; no geo, place or coordinates; physical origin unknown | occurred; official communications activation | Not a new experiment, roadmap, award, facility, license or electricity event; Washington is only the wheel convention, not posting provenance | DOE root post · X Snowflake documentation | | GEN-IOC-20260821 | Genesis IOC-seeking calendar target derived from 270 days after EO date | 2026-08-21; no hour or ceremony stated | conditional; date_only_no_clock; derived calendar date | DOE/national platform; operating locus to be identified by any completion record | scheduled; source directs DOE to seek to demonstrate IOC, subject to appropriations | Not an occurred event or proof that fusion is the selected challenge | EO 14363 | | SCI-PLAN-20261019 | Qualifying-agency implementation plans due; 90-day derived date | 2026-10-19; no hour stated | conditional; date_only_no_clock; derived calendar date | Submission/receiving locus unresolved | scheduled; implementation-plan clock | Verify OMB interpretation, extensions and actual receipt before marking delinquent or complete | NSTM-5 / M-26-16 | | GEN-REPORT-20261124 | First Genesis annual report due | 2026-11-24; no hour stated | conditional; date_only_no_clock; one-year deadline | DOE/White House reporting locus unresolved | scheduled; annual reporting clock | Public release is not guaranteed and would be a separate publication clock | EO 14363 | | FUS-NRC-DEADLINE-20271231 | ADVANCE Act NRC technology-inclusive rulemaking deadline | 2027-12-31; no hour stated | conditional; date_only_no_clock | NRC federal rulemaking / Washington, D.C. legal locus | scheduled; statutory completion deadline | Final-rule adoption, publication and effective date remain separate; Agreement State clocks continue independently | P.L. 118-67 | | FUS-PILOT-2031-2035 | DOE pilot-plants-delivering-electrons target window | 2031–2035; no day/time | conditional; year window; not_applicable_partial_date | Named project/site not yet identified | scheduled target window, not an occurred event | No point chart; wait for a named award, site, build, commissioning, synchronization or metered-delivery event | DOE roadmap |

DOE thread micro-sequence

Section 3 of 3

## DOE thread micro-sequence

The three posts are one atomic communications event anchored to the root post. The reply clocks are preserved for sequence reconstruction, not promoted as three separate campaign launches.

Order / cards X status ID UTC creation Washington display Relationship
Root / cards 1–2 2088680637729316925 2026-08-15T17:34:04.501Z 2026-08-15 1:34:04.501 p.m. EDT Thread root and canonical event clock
Cards 3–4 2088680640149426639 2026-08-15T17:34:05.078Z 2026-08-15 1:34:05.078 p.m. EDT Reply to root; +0.577 seconds
Card 5 2088680649326485551 2026-08-15T17:34:07.266Z 2026-08-15 1:34:07.266 p.m. EDT Reply to post 2; complete chain +2.765 seconds

X's direct syndication created_at fields are whole-second values. The millisecond values above are deterministically decoded from the official 64-bit Snowflake IDs using X's documented epoch. All three official payloads omit geo, place and coordinates.

## Roadmap webpage and file metadata — not the release clock

These exact timestamps are retained because they may help future provenance work. None should replace FUS-RMAP2-20260609 as the public-release record.

Metadata object UTC Washington display Ruling
DOE HTML datePublished / CMS node creation 2026-06-04T20:19:25Z 2026-06-04 4:19:25 p.m. EDT Page preparation/CMS creation; conflicts with visible June 9 release date and is not a defensible release clock
DOE HTML dateModified 2026-06-10T01:44:14Z 2026-06-09 9:44:14 p.m. EDT Exact page-modification clock; may be charted only if explicitly labeled as webpage modification
Current roadmap PDF XMP creation 2026-06-11T15:59:13Z 2026-06-11 11:59:13 a.m. EDT Later file-production clock; not release
Current roadmap PDF XMP modification 2026-06-15T19:11:27Z 2026-06-15 3:11:27 p.m. EDT Later file-revision clock; not release
Current PDF HTTP Last-Modified 2026-06-15T20:19:17Z 2026-06-15 4:19:17 p.m. EDT Server/file metadata; not release

## Astrology boundary

The former chart-readiness overlay is preserved in Chronicle Astrology Files at 03 - Astrology/Astrology Files/Mundane Story Overlaps/Federal Fusion Chart Readiness 2020-2035.md. This Research copy retains only factual clocks, source precision, places, unknowns and retrieval questions.

## Open retrieval queue

  1. NIF shot-log timestamp and identifier for June 20, 2026.
  2. Exact minute/second for the April 7, 2025 NIF shot.
  3. TDEC receipt stamp, filing medium and receiving locus for the January 29 Bull Run application.
  4. Source-stated timezone for the TDEC June 1 page's 9:00 a.m. display.
  5. A primary release timestamp for DOE's June 9 roadmap announcement, if one exists outside current page/file metadata.
  6. Actual opening time and physical/virtual venue for the March 17, 2022 fusion summit.
  7. Exact signature times/sites for P.L. 118-67, P.L. 119-74 and EO 14363.
  8. Named challenge, platform components, users, test, operating locus and exact completion clock for any Genesis IOC claim.
  9. Exact physical-event times for WHAM first plasma and the June 19, 2026 direct-energy-conversion experiment.
  10. Operative Massachusetts SPARC license and exact issuance clock; matching DOE action/decision records and clocks for Thea, Xcimer and Zap's company-reported design approvals.
  11. Source timezone for Tennessee's March 11, 2026 10:37 a.m. rule-filing receipt stamp.
  12. Execution/signature clocks for the TVA PSS contracts and LOI; PJM receipt, validation and later study/agreement clocks for ARC/Fall Line.
  13. TIA amendment, verification, invoice and payment clocks needed to join USAspending obligations/outlays to named technical milestones.

## Promotion and interpretation firewall